Annexure- ‘B’ Amendments to the Bid Identification No.BMC- EED-I/10(EL)/2012-13 Date: 04-02-2013 Sl. 1 Clause No. and Existing Provision Revised/New provision EPC, Schedul e 4 – 2.d Pole A Road Width (m) Illumination level (lux levels) shall be measured using a calibrated lux meter by the following method (Nine point method). The layout of a 9 point measuring grid (for one span) should be as below. The same methodology would be followed for all types of roads. Pole B 1 2 3 4 5 6 7 8 9 Pole A Average Lux Road Width (m) Measure illuminance using a calibrated lux meter at each point. Calculate the average value of measured illuminance at all points. If E1, E2,…, En are illuminance measurements at points 1,2,…., n Average illuminance, Eav = E1+E2 +E3 + …..+ En X correction factor N Pole B A1 C1 B1 C2 D C4 A2 C3 B2 Average Lux Avg. illuminance, Eav = (A1+A2+B1+B2)/16 + (C1+C2+C3+C4)/8 + D/4 Sl. 2 EPC, Schedul e3 Clause No. and Existing Provision Revised/New provision New Clause [To be inserted after Clause (d)] New Clause (e) – Accounting for voltage variations during baseline study; 1. In the event if the input voltage is not found to be within the acceptable range for any particular switching point(s) by either of the Parties, such Party may request for repeat of the TPEA exercise. Such request for the repeat of the TPEA for specific switching point(s) shall have to be completed within the timelines as specified for TPEA in the contract. 2. During the initial survey phase, if the Contractor feels that there is substantial voltage ( + or – 25 %) drop at the tail end of street lighting system covered under any particular switching point(s), due to infrastructure deficiencies, which is substantially deflating the baseline consumption norm, it may request BMC to complete the impending infrastructure works prior to the TPEA exercise. Such issues may also be highlighted or flagged by the Contractor during the TPEA exercise for specific switching point(s), for review by the IEA 3 EPC – Article 4 New Clause [To be inserted after Clause 4.5] New Clause (4.6) - Non-availability of power on any Switching Point(s) The BMC shall be obligated to take up the matters of lack of quality and continuity of supply of power with CESU on any particular switching point(s) in case the same is not found to be acceptable by the Contractor. Sl. 4 Clause No. and Existing Provision EPC – Article 1 New Definition Revised/New provision Book Value of Assets – Definition Book Value of the equipment shall mean original cost of equipment as reduced due to depreciation as per Companies for the respective equipment (from the date of installation to termination date).The same shall have to be certified reputable auditor and BMC. 5 6 EPC – Article 4: Article 4.4.1 On commencement of Phase 4 (as defined in Article 6), BMC shall conduct, with the assistance of the Independent Energy Auditor, lux level measurements on five percent (5%) randomly selected street lighting points on a half yearly basis. The Contractor shall be required to participate in the lux level measurements along with BMC and the Independent Energy Auditor. In the event the lux levels are found to be below the applicable standards as specified in Schedule 2, the Contractor shall be required to make payments to BMC for the amounts as determined under Article Error! Reference source not found.. RFP, Schedul e 3, Para 4 The consortium shall be required to incorporate a Project Company, per the provisions of the RFP, within fifteen (15) days of BMC's issuance of the letter of intent, provided that it has not incorporated a Project Company before the submission of its Bid. the Act the by Changes with respect to Sampling Methodology for Lux Level Surveys On commencement of Phase 4 (as defined in Article 6), BMC shall conduct, with the assistance of the Independent Energy Auditor, lux level measurements on five percent (5%) randomly selected street lighting points on a half yearly basis. The sample selection of points for the LUX level measurements should be spread across at least 50% of the switching points comprising the total project area and adequately cover different types of roads. The Contractor shall be required to participate in the lux level measurements along with BMC and the Independent Energy Auditor. In the event the lux levels are found to be below the applicable standards as specified in Schedule 2, the Contractor shall be required to make payments to BMC for the amounts as determined under Article Error! Reference source not found.. The consortium shall be required to incorporate a Project Company, per the provisions of the RFP, within thirty (30) days of BMC's issuance of the letter of intent, provided that it has not incorporated a Project Company before the submission of its Bid. Sl. Clause No. and Existing Provision Revised/New provision 7 EPC – Article 25 The Contractor shall at all times, as may be applicable, obtain, maintain and renew those insurance covers required in relation to people, equipment, systems as well as third party damages in accordance with good industry practice. In particular, the Contractor shall maintain an insurance coverage against the risk of damage by fire or otherwise of Contractor-owned and installed equipment and systems until the title to the equipment and systems passes on to BMC upon expiry of the Term. The Contractor shall at all times, as may be applicable, obtain, maintain and renew those insurance covers required in relation to people, equipment, systems as well as third party damages in accordance with good industry practice. In particular, the Contractor shall maintain an insurance coverage against the risk of damage by fire or otherwise (including vandalism) of Contractor-owned and installed equipment and systems until the title to the equipment and systems passes on to BMC upon expiry of the Term. In relation to damage caused by acts of vandalism, should the premium payable by the Contractor pursuant to this Article 25 increase due to a large number of such acts, BMC shall bear the costs of such increase in insurance premium by refunding the Contractor such amount. 8 EPCArticle 10: Article 10.1 (d) EPCArticle 27.5 Without BMC's written permission, the Contractor shall not engage in any related activities in the city of Bhubaneswar that may impinge upon this Project, other than the Services Without BMC's written permission, the Contractor shall not engage in any related activities in the Project Area that may impinge upon this Project, other than the Services. 9 New Article 27.5.2 for termination payments in case Deleted existing Article 27.5.2 and replace by Article below: of Force Majeure In case of termination of the Contract at any time during Phase 3 or Phase 4 due to a Force Majeure Event as specified in Article 20, BMC shall pay the Contractor [one hundred percent (100%)] of the book value for all the equipment constructed or systems installed up to the Termination Date, as duly certified by a reputable auditor and approved by BMC. In case of termination arising on account of a Force Majeure Event during Phase 1 or Phase 2, neither Party shall be liable for any payments to the other Party. Sl. Clause No. and Existing Provision Revised/New provision 10 EPCArticle 27.5 "statutory auditor" "reputable auditor" 11 EPCSchedul e 6: Trust & Retentio n Account : Para 3.2 The remaining twenty-five per cent (25%) of the amount of the invoice shall be paid by the Escrow Agent upon submission by ESCO of a written approval of its invoice by BMC. In the event the Escrow Agent does not receive a written approval by BMC, it shall not release the remaining twenty-five per cent (25%) The remaining twenty-five per cent (25%) of the amount of the invoice shall be paid by the Escrow Agent upon submission by ESCO of a written approval of its invoice by BMC. BMC shall provide its written approval (or disapproval with part or all of the invoice amount) within thirty (30) days following the receipt of such invoice. RFP Article 3.2 3.2.1 If the Winning Bidder is a Bidding Consortium, the 3.2.1 If the Winning Bidder is a Bidding Consortium, the aggregate equity share holding issued and paid aggregate equity share holding issued and paid up by the up by the Lead Member in the Project Company Lead Member in the Project Company shall not be less shall not be less than: than: 12 In the event the written approval (or disapproval with part or all of the invoice) is not received from BMC within thirty (30) days of receipt of copy of invoice by BMC as provided in the above paragraph, , the written approval from BMC shall be deemed to have been obtained by the ESCO and the Escrow Agent may release the remaining twenty-five per cent (25%). - - fifty-one per cent (51%) continuously for a period of two (2) years as from the date of execution of the Contract; and twenty-six per cent (26%) for a period of three (3) years thereafter. fifty-one per cent (51%) continuously for a period of two (2) years as from the Commencement Date; and twenty-six per cent (26%) for a period of three (3) years thereafter. Sl. Clause No. and Existing Provision Revised/New provision 13 RFP Article 3.4.1 3.4.1 If the Winning Bidder is a Bidding Company, it may choose to set up a Project Company under Indian laws to enter into the Contract with BMC. The Project Company will have to be incorporated within fifteen (15) days after the issuance by BMC of the letter of intent. 3.4.1 If the Winning Bidder is a Bidding Company incorporated in India, it may choose to set up a Project Company under Indian laws to enter into the Contract with BMC. The Project Company will have to be incorporated within thirty (30) days after the issuance by BMC of the letter of intent. 14 RFP Article 3.4.2 3.4.2 If the Winning Bidder is a Bidding Consortium, then it will have to set up a Project Company under Indian laws within fifteen (15) days after the issuance by BMC of the letter of intent. The Project Company will execute the Contract with BMC. 3.4.2 If the Winning Bidder is a Bidding Consortium or is a Bidding Company incorporated outside of India, then it will have to set up a Project Company under Indian laws within thirty (30)) days after the issuance by BMC of the letter of intent. The Project Company will execute the Contract with BMC. 16 RFP _ Article 3.5.1.2 The projects referred to by the Bidder in order to meet The projects referred to by the Bidder in order to meet this this qualification requirement shall be in operation for at qualification requirement shall be in operation for at least a year. least a year. Projects by the parent company of a Bidder (parent company owning at least 51% of the equity of the Bidder) may be taken into account for the purposes of meeting the experience requirement set out in this section. 17 RFP Article 4.4.1 18 RFP Schedul e9 (Form of Earnest Money Deposit) 4.4.1 BMC must receive all Bids in person or by mail on or before April 22, 2012 at 3 p.m. (d) This guarantee will remain in full force for one hundred fifty (180) days following [date of Bid Submission Deadline]. 4.4.1 BMC must receive all Bids by Speed Post/Registered Post on or before April 22, 2013 at 3 p.m. (d) This guarantee will remain in full force for one hundred eighty (180) days following [date of Bid Submission Deadline].
© Copyright 2026 Paperzz