Direct Charcoal Ltd HYDROPOWER AT BROUGH BUSINESS CENTRE PRE-FEASIBILITY STUDY Oliver Paish Jon Needle April 2007 Project Ref: 7105 117 Hazelwood Rd, Duffield Derbyshire DE56 4AA Tel/Fax: 01332-842942 BROUGH HYDROPOWER AT BROUGH Pre-Feasibility Study 1. INTRODUCTION The land occupied by Brough Business Park was previously a mill dating from the 18th Century. The mill building and some of the workings, including the remains of an old turbine, are still in place, and the owners wish to investigate the potential for generating hydro-electric power on the premises. A site survey was completed by Oliver Paish and Jon Needle of Derwent Hydro on 1st February 2007. The key observations and conclusions are summarised below. 2. SITE OBSERVATIONS • • • • • • • • • Bradwell Brook passes along the western boundary of the business park, spilling over a concrete weir 3.8 metres wide and 3 metres fall. 6-inch stop-boards are placed on top of the weir to raise the upstream level, removed in times of flood. Concrete spillways either side of the weir can take additional flow as the level rises. The weir is shown in Figure 2. The old turbine at the northern end of the original mill building (Figure 3) was fed by around 60 metres of open leat and 70 metres of buried concrete pipe. The leat has been completely filled in, with a tennis court over much of it, but the concrete pipe is still in place under the car-park, running from the end of the tennis court to the turbine, including one bend. At the turbine location, the 1 metre concrete pipe discharged into an open concrete tank where the flow was screened for debris. It appears that the pipe ran partially filled to a depth of around 700mm. A hole in the base of the tank allowed the water to fall vertically down through a 3 foot steel pipe to reach the turbine at the bottom of the wheelpit. The pipe is still in place and completely filled with gravel. The wheelpit is 1.85m wide by 2.5m from back to front. The turbine was a vertical-shaft open-flume early reaction turbine dating from the late 19th Century. Only part of the machine still remains. The flow exited the wheelpit through an arched culvert which runs 8 metres back to the river. This is in good condition, but substantially filled with silt. The depth of water in the wheelpit was measured at 700 mm. In general, the inlet pipe, screening tank and turbine enclosure are still in robust condition, and provide a good basis for a new, modern installation at this point. The incoming 3-phase low-voltage line enters the site adjacent to the turbine, where it converts from pole-mounted to an underground line to the switchboard on the opposite side of the car park. A new generator may be permitted to feed directly into the pole-mounted line, but this requires consultation with the electricity company. 3. HEAD & FLOW 3.1 Head The gross head was measured on the day of the survey to be 4.3 metres in the old wheelpit. There will inevitably be some losses through the trashrack, turbine inlet and tailrace and for the purposes of this report, a design head of 4.1m will be assumed. The head at the weir was 3.15m, allowing a net head of 2.8m to be considered at this location. OFP/Brough Survey Report 1 19/04/07 BROUGH 3.2 Flow The flow on the day of the survey was estimated at the weir to be 650 litres/sec. The client reported that the Brook sustains a consistent flow, and that the observed flow conditions were 'typical' for the winter. Bradwell Brook is not gauged by the Environment Agency. The HydrA hydraulic model from the Institute of Hydrology was run for this catchment, with estimated catchment area of 13.5 km2 and average rainfall of 1150 mm per year. The key parameters are as follows: Qmean Q95 Q50 Q10 Average Flow Flow exceeded 95% of the time Median Flow – flow exceeded 50% of the time Flow exceeded 10% of the time 310 75 220 560 litres/sec litres/sec litres/sec litres/sec The natural flow in the brook is substantially increased by the outflow from the sewage works downstream of Bradwell. This processes the sewage from Castleton and the surrounding area and Severn Trent Water should be able to provide an indication of the range of flows discharged into the brook at this point. Some flow (the 'compensation flow') would need to be left over the weir to maintain the ecology in that stretch, so the flow available for hydropower will be reduced by perhaps 50 litres/sec. The maximum power output that can be fed into a three-phase connection using the industry’s G83 standard1 is 11.1kW. This would imply a design flow of 450 litres/sec on 4.1m head. In the absence of more detailed flow data, we would proposes this figure as the provisional turbine design flow for the scheme. 4. SCHEME OPTIONS There are two locations where a new turbine could be placed: 1) in parallel with the weir 2) in place of the old turbine. 1. In principle, it would be possible to implement a new installation on the far side of the weir. This would involve excavating a new intake upstream of the weir in order to direct flow into a pipe which would run some 20 metres to a turbine located low down on the river bank downstream of the weir. The main disadvantages with this option are: • This location has 30 % less head than the old turbine pit, which translates into 30% less power and energy, plus the need for a bigger turbine. • Implementing the civil works on this side of the river (intake, pipeline, powerhouse, discharge sump) would not be straightforward. The existing works at this end of the weir appear to be unstable and construction firms generally do not like working this close to a steep-sided river bank. Some land would be required from the owner of the field backing on to the river, both for the temporary works and the powerhouse, plus future access for maintenance of the scheme. • 1 G83 allows pre-approved control systems to be used to connect electrical generators into the local network without consulting the local electricity company. OFP/Brough Survey Report 2 19/04/07 BROUGH 2. Overall, we believe that restoring the water supply to the old turbine enclosure, so benefiting from the extra head and making use of the existing infra-structure, will lead to a more economically attractive scheme, as follows. • • The intake at the bend in the brook will need to be restored, so as to direct the flow into a new pipeline. If the pipe is set low enough to be run full, it only needs to be 600 mm diameter. There is space to run this pipeline along the edge of the tennis court. The main difficulty will be in connecting this pipe to the existing 1 metre concrete pipe, which may require two 90 degree bends to pass the pipe around the back of the tennis court. However, laying this length of pipe is likely to be less risky and less costly than the riverside works required for Option 1. 4.1 Turbine The only type of turbine likely to be cost-effective for this head and flow is a crossflow turbine. This is a variable-flow machine which, in its twin-cell version, can still operate at 10% of design flow. It will run sufficiently fast to allow a low-cost belt-drive to connect to the generator. A crossflow turbine is self-cleaning with regard to ‘soft’ debris such as leaves, but requires a reasonably fine screen to keep out twigs and stones of a size which might jam between the runner blades. Low-cost crossflow turbines are available from Valley Hydro in Cornwall (see Figure 1), but on long lead times. There are more robust and efficient machines from Ossberger and WKV in Germany, which we would generally recommend as being worth the greater expense. Figure 1 Valley Hydro crossflow turbine installation, plus schematic illustration A fine-meshed screen will be required upstream of the turbine to prevent the ingress of both fish and debris. The screen itself could be a fixed bar screen, which would need to be raked at least twice daily, or be fitted with a more complex automatic raking system, which we would generally recommend for ensuring the efficient output of the system. Control System The control system will enable fully automatic operation of the turbine. It continuously monitors the headwater level, and will open or close the turbine valve in small adjustments, according to whether the OFP/Brough Survey Report 3 19/04/07 BROUGH upstream level is rising or falling. When there is insufficient water to generate power, the turbine will shut down completely, and will automatically restart when the river is replenished. 5. OUTPUT & REVENUE A turbine designed for 4.1 m net head and 450 litres/sec design flow would generate a peak electrical output of around 11kW. Depending on the actual availability of flow (the sewage discharge being the main unknown) , the electricity generated over one year could be expected to be in the range 50-70,000 kWh/year. The system would run ‘in parallel’ with the local network, i.e. any power generated by the turbine would first be consumed in the property (reducing the electricity that would otherwise be bought in) and any excess power would pass back through the grid through a meter, and could be sold to an electricity company. Depending on what proportion of the power could be consumed on site, the average value of the electricity generated by the scheme would be in the range 9-11 p/kWh, including the value of the Renewable Obligation Certificates 2. Hence an annual value of £5000-£7000 per year (increasing with electricity prices). It may be possible to strike a deal with one of the electricity companies (e.g. EDF or npower) for them to subtract the total energy exported by the hydro-scheme from the total energy imported by the business park. This would raise the value of the power to 12-13 p/kWh. 6. COSTS The initial broad-brush estimates for the electro-mechanical equipment and installation costs would be as follows: Item Valley Hydro Turbine and belt-drive +guard Generator, control panel and cabling Intake screen and automatic cleaner Detailed design and engineering Workshop assembly, installation and commissioning Transport and contingency TOTAL ex VAT @5% Option WKV or Ossberger turbine £ 12500 6000 6500 4500 6500 2000 £38000 +10,000 In addition, work would be required for: • Constructing the intake works at the river. • Procuring and burying 60m or so of 600mm drainage pipe and forming a connection with the existing concrete pipe. Removing the old turbine and down-pipe. • 2 Electricity generated from renewable sources can be used to obtain Renewables Obligation Certificates (ROCs) which can then be sold to one of the electricity companies. They need the ROCs in order to prove they are meeting the governments targets for renewable energy. ROCs have a market value in the range 3.5p – 4.5p per kWh which will vary over time depending on how well these companies are doing in meeting their targets. OFP/Brough Survey Report 4 19/04/07 BROUGH • • • Remedial works to the turbine enclosure, including the installation of a new floor just above maximum downstream flood level. Running the power cable to the network connection. Gaining planning and licensing permissions, as appropriate. 7. NEXT STEPS A formal license from the Environment Agency is likely to be required, plus planning permission. The main environmental criteria to be satisfied would involve fish-protection and the amount of water to be taken in dry conditions The logical next steps to develop the scheme would be: • • • • • To obtain discharge figures for the treatment works from Severn-Trent Water. To have an informal discussion with the Environment Agency to assess their viewpoint Commission the full scheme design to present to the EA and local planners and in order to define accurately the civil works requirements and costs. Obtain firm quotes for the cost of the electro-mechanical equipment. Prepare formal applications for the EA and planners. Derwent Hydro could offer to undertake these steps, and we would recommend a budget allowance of £3500. Figure 2 Main Weir OFP/Brough Survey Report 5 19/04/07 BROUGH Figure 3 Old turbine pit OFP/Brough Survey Report 6 19/04/07
© Copyright 2026 Paperzz