Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities NOTICE This document contains the expression of the professional opinion of SNC-Lavalin ATP Inc. as to the matters set out herein, using its professional judgment and reasonable care. It is to be read in the context of the agreement dated April 3, 2009 (the “Agreement”) between SNC-Lavalin ATP Inc. and the Nishnawbe Aski Development Fund (the “Client”), and the methodology, procedures and techniques used, SNC-Lavalin ATP Inc. assumptions, and the circumstances and constrains under which its mandate was performed. This document is written solely for the purpose stated in the Agreement, and for the sole and exclusive benefit of the Client, whose remedies are limited to those set out in the Agreement. This document is meant to be read as a whole, and sections or parts thereof should thus not be read or relied upon out of context. SNC-Lavalin ATP Inc. has, in preparing the analyses herein, followed methodology and procedures, and exercised due care consistent with the intended level of accuracy, using its professional judgment and reasonable care. However, no warranty should be implied as to the accuracy of information or data provided. Unless expressly stated otherwise, assumptions, data and information supplied by, or gathered from other sources (including the Client, other consultants, testing laboratories and equipment suppliers, etc.) upon which SNC-Lavalin ATP Inc.’s opinion as set out herein is based has not been verified by SNC-Lavalin ATP Inc.; SNC-Lavalin ATP Inc. makes no representation as to its accuracy and disclaims all liability with respect thereto. SNC-Lavalin ATP Inc. disclaims any liability to the Client and to third parties in respect of the publication, reference, quoting, or distribution of this report or any of its contents to and reliance thereon by any third party. Page i Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Executive Summary On April 3, 2009 SNC-Lavalin ATP, Inc., and its subcontractor, McLeod Wood Associates Inc., were awarded a contract to assess opportunities for building economically viable transmission and distribution interconnections between remote communities, renewable generation resources in Northern Ontario and Hydro One Networks Inc. (HONI) facilities. The goal was to identify a program of extensions that would involve as many communities as possible, while keeping the overall interconnection cost low. The existing load for the 24 remote communities studied is approximately 18 MW in total, which is expected to increase to approximately 39 MW in the next 20 years. The power demands of the communities are currently supplied by diesel generation operated by Hydro One Remote Communities Inc. (HORCI) and Independent Power Authorities (First Nations owned and controlled). Five connection options (shown conceptually in Figures A to E) were reviewed as an alternative to the existing diesel generation systems. Although both wind and hydro generation resources were considered, it was determined that hydro generation resources were the most easily developed and maintained. In particular, hydro sites that are close to the communities are most likely to the first to be developed and connected to the proposed system. Therefore, the transmission concepts shown below assume some level of hydro development in step with increasing load over the 20 year period considered in this study. However, this does not exclude the possibility of wind power development at locations where favourable economic and technical factors coexist. Option 1: Isolated or independent supply systems (supplied by renewable sources to be developed locally); Option 2: Supply loops connected to the grid at Red Lake; Option 3: Supply loops connected to the grid at Musselwhite Mine (MWM); Option 4: Supply loops connected to the grid at both Musselwhite Mine and Red Lake; Option 5: Supply arcs connected to the grid at both Musselwhite Mine and Red Lake. Page ii Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Independent Supply Loop G G G G G= Generation resources IESO-Controlled Electric Power Grid Fig. A: Option 1 - Isolated Supply Loops or Independent Systems Supply Loop Red Lake E2R Ear Falls IESO-Controlled Electric Power Grid Fig. B: Option 2 - Supply Loops Connected at Red Lake Page iii Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Supply Loop Musselwhite Mine M1M Pickle Lake IESO-Controlled Electric Power Grid Fig. C: Option 3 - Supply Loops Connected at Musselwhite Mine Supply Loop Red Lake Musselwhite Mine E2R Ear Falls E4D M1M E1C Pickle Lake IESO-Controlled Electric Power Grid Fig. D: Option 4 - Supply Loops Connected at both Red Lake and Musselwhite Mine Page iv Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Supply Arc Red Lake M1M E2R Ear Falls E4D Musselwhite Mine Pickle Lake E1C IESO-Controlled Electric Power Grid Fig. E: Option 5 - Supply Arcs Connected at both Red Lake & Musselwhite Mine and Complemented by Radial Lines Table A provides a high level comparison of the main factors influencing the cost of the various optional configurations or solutions. Table A – Influences of Various Cost Factors on Optional Configurations Cost Factor Overall 115-kV Length Overall 44-kV Length Line Maintenance Transmission Losses 115-kV Substations VAR Compensation Option 1 Option 2 Option 3 Option 4 Option 5 >1500 km >1500 km >1500 km >1500 km ≈795 km ≈210 km ≈210 km ≈210 km ≈210 km ≈565 km High High High High Moderate Moderate Moderate Moderate Moderate Moderately High 21 21 21 21 16 High High High High Moderate Page v Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities In Table A, supply loops for Options 1 to 4 are 115-kV and directly connect 21 communities. For Option 5, 12 communities are connected by the 115-kV supply arc, and 9 communities are connected via 44-kV radials. Sixteen 115-kV substations are required for the Option 5 connections. For all options, the 4 communities southeast of Pickle Lake (see Figure F) are assumed to be connected to the HONI power grid by 44kV radials. The cost of these radials and substations has been included in this study. An assumption has been made that at some point in the future, the planned HONI 240kV line from Lake Nipigon to Little Jackfish will be extended to Pickle Lake. This will enable the connection of these 4 communities. A comparison of the factors impacting operational reliability of the various configurations is provided in Table B. Table B – Impacts of Key Reliability Factors on Different Configurations Reliability Factor Option 1 Option 2 Option 3 Option 4 Option 5 Overall 115-kV Length Power Grid Connection >1500 km >1500 km >1500 km >1500 km ≈795 km None At Red Lake At MWM Import/Export Capability None Limited by E2R capacity Reserve Generation Capacity Limited by power demand of FN communities Limited by FN demand & E2R At Red Lake & MWM Limited by E2R & M1M capacities Limited by FN demand, E2R & M1M At Red Lake & MWM Limited by E2R & M1M capacities Limited by FN demand, E2R & M1M Limited by M1M capacity Limited by FN demand & M1M Table C below brings together the cost and reliability aspects of different configurations. Table C - Comparing Overall Cost and Reliability for Different Options Key Items Option 1 Option 2 Option 3 Option 4 Option 5 Build Cost Very High High High High Moderate Very High High High High Moderate Low Low Low Relatively High Moderate Operation & Maintenance Cost Supply Reliability Page vi Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The most reasonable compromise between cost and reliability is offered by configurations falling under Option 5, as they have moderate build and O&M costs and can offer a relatively high level of reliability. The Recommended Concept Of the five possible configurations, Option 5, the option with the shortest transmission length, as shown in Fig. F, is the one recommended in this study. Bearskin Lake Sachigo Lake Kitchenuhmay Wapekeka Kasabonika Lake Muskrat Dam Wawakapewin Sandy Lake Keewaywin Weagamow (NC) Wunnumin Kingfisher Lake Nibinamik Webequie Bear Head Lake North Spirit Lake Neskantaga Musselwhite Deer Lake 115 kV private line Poplar Hill Eabametoong Pickle Lake Albany River Pikangikum 44 kV private line Little Jackfish Red Lake 44kV 115kV HONI 230kV Hydro Substation Whitesands Figure F – Recommended Concept (Option 5) Page vii Gull Bay Wind Farm Tap Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The recommended concept consists of a 115-kV backbone system approximately 795 km in length with 44-kV radial lines. Its backbone passes through 12 communities and it connects an additional 9 communities via radial lines. The total estimated cost of this concept is $321 million. It supplies all of the power demands of the indicated 21 communities up to and beyond the horizon year of 2029, while passing through regions with high potential for hydro and mining developments. As mentioned previously, a key assumption of the recommended configuration is that the Hydro One planned 230-kV line from Lake Nipigon to Little Jackfish will be extended to Pickle Lake at some point in the future, enabling connection of the four communities east of Pickle Lake via 44-kV radials. In the absence of this extension, other alternatives for connecting these four communities have to be considered. One such alternative is the extension of the 115-kV backbone southward to include the Musselwhite 115-kV private line and a 115-kV line segment connecting Pickle Lake to Little Jackfish. The report also discusses options for connecting the remaining three communities (Fort Severn, Marten Falls and Peawanuck) to the power grid. Pikangikum will be connected by a privately owned 44-kV line and is not included in the cost analysis for the proposed concept. Cost of Existing System vs. Recommended Concept The annual cost of the diesel generation system will require continuous investment to cover the increased demand on the system due to population growth and growth in household demand. The difference in annual and cumulative costs favors the construction of a transmission line immediately. Over 20 years, the savings begin to appear between the two systems, totaling more than $800 million. Over the 50 years modeled, the difference reaches a higher order of magnitude exceeding $5 billion. Page viii Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table D – Cost Comparison Summary Supply System Annual Cost (in Millions) Cumulative Cost (in Millions) 2009 2029 2009-2029 Diesel Generation $49.7 $109.3 $1,591.6 Recommended Concept $37.4 $30.2 $709.6 Next Steps This section provides an overview of the suggested next steps for the project based on the recommended concept detailed in this report. Since both the technical and cost evaluations presented in this report have been done at a preliminary level, additional follow-up analysis is required before any final decision can be made to move forward with the proposed option. Step 1 – Consultations with Interested Parties • Support or buy-in by the Off-Grid communities impacted, in order to move forward; • Discussions with interested parties should be conducted to obtain technical feedback on the transmission line concept; • On-going communications and/or preliminary consultations with First Nations communities using the process outlined in Section 13.0 of this report; • Discussions with owner of private line at termination point at Musselwhite Mine (Goldcorp Inc.); and, • Discussions with sources of funding to support more detailed analysis including: MEI, INAC, FedNor, and potential transmission partners. Step 2 – More Detailed Analysis • If the transmission line routing as presented in this report is accepted by stakeholders, then a more detailed analysis should be conducted that would include the following: Page ix Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities - load flow analysis that would test the system with up to 200 MW of local generation development and increased mining loads; - more accurate line routing and cost estimate; - on-going and enhanced communications with off-grid communities; - at the present time, no assessment has been made as to the environmental impact of the proposed solution; some preliminary study is required in this area. • If, as a result of discussions with stakeholders, other configurations or modifications to the route are proposed, then these options could be assessed at a high level to eliminate options that are not feasible. Step 3 – Pursue Other Incentives and Financial Assistance • The Feed-in Tariff (FIT) Program could be used to make this project more attractive by assisting in the development of the hydro resources required to support this project. • HONI is looking at a radial supply to Whitesands and Gull Bay from the 230-kV line at Little Jackfish. If this goes forward, the cost of Option 5 would be reduced. • Reduction of carbon footprint and carbon credits. Page x Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities TABLE OF CONTENTS Executive Summary 1.0 INTRODUCTION........................................................................................................................................... 1 2.0 SCOPE OF STUDY ........................................................................................................................................ 3 3.0 METHODOLOGY ......................................................................................................................................... 4 3.1 3.2 3.3 4.0 TECHNICAL ANALYSIS .................................................................................................................................. 4 COSTING APPROACH ..................................................................................................................................... 5 COLLECTION OF MAPPING INFORMATION...................................................................................................... 5 SYSTEM REQUIREMENTS ........................................................................................................................ 7 4.1 FORECASTED GROWTH AND ELECTRICITY DEMAND ..................................................................................... 7 4.2 GENERATION REQUIREMENTS ....................................................................................................................... 9 4.2.1 Existing and Future Power Supply System............................................................................................... 9 4.2.2 Potential Wind and Hydro Generation Developments ............................................................................. 9 4.3 TRANSMISSION SYSTEM REQUIREMENTS .................................................................................................... 11 5.0 STUDY ASSUMPTIONS ............................................................................................................................. 12 5.1 5.2 6.0 GENERAL ASSUMPTIONS ............................................................................................................................. 12 SPECIFIC ASSUMPTIONS .............................................................................................................................. 12 STUDY RESULTS........................................................................................................................................ 14 6.1 CONFIGURATION OPTIONS........................................................................................................................... 14 6.1.1 Characteristics of Option 1 .................................................................................................................... 15 6.1.2 Option 2 Characteristics ........................................................................................................................ 17 6.1.3 Option 3 Characteristics ........................................................................................................................ 18 6.1.4 Option 4 Characteristics ........................................................................................................................ 19 6.1.5 Option 5 Characteristics ........................................................................................................................ 20 6.1.6 Cost Comparison for Different Solutions ............................................................................................... 21 6.1.7 Comparing Reliability of Different Options ........................................................................................... 21 6.1.8 Recommended Configuration Concept................................................................................................... 22 6.2 RECOMMENDED TRANSMISSION CONCEPT .................................................................................................. 23 7.0 PROPOSED CONCEPT DETAILS............................................................................................................ 26 7.1 7.2 7.3 7.4 8.0 BACKBONE AND RADIALS ........................................................................................................................... 26 SYSTEM PERFORMANCE ANALYSIS ............................................................................................................. 28 UNCONNECTED REMOTE COMMUNITIES ..................................................................................................... 28 SYSTEM IMPLEMENTATION.......................................................................................................................... 29 COSTING THE PROPOSED CONFIGURATION .................................................................................. 30 8.1.1 8.1.2 8.1.3 9.0 9.1 Line and Equipment Cost Breakdown .................................................................................................... 30 Operation and Maintenance Cost Estimation ........................................................................................ 33 Transmission Loss Estimation................................................................................................................ 33 COST COMPARISON OF EXISTING AND PROPOSED SYSTEM..................................................... 35 HORCI SUBSIDY ......................................................................................................................................... 35 Page xi Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 9.2 9.3 9.4 9.5 9.6 9.7 IPA SUBSIDY COSTS.................................................................................................................................... 37 UPGRADE OF DIESEL GENERATION ............................................................................................................. 38 OTHER COSTS ASSOCIATED WITH DIESEL GENERATION ............................................................................. 39 EXISTING SYSTEM COST SUMMARY ............................................................................................................ 40 FINANCING NEW FACILITIES ....................................................................................................................... 40 COST OF PROPOSED TRANSMISSION LINE VS. EXISTING DIESEL GENERATION ............................................ 41 10.0 REGULATORY IMPACTS......................................................................................................................... 44 11.0 RECOMMENDATIONS.............................................................................................................................. 48 12.0 NEXT STEPS ................................................................................................................................................ 49 13.0 PROPOSED PROCESS FOR COMMUNITY ENGAGEMENT............................................................. 51 13.1 13.2 13.3 13.4 13.5 13.6 PURPOSE...................................................................................................................................................... 51 KEY MESSAGES ........................................................................................................................................... 51 MESSAGE FORMAT ...................................................................................................................................... 51 SPECIFIC MESSAGE CONTENT ..................................................................................................................... 52 AUDIENCE ................................................................................................................................................... 52 SPECIFIC ENGAGEMENT STRATEGY ............................................................................................................. 52 APPENDIX A: APPENDIX B: APPENDIX C: APPENDIX D: APPENDIX E: APPENDIX F: MAP TECHNICAL DATA CONSULTATION CONTACTS SUMMARY OF STATION COSTS REGULATORY IMPACTS GLOSSARY OF TECHNICAL TERMS Page xii Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities LIST OF TABLES TABLE 4.1- EXISTING AND FORECAST LOADS ................................................................................................................. 8 TABLE 4.2 - HYDRO GENERATION SITES THAT COULD BE DEVELOPED BY 2029 ............................................................ 10 TABLE 6.1 - INFLUENCES OF VARIOUS COST FACTORS ON DIFFERENT SOLUTIONS ...................................................... 21 TABLE 6.2 - IMPACTS OF KEY RELIABILITY FACTORS ON DIFFERENT CONFIGURATIONS.............................................. 22 TABLE 6.2 - COMPARISON OF OVERALL COST AND RELIABILITY OF DIFFERENT OPTIONS ........................................... 22 TABLE 7.1 - SUMMARY OF PROPOSED COMMUNITY CONNECTIONS .............................................................................. 27 TABLE 8.1 - COST BREAKDOWN FOR RECOMMENDED OPTION: BACKBONE WITH RADIAL CONNECTIONS TO COMMUNITIES (INSTALLED COST) ....................................................................................................................... 31 TABLE 8.2 - OPTION 5 BACKBONE ONLY - WITHOUT RADIAL CONNECTIONS TO .......................................................... 32 TABLE 8.3 - ADDITIONAL COST OF CONNECTING MARTEN FALLS, PEAWANUCK AND FORT SEVERN .......................... 33 TABLE 8.4 - LOSSES OF THE PROPOSED TRANSMISSION CONCEPT UNDER TWO LOAD LEVELS, WITH NO LOCAL GENERATIONS ...................................................................................................................................................... 34 TABLE 8.5 - ANNUAL COST OF LOSSES FOR THE PROPOSED TRANSMISSION CONCEPT, UNDER CONDITIONS OF TABLE 8.4 ............................................................................................................................................................................. 34 TABLE 9.1 - HORCI SUBSIDIES (ALL FIGURES, 2009 $)................................................................................................ 36 TABLE 9.2 - IPA SUBSIDIES (ALL FIGURES, 2009 $)...................................................................................................... 38 TABLE 9.3 - COST COMPARISON SUMMARY (IN $ MILLIONS) ....................................................................................... 42 LIST OF FIGURES FIG. 6.1: OPTION 1 - ISOLATED SUPPLY LOOPS OR INDEPENDENT SYSTEMS ................................................................. 15 FIG. 6.2: OPTION 2 - SUPPLY LOOPS CONNECTED AT RED LAKE ................................................................................... 16 FIG. 6.3: OPTION 3 - SUPPLY LOOPS CONNECTED AT MUSSELWHITE MINE .................................................................. 18 FIG. 6.4: OPTION 4 - SUPPLY LOOPS SUPPORTED AT BOTH EAR FALLS AND MUSSELWHITE ......................................... 19 FIG. 6.5: OPTION 5 - SUPPLY ARCS CONNECTED AT BOTH RED LAKE & MUSSELWHITE AND COMPLEMENTED BY RADIAL LINES ...................................................................................................................................................... 20 FIG. 6 6: THE RECOMMENDED CONFIGURATION (OPTION 5)......................................................................................... 24 Page xiii Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 1.0 Introduction On April 20, 2009 SNC-Lavalin ATP, Inc. and its subcontractor McLeod Wood Associates, were awarded a contract to assess opportunities for building economically viable transmission and distribution interconnections between remote communities in Northwestern Ontario, identifiable renewable generation resources in Northern Ontario, and points of interconnection with transmission facilities in the transmission grid controlled by the Independent Electricity System Operator (IESO) in Ontario. The goal of this investigation was to identify a program of extensions that could connect as many communities to grid supply as possible, while keeping the overall interconnection cost low. Remote communities are generally defined as those communities whose power systems are not connected to the main Ontario electricity grid. These communities utilize diesel generation to produce electricity which remains a more expensive form of electricity generation when compared to the Ontario average cost of generation. The ever rising cost of fuel, especially the rapid rise of diesel costs in 2008, is a challenge for ratepayers and for various levels of government which subsidize these supply arrangements. Little relief from these high costs is expected in the short or the long term. In most cases, these remote communities are also not connected to the rest of Ontario via all season roads or by rail, and thus rely upon winter roads, or air freight, to deliver goods and equipment, including diesel fuel for electricity generation. In Ontario, Hydro One Remote Communities Inc. (HORCI) operates fourteen remote communities that are not grid connected. HORCI receives a subsidy, through the Remote and Rural Rate Program, which enables it to charge rates to the remote community residents that are approximately equal to those rates paid by other Ontario electricity consumers. The HORCI distribution networks are regulated by the Ontario Government, and follow the Distribution Code as set out by the Ontario Energy Board. There are twelve First Nation owned and controlled Independent Power Authorities (IPAs) that operate within Ontario outside of the HORCI system. These IPAs do not operate within the rules set out by the Ontario Government, and without the subsidies, struggle to provide electricity at a reasonable cost to their respective community members. The cost of energy in these communities may be several times the cost charged to grid connected consumers. This pre-feasibility study reviewed a number of options for connecting these First Nations communities to the IESO controlled grid. The most promising option was Page 1 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities subjected to further analysis, which included a series of load flow analyses to see how the system would react under various load, generation, and network scenarios, and finally a cost comparison with existing diesel generation. The sections that follow provide the details of this analysis and the steps necessary to move forward with this project. Page 2 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 2.0 Scope of Study The scope of work to be delivered in this report will include all areas incorporated in the SNC-Lavalin proposal dated April 3, 2009. In evaluating the potential network solutions for supplying power to the off-grid communities, the study has to allow for the following: • Communities have existing isolated power systems powered by diesel generators. These power systems have small distribution networks, whose voltages are primarily set by the diesel generators’ output voltages. • Hydro One Networks Inc. (HONI) has plans for building transmission infrastructure in support of East-West power transfers and enabling hydro and wind power facilities in northern Ontario. These plans call for bringing power from Lake Nipigon area to Pickle Lake via a 230-kV line. This will result in a “strong” power supply at Pickle Lake, subject to ongoing weakness in the existing line E1C from Ear Falls to Pickle Lake, which will require upgrading at a later date. • The costs of O&M, diesel fuel, fuel transportation and environmental impacts of the existing local power systems need to be compared with those of any transmission concept recommended by this study. In brief, this study should assess the feasibility of connecting off-grid First Nations communities to the Ontario grid using approximate transmission line lengths and cost figures. It is a pre-feasibility study only, and the cost comparisons between the existing diesel generation systems and any proposed transmission concept will be based on approximate construction and O&M costs driven by forecasted electricity demands. Socio-economic benefits have not been included in the analysis. A more detailed study will be required at a later date to solidify the data provided in this report, in particular the data associated with cost/benefit figures. Page 3 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 3.0 Methodology 3.1 Technical Analysis The technical analysis of the various options for the proposed supply system was based on the raw data available from Nishnawbe Aski Development Fund (NADF), the Waterpower Working Group, the Ontario Ministry of Natural Resources, the Ontario Ministry of Energy and Infrastructure, and others. The supply system options were first analyzed to identify the configuration offering the best costreliability mix, and then evaluated based on a set of performance indices that measure the following parameters: • Ability to supply the greatest number of First Nations communities; • Overall transmission length and the required number of substations (of various types) and reactive power (VAR) compensation points; • Proximity of the supply path to hydro and wind development sites within the area; • Proximity of the supply path to regions identified with high mining potential within the area; • Proximity of the supply path to all-season and winter roads; and, • Proximity of the supply path to suitable terrain for construction and access for transporting material and personnel. The study has also taken into account: • System performance of the proposed solution under normal conditions, for a range of load, generation and line outage scenarios; and, • Impact of the proposed solution on the IESO controlled power grid. Using the above information, one configuration was identified as most attractive and its electrical performance was further analyzed for the following supply scenarios: • Full supply of the community demands by IESO controlled power grid; • Supply of the community demands by hydro generation expected to be developed by 2029. These generation developments are selected to be located Page 4 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities close to the communities (<20 km) and are expected to be mostly small (<5 MW), run-of-river type. 3.2 Costing Approach The cost comparison of producing electricity with the existing diesel system vs. the proposed grid-connected supply system was conducted using the following: • Data on existing diesel generation plants in both the regulated (HORCI) and the unregulated (IPA) remote community electricity supply system; • Cost estimates developed for operating, upgrading, and maintaining remote diesel system; • Cost estimates projected to year 2029 for diesel systems; • Cost estimates for the lines and substations (transformers, breakers, SVCs, etc.) making up the transmission loop, including their construction, operation and maintenance; and, • Cost factor applied to construction of transmission lines based on the terrain and transportation costs for materials. 3.3 Collection of Mapping Information Geographical and geological information used for routing various transmission concepts considered in the study were obtained from: • the SNC-Lavalin database developed for a previous NADF study; and • the Canadian Geological Survey soils data. Data on infrastructure, communities/reserves, parks, etc was obtained from: • the website http://geogratis.cgdi.gc.ca/geogratis/en/collection\, Natural Resources Canada Geogratis; and, • the Ontario Ministry of Natural Resources. Mining data was obtained from: • Ministry of Northern Development, Mines and Forestry Page 5 operated by Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities All mapping was conducted using ESRI Arcview GIS (Geographic Information Systems) software. Page 6 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 4.0 System Requirements 4.1 Forecasted Growth and Electricity Demand The IPAs could not be used as a source of data for this study since they are not required to file rate applications to the Ontario Energy Board (OEB), as is the case for HORCI. The data used throughout this analysis utilizes the best available data at the time of writing, and includes Hoshizaki (2006), Reimer (2009), and Econalysis and Hoshizaki (2003) reports. A significant source of data is the EB-2008-0232 distribution rates filing by HORCI with the OEB. Where verifiable data was not available for the IPAs, the data from HORCI was extrapolated. While there are likely significant differences in the costs of operating HORCI generation facilities and the IPAs, it is the best data available, and is likely to represent a close approximation. A significant portion of the analysis requires the projection of data into the future. Projections are inherently subject to a margin of error, and the further into the future a projection goes, the larger the margin of error is likely to be. In order to simplify the analysis and avoid unnecessary projections, the costs and revenues of the remote system and the alternatives are projected in 2009 dollars. Projecting the future price of diesel fuel is extremely difficult and subject to a very large margin of error at 20 years into the future. The future cost of the diesel generation system in each community is strongly correlated to the projected growth of the community and resultant increase in demand. First Nations communities are among the highest growth communities in Canada, exceeding the Canadian average growth rate. For this analysis, the projected numbers submitted by Econalysis and Hoshizaki (2003) to Indian and Northern Affairs Canada showed an average growth rate of 4.02% over a 17 year period. This was the rate used in this analysis for the first 20 years of projections. After 20 years, a rate of 2.5% was used, assuming that individual demand growth had slowed, and growth rates had also slowed. This was used in order to provide a longer term comparison with the cost of a transmission connection to the IESO controlled grid. The following is a summary of the existing and projected loads to 2029 for each of the communities included in this study. The projected load to 2029 is based on a load growth of 4.02% per year. Page 7 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table 4.1- Existing and Forecast Loads First Nations Community 2009 Measured Peak Load (kW) 2029 Projected Peak Load* (kW) --- Keewaywin (Couchiching) Marten Falls Nibinamik/Summer Beaver Pikangikum** Poplar Hill Wawakapewin Peawanuck Keewaywin (Niska) Eabametoong Muskrat Dam North Spirit Lake Wunnumin Bearskin Lake Kitchenuhmaykoosib Inninuwug Deer Lake Fort Severn Kasabonika Lake Kingfisher Lake Landsdowne House/Neskantaga North Caribou Lake/Weagamow Sachigo Lake Sandy Lake Wapekeka Gull Bay Whitesands Webequie 548 402 (1193) 463 61 341 292 883 591 511 772 835 1371 820 634 941 594 739 1169 938 2784 424 250 509 754 --1205 884 (2625) 1018 134 750 643 1942 1299 1125 1698 1838 3016 1803 1396 2071 1307 1626 2572 2063 6123 932 549 1120 1658 Totals for listed Communities (kW) 17,626 38,772 *Based on INAC Central Corridor Assessment growth rate of 4.02% **Assumed to be supplied by new private 44-kV line being built and not included in total demand The 4.02% demand growth rate allows for an initial spike in power demand once the communities become interconnected and current restrictions on electricity Page 8 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities consumption are relaxed. The 2029 demand estimates listed in Table 4.1 include the effect of this early rise in demand. 4.2 Generation Requirements 4.2.1 Existing and Future Power Supply System A breakdown of the diesel generation capacity at each community is provided in Appendix B3. For estimation purposes, it was assumed that generation capacity would mostly follow (not lead) the load growth at the rate of 4.02% per year for the next 20 years. As indicated in Appendix B3, this leads to situations where, at times, some sites will not have adequate diesel generation capacity to meet their forecasted loads. 4.2.2 Potential Wind and Hydro Generation Developments Due to the problems associated with access and the routine maintenance required by wind turbines, as well as the soil type at many potential wind farm locations, only the development of potential hydro sites has been considered as feasible at this time. In particular, run-of-river hydro sites that are close to the communities are most likely to be first to be developed and connected to the proposed system. Some of the hydro sites are considered to be beneficial to system operation and the path of the proposed transmission network was chosen to pass in close proximity to these generator locations. These locations are listed in Table 4.2. For each of the five transmission line options studied, including the recommended option, three types of generation development were considered: 1. Generation Development 1: No local generation. The communities’ electricity demands are all supplied by Hydro One Networks via its interconnections to the proposed configuration. 2. Generation Development 2: Generation at Muskrat Dam Lake and Wunnumin hydro sites. The two sites are assumed to jointly supply 54.7 MW at peak demand, which is sufficient to meet the demands of all communities, supply transmission losses and export more than 10 MW to the IESO-controlled grid in 2029. 3. Generation Development 3: Generation from many small hydro sites along the routes considered. The small sites are assumed to collectively generate as Page 9 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities much as in Generation Development 2. However, the transmission losses in this case are lower and the export to the grid is slightly higher. Table 4.2 - Hydro generation sites that could be developed by 2029 Generation Site Designation Pikangikum Eabametoong Muskrat Dam Wunnumin Kitchenuhmaykoosib Inninuwug Wapekeka Flammagan Gobham Bearskin Lake Deer Lake Gull Bay Webequie Neskatanga Kee-waywin/Koocheching Distance to Community (km) Plant Capacity (MW) Output in Scenario 2 (MW) Output in Scenario 3 (MW) 9.40 9.10 12.10 15.50 2.60 15.50 1.6 0.4 3.2 8.5 53.0 14.1 0 0 0 0 40.6 14.1 1.6 0.4 3.2 4.25 10.6 7.05 9.6 0.3 0 0.3 3.3 12 20 0.10 0.20 1.70 4.20 5.00 6.00 4.40 11 14.20 4.7 19.3 21.4 0.3 0.3 1.2 2.0 1.6 2.0 1.0 0.3 0.7 1.5 2.2 5.4 0.7 3.1 5.0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.3 0.3 1.2 2.0 1.6 2.0 1.0 0.3 0.7 1.5 2.2 5.4 0.7 3.1 5.0 108.4 54.7 54.7 Total Page 10 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Note that: • The names given to hydro sites in Table 4.2 are mostly those of their nearby communities. Where there are no nearby communities, names of adjacent lakes or rivers have been used. • To allow for a fair comparison between Scenarios 2 and 3, generation at Muskrat Dam and Wunnumin are reduced to have the same total generation for the two scenarios, 4.3 Transmission System Requirements This study outlines a high-level transmission concept or solution consistent with the requirements listed below, along with a preliminary performance analysis and estimates of its construction and O&M costs. The proposed solution must consider: • Factors influencing cost, reliability and environmental impacts of the required system, with the aim of bringing its overall cost and environmental impacts down, while keeping its reliability at an acceptable level; and • The role of the system for developing natural resources of Northwestern Ontario. The proposed transmission solution must allow for: • • • Power demand growth in off-grid communities as forecasted for 2029; Development of key generation facilities within the area; and Development of existing and future mines in the area and the associated increase in required power demands. The overall cost of the proposed solution must be kept low by: • • • • • Having a relatively short length, as lines’ build costs are proportional to their lengths; Using appropriate transmission voltages, tower configurations, and conductor sizes; Staying close to existing roads; Minimizing the number of transformers and switching substations, when possible; and, Having voltage/VAR support facilities that are as few and as small as practical. Page 11 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 5.0 Study Assumptions 5.1 General Assumptions • Electricity cost differentials - For the foreseeable future, the cost of HONIsupplied electricity in Northwestern Ontario will remain significantly lower than the electricity supplied by diesel generators. • Stakeholders’ cooperation - There will be cooperation between the interconnection parties (First Nations communities, HONI, IESO, Goldcorp) to the extent that would allow the proposed network to be interconnected to Hydro One Networks facilities and to the Goldcorp Musselwhite transmission facilities (M1M line and SVCs). • Voltage support - There will be installations or upgrades of voltage support facilities within the HONI system in support of the proposed system. • Cost of new generation facilities - The cost of hydro and wind generation facilities, including transmission equipment required for their interconnection, have not be considered here. These costs are assumed to be taken on by developers of the generation facilities. • Costs of using transmission facilities - The costs of utilizing existing transmission facilities to import/export power from/to the proposed system does not need to be considered, as they would be included in the electricity rates. • Access via Winter Roads - Since access for construction and maintenance is problematic, proximity to winter roads is assumed to be an important factor in the selection of the preferred paths for the transmission network. 5.2 Specific Assumptions The following specific assumptions were made in assessing the various options for the transmission line: • Extension to Little Jackfish Project – It is assumed that the Hydro One planned 230-kV line, between Lake Nipigon and Little Jackfish, will eventually be extended from Little Jackfish to Pickle Lake. The probability that this assumption becomes a reality is fairly high, as it coincides with the Ontario Power Generation (OPG) plans for developing Northern Ontario generation Page 12 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities resources, as well as Hydro One’s plans to establish an East-West power transfer corridor. • Reinforcement of EIC - It is also assumed that, as part of any future line between Little Jackfish and Pickle Lake, there will eventually (i.e. - before year 2029) be a reinforcement of line E1C from Pickle Lake to Ear Falls by Hydro One, to facilitate East-West power transfers. • Musselwhite Mine Line - Line M1M at Musselwhite Mine is a privately owned line and is the main connection point at the east end of the loop. It was assumed that negotiations with Goldcorp Inc. could take place to allow connection of the transmission extension to this line, thus providing an alternate supply path for Musselwhite Mine. • Musselwhite Mine SVCs - The mine would also provide additional VAR support to the loop via its two SVCs. Like the use of M1M, the cost associated with the VAR supplied by the SVCs at the mine site has not been taken into account. • Private Line from Red Lake to Pikangikum - This is a privately owned line and is being built to 115-kV standards, but will be operated at 44-kV. Since this is a privately owned line, no assumptions can be made as to the availability of this line to operate at 115-kV at some time in the future. Therefore, for purposes of this study, this private line is considered to be unavailable and any proposed concept will be built in parallel with this 44-kV line. However, a cost allowance has been included for a substation at Pikangikum to provide a backup supply if the privately owned 44-kV line is out of service. Page 13 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 6.0 Study Results 6.1 Configuration Options The following interconnection options were identified for study: Option 1: Option 2: Option 3: Option 4: Option 5: Isolated or independent supply systems; Supply loop connected to the grid at Red Lake; Supply loop connected to the grid at Musselwhite Mine; Supply loop connected to the grid at both Musselwhite and Red Lake; and, Supply arc connected to the grid at Musselwhite and Red Lake. The study was performed in two stages. First, the options were evaluated for their: 1) 2) 3) 4) Construction costs; Operational reliability levels; Abilities to develop local generation sites; and Impacts on the IESO controlled grid, including power import from, and power export to the grid. Promising options were then assessed for their: 1) Ability to provide power to as many First Nations communities as possible; 2) Overall transmission lengths; 3) Steady-state performances, when operating as part of the Eastern interconnection; 4) Road access for construction and maintenance; 5) Proximity to both hydro and wind potential development sites; and, 6) Impacts on existing and future mining loads in the area. For a fair comparison between the options: • Fort Severn, Marten Falls and Peawanuck in the far North-East have not been included in the analysis at this time and their costs have been evaluated separately; and, • The four communities east of Pickle Lake (near Lake Nipigon) are assumed to be connected to the presumed extension of the Hydro One planned Lake Nipigon – Little Jackfish 230-kV line (see Section 5.2). Page 14 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities In the following sections, the characteristics of each option are discussed. Independent Supply Loop G G G G G= Generation resources IESO-Controlled Electric Power Grid Fig. 6.1: Option 1 - Isolated Supply Loops or Independent Systems 6.1.1 Characteristics of Option 1 Figure 6.1 shows, at a conceptual level, configurations that belong to Option 1. These configurations have the following general characteristics: • They are very long (> 1500 km) and, consequently very expensive; • They require the presence of diesel generators until local generation resources are sufficiently developed; • They do not offer options for importing power or exporting excess generation to the south; • They require an independent “command & control” system for their operation; Page 15 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities • • They provide little economic incentive to IPPs to develop generation resources in the area beyond the local demand; They still need to keep and operate the diesel generators, since: o Hydro generation in the area will be largely seasonal; and, o They will provide on and off line reserves to maintain supply reliability. Note that, for this option, it is possible to reduce reliance on diesel generators by combining hydro generation with some wind power. However, that will not allow disposing the diesel generators entirely, as wind power is also intermittent. Furthermore, in an isolated power system, wind power can only come at the expense of making system frequency control a major operating challenge. For the reasons listed above, Option 1 is considered to be impractical. Supply Loop Red Lake E2R Ear Falls IESO-Controlled Electric Power Grid Fig. 6.2: Option 2 - Supply Loops Connected at Red Lake Page 16 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 6.1.2 Option 2 Characteristics A conceptual representation of transmission configurations falling under Option 2 is shown in Fig. 6.2. The general features of configurations belonging to this category include: • Being expensive, since: • • • • • • Their transmission network is typically very long (> 1500 km); They require use of large conductors and high transmission voltages to allow transmission of power to remote loads while keeping transmission losses low; They require extensive VAR compensation at multiple points; They need many substations converting transmission voltage to distribution voltages and housing VAR compensation facilities; and They provide ability to export/import power from/to the IESO controlled grid. However, the ability to export power is limited by the capacity of line E2R. Offering low levels of power supply reliability since: • • Loss of the line connecting them to the power grid turns them into islanded systems, with potentially significant load-generation imbalances; and Loss of any line segment close to the power grid interconnection point (within the loop) turns them into longitudinal transmission systems which, for large demands, are vulnerable to voltage collapse. Although configurations belonging to Option 2 do not have the key drawback of those falling under Option 1 (i.e. being an isolated system), still they are considered unattractive because of their relatively high cost and poor reliability. Page 17 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Supply Loop Musselwhite Mine M1M Pickle Lake IESO-Controlled Electric Power Grid Fig. 6.3: Option 3 - Supply Loops Connected at Musselwhite Mine 6.1.3 Option 3 Characteristics The configurations belonging to this category are fundamentally similar to those belonging to Option 2 and share the same characteristics. However, they differ from Option 2 configurations in the following respects: • • • They are connected to the power grid via 115-kV line M1M, owned by Musselwhite Mines/Goldcorp; Voltage support at Musselwhite Mine is provided by two SVCs; and Pickle Lake substation will be supplied by the 230-kV line from Nipigon via Little Jackfish, which is a stronger source than Red Lake. Option 3 configurations are therefore unattractive for the same reasons listed for Option 2 (i.e. they are expensive and have poor reliability). Page 18 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 6.1.4 Option 4 Characteristics The level of reliability offered by the configurations belonging to Option 4 is obviously much higher than those belonging to Option 2 and Option 3. This is reflected in the fact that they can lose connection to the grid at one point and still remain connected to the grid at the other point. They can also import/export power to and from the grid at two locations. However, they remain expensive due to: • • • Their long line lengths (> 1500 km); Their need for extensive VAR compensation at multiple points; Their need for large conductors and high transmission voltages to keep losses low and allow for higher power transfers; and While Option 4 offers an improvement in reliability over Options 2 and 3, it is still relatively expensive. Supply Loop Red Lake Musselwhite Mine E2R M1M Ear Falls E4D E1C Pickle Lake IESO-Controlled Electric Power Grid Fig. 6.4: Option 4 - Supply Loops Supported at both Ear Falls and Musselwhite Page 19 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 6.1.5 Option 5 Characteristics The transmission configurations falling under Option 5 are made up of a supply backbone (arc) with the following specifics: • • • • • • They pass through regions with high potential for hydro and wind generation and mining developments; They exploit existing roads in the area, where possible; They have shorter transmission lengths; They need VAR compensation at a few points; They have low built and maintenance costs; and, They provide alternative sources of power supply to most connected communities Supply Arc Red Lake M1M E2R Ear Falls E4D E1C Musselwhite Mine Pickle Lake IESO-Controlled Electric Power Grid Fig. 6.5: Option 5 - Supply Arcs Connected at both Red Lake & Musselwhite and Complemented by Radial Lines Page 20 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 6.1.6 Cost Comparison for Different Solutions Table 6.1 provides a high level comparison of the main factors influencing the cost of different solutions. The table indicates that the costs of solutions that belong to Option 5 are generally lower than those falling under other options. This is irrespective of higher levels of transmission losses for Option 5 solutions, as losses happen to constitute only a small fraction of the overall system cost for any of the options. Table 6.1 - Influences of Various Cost Factors on Different Solutions Cost Factor Overall 115-kV Length Overall 44-kV Length Line Maintenance Transmission Losses 115-kV Substations VAR Compensation Option 1 Option 2 Option 3 Option 4 Option 5 >1500 km >1500 km >1500 km >1500 km ≈795 km ≈210 km ≈210 km ≈210 km ≈210 km ≈565 km High High High High Moderate Moderate Moderate Moderate Moderate Moderately High 21 21 21 21 16 High High High High Moderate 6.1.7 Comparing Reliability of Different Options A comparison of the key factors affecting operational reliability of the different configuration options is provided in Table 6.2. Obviously, it is possible to make any supply system, including those falling under Option 1, sufficiently reliable by extensively developing its local generation resources and interconnecting them to the demand points. However, since such developments are often uneconomic, it is reasonable to assume only a moderate level of local generation development for all options. In that case, Table 6.2 clearly indicates that those solutions belonging to Option 4 have higher levels of reliability, followed by those belonging to Option 5. Those demand points that are directly connected to the supply arc of Option 5, enjoy almost the same level of reliability as their counterparts in Option 4. On the other hand, demand points served by radial lines in Option 5 have obviously lower operational reliability. Page 21 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table 6.2 - Impacts of Key Reliability Factors on Different Configurations Reliability Factor Option 1 Option 2 Option 3 Option 4 Option 5 Overall 115-kV Length Power Grid Connection >1500 km >1500 km >1500 km >1500 km ≈795 km None At Red Lake At MWM Import/Export Capability None Reserve Generation Capacity Limited by power demand of FN communities Limited by E2R capacity Limited by FN demand & E2R Limited by M1M capacity Limited by FN demand & M1M At Red Lake & MWM Limited by E2R & M1M capacities Limited by FN demand, E2R & M1M At Red Lake & MWM Limited by E2R & M1M capacities Limited by FN demand, E2R & M1M 6.1.8 Recommended Configuration Concept Since reliability of any supply system can be raised to any desired level by ignoring the costs involved, the recommendation of the preferred configuration has been made in the context of the information provided by both Tables 6.1 and 6.2. Table 6.3 brings together the cost and reliability aspects of the various options, allowing one to consider possible compromises between these two aspects for each option. Table 6.2 - Comparison of Overall Cost and Reliability of Different Options Key Items Option 1 Option 2 Option 3 Option 4 Option 5 Build Cost Very High High High High Moderate Operation & Maintenance Cost Very High High High High Moderate Supply Reliability Low Low Low Relatively High Moderate Despite lower transmission losses for Options 1 to 4, their O&M costs are significantly higher than those of Option 5, due to their significantly longer Page 22 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities transmission systems. The most reasonable compromise between cost and reliability is then offered by solutions falling under Option 5, as they have moderate build and O&M costs, and at the same time, provide a reasonable level of reliability for most demand points. Based on this conclusion, the focus of the study from this point forward has concentrated on those interconnection solutions that belong to Option 5. The category of solutions represented by Option 5 is made up of a “backbone” and a number of radial lines. The cost of building the backbone is relatively low, since it can have a relatively short length and can be operated with medium transmission voltages and does not need VAR support at many points. Also, the cost of radial lines is much lower, as they can be operated with lower transmission voltages; require smaller conductors, and less expensive support structures. At the same time, their VAR support requirements can be much lower during normal operation. Reliability of supply for Option 5 solutions depends on the connection type; that is, one achieves good reliability for backbone-connected loads and slightly lower reliability for radially-connected loads. 6.2 Recommended Transmission Concept As part of this study, several Option 5 systems were formed and analyzed. The analysis included filtering out transmission concepts that did not directly serve a large number of First Nation communities, and/or had little proximity to significant hydro generation resources, existing and future mining areas, or access roads. In the filtering process, proximity to potential wind generation sites has not been weighted as heavily as those for hydro sites, since soil conditions at many sites with high wind potential are not amenable to development of wind power facilities. Furthermore, maintenance of such facilities is expected to pose a significant logistical challenge, considering the sites’ remoteness and limited accessibility. The systems that survived the filtering process were then subjected to power flow analysis to assess their steady-state performance. For the chosen voltage levels and equipment, the analyzed systems in general performed quite well under normal operating conditions. Among them, the system with the shortest transmission length is shown in Figure 6.6. That is the configuration recommended in this study. Page 23 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Bearskin Lake Sachigo Lake Kitchenuhmay Wapekeka Kasabonika Lake Muskrat Dam Wawakapewin Sandy Lake Keewaywin Weagamow (NC) Wunnumin Kingfisher Lake Nibinamik Webequie Bear Head Lake North Spirit Lake Neskantaga Musselwhite Deer Lake 115 kV private line Poplar Hill Eabametoong Pickle Lake Albany River Pikangikum 44 kV private line Little Jackfish Red Lake 44kV 115kV HONI 230kV Hydro Substation Whitesands Gull Bay Wind Farm Tap Fig. 6 6: The Recommended Configuration (Option 5) The recommended transmission concept consists of a 115-kV backbone system approximately 795 km in length with 44-kV radial lines. Its backbone directly passes through 12 communities and it connects an additional 9 communities via its radial lines, while passing by regions with high potential for hydro and mining developments. Implicit in selecting the proposed transmission concept are the assumptions outlined in Section 5.2. A key assumption of the recommended configuration is the extension of the Hydro One planned Lake Nipigon – Little Jackfish 230-kV line from Little Jackfish to Pickle Lake. In the absence of this extension, other alternatives for Page 24 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities connecting the four communities supplied by the 230-kV line have to be considered. This could include extension of the 115-kV backbone southward to include the Musselwhite 115-kV private line and a 115-kV line segment connecting Pickle Lake to Little Jackfish. It is assumed that the new private line from Red Lake to Pikangikum will not be available to become part of the proposed supply arc. However, the proposed concept includes a substation at Pikangikum to provide a backup supply should the 44-kV private line be out of service. The system was also analyzed with the 44-kV Pikangikum load being supplied by the proposed concept to ensure that it can be supplied within the operating limits of the concept. Options for connecting the remaining three communities (Fort Severn, Marten Falls and Peawanuck) to the power grid have also been considered in this report (see Section 7.3). Page 25 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 7.0 Proposed Concept Details Based on the proposed configuration (Fig. 6.6), 21 remote communities will be connected to the power grid through: o A 795 km 115-kV transmission system backbone with termination points at Red Lake and Musselwhite Mine; o 44-kV radial lines off the proposed backbone; and o 230-kV HONI transmission line extension (see Section 6.2). The proposed configuration connects these communities and supplies their 2029 peak demand with significant additional transmission capacity for future demand growth. The total demand of these 21 communities is roughly 91% of the off-grid electric power demand. Connection of the remaining 3 distant communities, which have the remaining 8.6% of the demand, is discussed at the end of this section. 7.1 Backbone and Radials The proposed configuration requires a 115-kV backbone which should be adequate for the amount of power that is expected to be transferred to the south. This is based on the fact that there are only about 200 MW of hydro generation capacity within the area (excluding those in the Northeast and James Bay area) and, at this time, the prospects for serious development of wind power resources in the area appear to be small. By 2029, assuming extensive development of hydro generation sites in the area, the 200 MW of generation will be largely consumed by the loads of the communities as well as the mining loads in the area (including loads at Musselwhite Mine and Red Lake), and the surplus power that would be available to export would not exceed 60 MW. The 44-kV lines are used mostly to connect sites that are not more than 150 km away from the 115-kV backbone. The losses in this case are relatively low, as the size of the demands are small. Significant generation is assumed to be built around the backbone, rather than at the end of radial lines. Table 7.1 contains the communities’ connectivity and forecasted 2029 peak load data. Details on the length of transmission line segments forming the concept are provided in Appendix B1. Page 26 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table 7.1 - Summary of Proposed Community Connections Community Keewaywin (Couchiching) Marten Falls Nibinamik/Summer Beaver Pikangikum** Poplar Hill Wawakapewin Peawanuck Keewaywin (Niska) Eabametoong Muskrat Dam North Spirit Lake Wunnumin Bearskin Lake* Kitchenuhmaykoosib Inninuwug* Deer Lake* Fort Severn* Kasabonika Lake* Kingfisher Lake* Landsdowne House/Neskantaga* North Caribou Lake/Weagamow* Sachigo Lake* Sandy Lake* Wapekeka* Gull Bay* Whitesands* Webequie* Totals for each connection type (in kW) 2029 Total off‐grid demand ( in %; based on 38,772 kW total) Demand On 115-kV (kW) Demand On 44-kV (kW) Demand On 230-kV (kW) Supplied by Other Means (kW) 1205 884 (2625) 1018 134 750 643 1942 1299 1125 1698 1838 3016 1803 1395 2071 1307 1626 6123 932 2572 2063 1658 549 1120 21,105 9,079 5,237 3,351 54.4% 23.4% 13.5% 8.6% *Serviced by Hydro One Remote Communities Inc. ** Load at Pikangikum is not included in the proposed concept, however, the system proposed is capable of acting as a backup to the private line serving Pikangikum Page 27 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 7.2 System Performance Analysis The performance of the proposed transmission concept has been studied under a variety of situations, including different load and generation levels and specific lines being out of service (contingency cases). The goal was to confirm the robustness of the proposed concept for operating as an integral part of the IESO controlled transmission system. The details of the scenarios and the results are given in Appendix B2. A summary of the system performance is provided below: • The proposed transmission concept performs quite well under normal operating conditions. The loadings of transmission facilities stay well within their set thermal limits for all tested scenarios. • There is need for reactive support at three points within the supply arc to maintain an acceptable voltage profile, under different loading conditions. Transmission losses were generally small, irrespective of the fact that more than 500 km of lines are operating at 44-kV. The performance of the system following a single line outage was also analyzed for seven key contingency cases (see Appendix B2 for details). In general, the system performs satisfactorily following the loss of any line belonging to the arc. For line outages occurring within the IESO-controlled power grid, the results remain encouraging as long as some local generation resources are present. In the absence of any local generation, for two contingency cases there are no power flow solutions, indicating that it could become difficult to operate the system under those conditions. Three remedies are proposed for the above problem: 1) Coordinating development of key local generation resources with building of the proposed transmission concept; 2) Using Special Protection Schemes (SPS); or, 3) Re-enforcing the two problematic lines. These solutions should be further investigated as part of a much larger, in-depth, study. 7.3 Unconnected Remote Communities The engineering and financial analyses of the proposed transmission concept did not include power supply to Fort Severn, Peawanuck and Marten Falls at this time. Page 28 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities However, the possibility of connecting these communities using a 115-kV extension from the backbone system does exist and can be investigated. An estimate for connecting these communities is shown in Table 8.3, but it is assumed at this point, that the cost is prohibitive. Connection of these three communities would be the subject of further study. Also, Pikangikum will be connected by a privately owned 44-kV line and has not been included in this concept. Never-the-less, the proposed concept is designed to provide a backup supply when the private line is out of service. 7.4 System Implementation The proposed system could be completed in three phases: • • • Phase 1 - build the 115-kV backbone (estimated time: 5 years) Phase 2 - build the 44-kV radials (estimated time: additional 2 years) Phase 3 (optional) – connect distant communities (estimated time: additional 2 to 3 years) Development of generation resources is understood to be undertaken by IPP’s and should be encouraged to be concurrent with Phase 1, as much as possible. Page 29 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 8.0 Costing the Proposed Configuration In arriving at the estimated cost of the proposed solution, the following were considered: • Costing of required capital for constructing the transmission lines forming the selected transmission solution, based on the line voltage level, conductor type and wood pole structure details; • Costing of the required substations, including breakers, transformers, and shunt devices for voltage/VAR support, while considering the required level of equipment redundancy; • Costing of the line losses over a 20 year period, based on an assumed daily load profile; • Costing of the transmission system maintenance based on the lines’ lengths and their probable number of outages per year; and • Costing of the roads to be built to allow transporting transmission equipment to construction sites and later access to equipment for maintenance purposes. 8.1.1 Line and Equipment Cost Breakdown Table 8.1 provides a cost breakdown for the proposed concept, identifying the installed cost of major system components. Fibre has been included as a component of the proposed system. However, the activation of this fibre will depend on the availability of appropriate equipment at the termination points at both ends of the proposed system. Page 30 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table 8.1 - Cost Breakdown for Recommended Option: Backbone with Radial Connections to Communities (Installed Cost) System Component 115-kV backbone system 44-kV radials No/Length Unit Cost ($ 000’s) Total Cost ($Millions) 795 km 200 159.0 495 km 83 41.1 Substations (see Appendix D) Additional Cost for Redundancy Fibre (backbone) 67.5 38.5 795 km Fibre (radials) 495 km Fibre (Musselwhite to Pickle Lake) Fibre Equipment: (Red Lake and Nipigon) 186 km (Bear Head, Muskrat Dam, Wunnumin, Albany River, Little Jackfish) 5 units 6.0 4.8 6.0 2.97 15.0 2.79 360 0.72 720 3.6 2 units Total Estimated Cost *Class C cost estimate Page 31 $320.9* Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The following options in Table 8.2 and Table 8.3 are related to Option 5 and are shown for information purposes only and are not considered in the final costing analysis. Table 8.2 - Option 5 Backbone Only - without Radial Connections to the First Nations Communities System Component 115-kV backbone system Substations (see Appendix D) Additional Cost for Redundancy Fibre (backbone) Fibre (Musselwhite to Pickle Lake) Fibre Equipment: (Red Lake and Nipigon) (Bear Head, Muskrat Dam, Wunnumin, Albany River, Little Jackfish) No/Length Unit Cost ($ 000’s) Total Cost ($Millions) 795 km 200 159.0 53.2 28.3 795 km 6.0 4.8 186 km 15.0 2.79 2 units 360 .72 5 units 720 3.6 Total Estimated Cost *Class C cost estimate Page 32 $252.4* Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table 8.3 - Additional Cost of Connecting Marten Falls, Peawanuck and Fort Severn System Component 115-kV line: • Marten Falls • Peawanuck • Fort Severn Substations (Cost of Redundancy not included) Additional Fibre Fibre Equipment: (Kasabonika Lake and Eabametoong) No./Length Unit Cost ($ 000’s) Total Cost ($Millions) 190 km 270 km 200 km* 200 200 200 38 54 40 13.2 660 6.0 2 units 720 Total Estimated Cost 3.96 1.44 $150.6* *Part of cost already included in Peawanuck connection, Class C cost estimate 8.1.2 Operation and Maintenance Cost Estimation Operation and maintenance costs are assumed to be 2% of equipment capital cost. This is more than normally allowed for O&M costs, but due to the problematic access conditions for maintenance, this seems like a more realistic estimate. 8.1.3 Transmission Loss Estimation Line active losses for the proposed concept were determined for a number of generation and load scenarios. The calculated 2029 losses and their associated costs, based on a basic daily load profile, are shown in Table 8.4 and Table 8.5 Page 33 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table 8.4 - Losses of the proposed transmission concept under two load levels, with no local generations Local Generation (MW) Total Power Demand (MW) Net Active Power Export (MW) Active power Loss (MW) 38.05 - 41.1 3.05 19.02 -19.6 0.58 0 Table 8.5 - Annual cost of losses for the proposed transmission concept, under conditions of Table 8.4 Local Gen. (MW) 0 Demand Period Daily Duration (hours) Daily Energy Loss (MWH) Electricit y Rate ($/MWH) Annual Cost (M$) On-peak 8 24.40 75.00 0.67 Off-peak 16 9.28 75.00 0.25 Total Annual Cost (M$) 0.92 The losses are calculated with the assumption that there are no local generations (i.e. all required power is imported from the IESO-Controlled system). The on-peak demand is assumed to be 38.05 MW, lasting 8 hours, while the off-peak demand (or base load) is set at 50% of the on-peak demand (i.e. 19.6 MW) and assumed to last for 16 hours. Page 34 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 9.0 Cost Comparison of Existing and Proposed System In order to compare the costs of maintaining and upgrading the diesel generation systems in each community with that of the cost of constructing a high voltage transmission line to connect these communities to the provincial grid, it is necessary to determine the approximate costs associated with this remote system, and the approximate costs of constructing a transmission line. The costs of the remote system are broadly divided into two categories, the HORCI communities, which receive various known subsidies, and the IPA communities, for which the total amount of subsidies are not available. The HORCI system receives two broad categories of subsidy, the Remote and Rural Rate Protection (RRRP) and an indirect subsidy through the higher rates charged to Standard “A” customers. These cost estimates are pro-rated to only include those communities that will be connected to the proposed grid, so the total RRRP subsidy shown here is not the actual total RRRP subsidy provided to HORCI. The demand of Pikangikum, Marten Falls, Fort Severn, and Peawanuck are not included in the model for this reason. 9.1 HORCI Subsidy The Remote and Rural Rate Protection (RRRP) subsidy is paid through the Ontario rate base as part of all Ontario electricity consumers’ bills. This socialized cost creates a “postage stamp” price for energy and transmission across Ontario, which means that all customers pay approximately the same price, regardless of their location, or the higher cost of providing service to the customers. The value of the RRRP awarded to HORCI in the EB-2008-0232 OEB decision order is $27 895 000. Based on the projected generation by HORCI, this amounts to a subsidy of $0.51/kWh. HORCI charges different rates to institutional customers (customers that receive funding from the provincial or federal government) than similar institutions would pay in a grid connected community. These rates are significantly higher than in IESO grid connected communities, especially in air access only communities, and range from $0.55/kWh to $0.88/kWh. The difference between the rate paid by institutional customers in IESO grid connected communities and the rate paid in remote HORCI communities is an effective subsidy paid by the institutions. In most of these communities, this is paid by the Federal government, through its support for band owned buildings, hospitals or nursing stations, water treatment plants, teacherages and schools. The provincial institutional customer base in most of these Page 35 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities communities is generally limited to the airports and some health facilities. The analysis of the value of this effective subsidy is based on a total cost of energy in IESO communities of $0.17/kWh. This cost is an inflated estimate of a standard electricity service charge using $0.13/kWh for energy, and $0.04/kWh for transmission, distribution, and other charges. Based on the average Standard A rate paid in HORCI communities of $0.86/kWh, there is an indirect subsidy of $0.69/kWh paid by the institutional customers. Standard A customers consume approximately 20% of the energy generated by HORCI, and supply approximately 70% of the revenue. The total number of kilowatt hours used by HORCI communities in 2009 (projected data) in this study is more than 48 000 000 kWh. The kWh figure is derived from a projection of the 2004 use to 2009 based on the 4.02% growth rate indicated earlier, and then from 2009-2029 the same growth rate is projected into the future and the usage is summed. The potential line and radial lines do not connect the communities of Peawanuck, Fort Severn, and Marten Falls, and they have been removed from the analysis by deducting their contribution to the total kWh figure. Pikangikum is expected to also be connected to the grid via a private line and its consumption has also been excluded. The effective subsidy provided to HORCI communities is a combination of the RRRP and the indirect Standard A subsidy. The value of these subsidies is shown below. Table 9.1 - HORCI Subsidies (All figures, 2009 $) HORCI 2009 kWh Subsidy value Total Subsidy ($millions) RRRP 48 686 519 $0.51 $ 24.9 Std A Subsidy 9 737 304 $0.69 $ 6.7 Total Subsidy, 2009 HORCI 2009-2029 RRRP Std A Subsidy kWh $ 31.6 Subsidy value Total Subsidy ($millions) 1 559 892 463 $0.51 $795.6 311 978 463 $0.69 $215.3 Total Subsidy 2009-2029 Page 36 $1,010.9 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The total expected value of the subsidy is projected to rise with the growth in consumption in the communities over the 20 year period. The price of diesel fuel has been held constant throughout the period, owing to the uncertainties in predicting diesel fuel prices far into the future, and this is considered to be a conservative assumption. The efficiency of the system has also been held constant. The total value of the RRRP subsidy requested in the 2009 rate application is only enough to cover the predicted cost of fuel for the year. The cost of fuel for generation, including delivery, in HORCI systems averages $0.423/kWh, with the RRRP subsidy valued at $0.51/kWh. There are also significant costs associated with operations, maintenance, and administration of the distribution system, the generation assets, as well as upgrades and emergency repairs. These other items raise the total cost per kWh within the HORCI communities to $0.778. 9.2 IPA Subsidy Costs As previously noted, there is significantly less information available from the IPAs on their actual costs, revenues, and operations. A significant amount of the analysis here relies on the assumption that the IPAs operate at a similar level of efficiency, and with similar technology to HORCI communities, which may not be true. HORCI is likely able to operate at a lower cost per kWh because it has a larger customer base, and easier access to bulk fuel purchases. However, the best and most conservative assumption is to assume the same cost of generation in both types of systems, $0.778/kWh. IPAs are not regulated by the Ontario Energy Board. This means that they can set their own rates and standards. As a result, the rates charged, and revenue earned per kWh varies significantly between the IPAs. The range in revenue for IPAs ranges from $0.19/kWh to $0.49/kWh, based on best estimates. The average rate charged to residential customers is approximately $0.12/kWh, and to institutional customers, $1.06/kWh. As there is no general subsidy paid to the IPAs, like the RRRP, it is more difficult to estimate the total amount of subsidy paid to the IPA’s. The analysis here approximates the subsidy based on the difference between the rate paid by the residential customers and the estimated cost of generating the energy, based on the HORCI data provided in EB-2008-0232. The IPAs cannot operate at a loss continuously, and must make up the difference somehow, either through accessing funding from other programs, such as Welfare, Education, or First Nation administration, or through the rates charged to institutional customers. The effective subsidy in this case is based on the difference in the cost to generate a kWh of energy, and the effective revenue earned from that kWh when it is sold to Page 37 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities consumers. The difference between the revenues earned in the IPAs through the average residential rate of $0.12/kWh and the cost of generation is the effective subsidy. This amounts to $0.66/kWh. There is a secondary indirect subsidy provided by government customers, in the same manner as in HORCI communities. However, the rate charged to these government users is higher in the IPAs than is charged to the Standard A customers in the HORCI communities, so the effective subsidy rate is $0.89/kWh, which is the difference between the average rate charged in the IPAs, and the same rate that would be applied to an IESO grid based customer. Table 9.2 - IPA Subsidies (All figures, 2009 $) IPAs 2009 kWh Total Subsidy ($millions) Subsidy value Revenue Deficit 26 215 818 $0.64 $ 13.4 Government User Subsidy 5 243 163 $0.89 $ 4.7 Total Subsidy, 2009 IPAs 2009-2029 kWh $ 18.1 Total Subsidy ($millions) Subsidy value Revenue Deficit 839 942 095 $0.64 $537.6 Government User Subsidy 167 988 419 $0.89 $149.5 Total Subsidy 2009-2029 $ 687.1 The total subsidy provided to the IPAs over a 20 year period totals more than $680 million. 9.3 Upgrade of Diesel Generation The final cost associated with the diesel generators in the remote communities is the continued need to add to or upgrade the generation systems in each community to match the growth in population and demand. A conservative estimate of the cost of demand related upgrades and replacements in all remote communities is Page 38 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities approximately $4000/kW to complete, based on best available information. We do not include in the calculations the cost of overhauls and significant maintenance, as the HORCI numbers include these elements in their rate base and our part of their normal operations and maintenance costs. The impact on the IPA’s is not calculated, however, it would result in an increase in the overall cost, as generally, the planned overhauls are not included in the IPA’s rate base. The estimates of growth in the remote communities, compared to the available capacity in these communities, suggests that demand-based upgrades of approximately 20 MW will be required in the remote communities over 20 years, which averages 1 MW per year. The total cost of these upgrades is thus estimated to be $4 000 000 annually. This has been added to the total cost of the diesel system. However, this cost has not been included in the final calculations because it may be advisable to utilize this small capital funding to ensure the current systems within the communities are maintained in the event of an emergency requiring backup power should grid based power be interrupted. This will be of most concern to the several communities that are on the radial lines, for which a disruption is more likely. The diesel systems would not necessarily be maintained or upgraded in such a way as to provide the full community with power, but would provide enough power to meet the emergency needs of a community. 9.4 Other Costs Associated with Diesel Generation There are other costs associated with the diesel system that are more difficult to quantify, and have not been included in the economic model. However, they may be significant and would increase the costs. The environmental liability of operating and maintaining the diesel generation systems in these communities is extremely high. Millions of litres of diesel fuel are transported annually on winter roads, or by barge or air in some cases. There is the possibility of fuel spill during the transportation, transferring, and storage. The cost of a single large spill could be massive as these communities are remote, and have little capacity to clean up from a spill. The cost of emissions generated by diesel consumption is also likely to increase. Although currently there is no carbon tax in Ontario, the environmental cost of diesel consumption and emissions is likely to become a factor at some point in the future. The current proposal for a cap and trade system must consider the amount of emissions generated by this consumption of diesel. In 2009, the communities as a whole were predicted to use 25 million litres of diesel. Over the 20 year period of 2009-2029, the communities are expected to consume more than 750 million litres of diesel fuel. The emissions generated by diesel are almost 4 times the amount Page 39 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities generated by the current generation assets employed by Ontario (.88 tonnes CO2/MWh vs .22 tonnes CO2/MWh see: http://www.ec.gc.ca/pdb/ghg/inventory_report/2005_report/ta9_7_eng.cfm using the average for the grid overall and the average for refined petroleum products). Although Ontario does not have a carbon tax like British Columbia, it is participating in the Western Climate Initiative which will bring Cap and Trade legislation, and effectively may place a value on emissions. Using the best available data, in this case British Columbia’s carbon tax values of between $10/tonne and $30/tonne, the value of the emissions offset for 20 years would range from $17 million to $52 million in 2009 dollars. There is also the potential for continued large and rapid increases in the price of diesel fuel, especially if global consumption continues to rise, and oil discovery and extraction continues to decrease, also called peak or plateau oil. This situation is very difficult to predict, but the cost of diesel fuel may experience significant increases in the relatively near future. 9.5 Existing System Cost Summary The total subsidy provided to the remote communities through the RRRP program, the rates charged to institutional customers, and the deficit in revenue from IPA residential customers, is large, totaling more than $49,000,000 in 2009, and rising to more than $100,000,000 in 2029. The cumulative value over the 20 years is more than $1.5 billion in effective subsidies. 9.6 Financing New Facilities Connecting the remote communities to the IESO controlled grid would eliminate these costs, although it would take time to construct the necessary transmission infrastructure and ensure that all communities are upgraded to the necessary specifications. The current Green Energy and Green Economy Act, and the associated regulatory changes may create changes in the transmission system as well. It has been argued by investors in transmission infrastructure that the current rates of return for electricity transmission are too low to attract new capital. The rates are currently around 8.83% for equity, and 6.25% for debt. The return on equity is based on a formula that provides a premium of 3.80% on top of a discounted Government of Canada 10 year bond forecast. Page 40 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities For the purposes of this research, the return on equity has been inflated to account for potential increases due to increasing bond rates, and to ensure that the investment appears lucrative for the potential investors. The rate has been set at 11.50% which is higher than almost all rates of return in North America in the gas and electricity utility sector (see comments by Hydro One Networks Inc. in response to the OEB’s updated Cost of Capital parameters of February 24, 2009, EB-20090084). The return on debt has been set at 7.62% based on the proposed rates identified in the OEB Cost of Capital Parameters of February 24, 2009. The remaining assumptions are based on the current structure for transmission assets in Ontario. The Debt to Equity ratio is set at 60:40. The asset depreciates in a straight line for 40 years at 2.5% annually, reaching zero book value at year 40. The debt is amortized over 40 years, reaching zero in year 40. Operations and maintenance is set at 2% annually, and is shown without inflation, in order to match the assumptions of the diesel generation model. 9.7 Cost of Proposed Transmission Line vs. Existing Diesel Generation Using the proposed line and infrastructure shown in Fig. 6.6, the cost of building, operating, and maintaining these assets would be approximately $37.4 million in 2009. There is a potential variance in the total cost annually based on the cost of operations and maintenance, although in this model this cost has been estimated at a relatively high value of 2% of capital cost. Over 20 years, the cumulative cost would total $709.6 million. This shows no inflation, and also does not consider the cost of any upgrades to the line. The initial costs for the system are shown in Table 8.1 and are estimated to be $320.9 million. Page 41 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The current Transmission System Code rate of return, and thus the cost to the rate payers, of transmission assets is based on the book value of the asset, which depreciates over 40 years to a zero book value. This results in a decrease in total cost annually for 40 years at a relatively slow pace. As the following table indicates, the construction of a transmission concept linking these communities to the IESO controlled grid is economically advantageous for Ontario, Canada, and the rate payers in the long run. The growth rate for the diesel generation system is modeled to slow to 2.5% annually after 2029. Table 9.3 - Cost Comparison Summary (in $ Millions) Supply Option Annual cost in 2009 Annual Cost in 2029 Cumulative Cost 2009-2029 Diesel Generation system $ 49.7 $ 109.3 $1 591.5 Transmission Concept $ 37.4 $ 30.2 $ 709.6 The annual cost of the diesel generation system will require continuous investment to cover the increased demand on the system due to population growth and growth in household demand. The difference in annual and cumulative costs favors the construction of a transmission line immediately. Over 20 years, the savings begin to appear between the two systems, totaling more than $800 million. Even assuming a massive cost increase in the transmission infrastructure, 100% or more, the transmission system remains the lower cost option over 20 years. Continued maintenance on the transmission assets will be ongoing, and will accelerate in the latter years of the period, but it is only a fraction of the expected cost of the subsidies provided to the remote diesel systems. The total subsidy that is used to maintain the diesel generation system is buried in several items. The most direct subsidy is the RRRP program, which currently provides the single largest subsidy to the remote communities within the Hydro One Remote Community system. This subsidy is paid by the rate base of Ontario as a whole. There are also subsidies paid indirectly by the federal and provincial Page 42 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities governments in the remote communities, whether HORCI or IPA communities. The institutional rate charged is far above the rates these entities would pay in grid connected communities, and is subsidized by the tax payers of Ontario and Canada. Finally, there is an apparent structural deficit for the Independent Power Authorities, which will only become more acute and unsustainable as the communities grow and demand more power. This deficit can not be maintained, and is likely paid for by other programs and other budgets, such as from education, health, and operations, or from emergency funding from Indian and Northern Affairs. This revenue deficit, the difference between the costs and the revenues, represents a large and growing indirect subsidy. Finally, it is important to note that none of these calculations consider the price of diesel increasing, and thus the potentially increasing cost of generation, nor do these calculations consider the environmental liability of maintaining these systems. The cost of a single large scale spill in a remote community increases the attractiveness of the transmission line, both for the community, and for Ontario. The Green Energy and Green Economy Act, and the proposed Environmental Protection Amendment Act (Greenhouse Gas Emissions Trading) 2009 suggest that Ontario will be seeking a variety of measures and methods to reduce the dependence on fossil fuels. While these communities may be small, and the overall energy consumption a small fraction of the total used in Ontario, the diesel system is four times as polluting in terms of CO2 emissions. The value of these emissions, or their cost, is likely to increase, and an early removal of these emissions may be more cost effective. Page 43 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 10.0 Regulatory Impacts This section is included to identify a number of the key issues that the decision makers in the First Nations communities need to consider in their attempt to bring together the resources that will be needed to make the proposed transmission concept a reality. As these issues are complex and need to be presented along with their background information, the entire Appendix E has been devoted to them. To briefly summarize the issues, it must be understood that the high voltage electricity transmission system in Ontario is from a technical stand point, fully controlled by the Independent Electricity System Operator. From a financial standpoint, the Independent Electricity System Operator is regulated by the Ontario Energy Board. All of these agencies fall under the purview of the Minister of Energy and Infrastructure. It is also important to know that there are six transmitters in Ontario: Hydro One Networks Inc., Great Lakes Power, Five Nations Energy Inc., Niagara West Transformation Corporation, Cat Lake Power Utility Ltd. and Canadian Niagara Power. All of these transmitters have a license to operate anywhere within Ontario and all are able to make an application to the Ontario Energy Board to include the costs of new approved transmission projects costs in their rate base. However, the ability of an individual transmitter to move forward on any new project is tempered by the ability of the Minister of Energy and Infrastructure to issue strong directives (as outlined in the new Green Energy Act), regarding which transmission line(s) can be included into the transmission pool, and which transmitter or transmitters will be allowed to build, or compete to build, a particular transmission system that would be included in the regulated IESO controlled grid. This study shows that the connection of the majority of the remote communities is technically feasible, and would be a lower cost operation when compared to the estimated current cost of the diesel generation system. Therefore, the next step in developing the transmission supply option, would be to decide if the proposed grid will be a direct connect customer, or to work toward having the this new transmission line become part of the Ontario high voltage transmission system and included in the transmission pool. A direct connect system would bear all of the costs of building and operating the system and would spread those costs to its customers. A new system that is part of the transmission pool has the ability to subsidize its costs as they are spread across all Ontario rate payers. Page 44 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Advantages and disadvantages: • The pooled cost of transmission in Ontario is currently about $0.05/kWh vs. approx. $0.19/kWh in the direct connect option as identified in this study, • If there is a shortage of power, direct customers are the first to be shed or disconnected from the transmission system and regulated local distribution companies (mainly serving residential customers) are the last to be shed, • In a pooled system the cost of building, operating, and maintaining the system is included in Ontario wide pooled cost of transmission. The transmitter that operates the system receives its’ revenues from the IESO on a monthly basis beginning 30 days after the asset is operational, • To be part of the transmission pool a transmission company must accept regulation from the Ontario’s regulators (The Ontario Energy Board). Likely, any assets that are connected to the main Ontario transmission grid would have to submit to some controls (i.e. connection agreements with the IESO) for safety’s sake. Once a decision is made by the communities to be either a direct customer, or to become part of the Ontario transmission pool, a political strategy must be developed to support the proposed decision. Generally, the following key elements that would follow are: Direct Connect: • Funding applications to carry out a feasibility study and business plan • Completion of a detailed feasibility study and business plan that would include: o More accurate estimates of the costs to build and operate the system o More detailed system planning and design including route selection o Development of necessary financial system(s) o Development of management and technical capacity to operate and maintain the system o Development of operational policies and procedures so that power can be delivered to each community in a safe, reliable and cost effective manner, and o Determination of the appropriate kinds of business entities that will deliver power to community members and businesses, including decisions regarding ownership structures: Transmission company Independent power authorities which buy their power from the transmission company and reselling it in the community Or regional single entity serving all customers Or a regional entity comprising both transmission and distribution serving all customers Page 45 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities • • • • • Raising of the necessary funding to build, operate and maintain the line, Negotiations regarding the connection to the Hydro One Networks system. System Impact and Customer Impact Assessments would be completed by IESO and Hydro One Networks to ensure the project will not hamper the existing system and would identify any necessary upgrades to the Hydro One Networks System that will need to be undertaken, at the cost of the new direct connect customer, Application to be connected to the Independent Electricity System Operator grid which would involve connection agreements with the IESO Negotiations with Hydro One Remote Communities and the Independent Power Authorities to take over the distribution systems in their communities which may include distribution system assessments and environmental sampling to determine if there is contamination at the sites due to diesel fuel spills, and Provincial environmental assessment and possibly a federal EA if federal funding is part of the funding package. Pooled Transmission Option: • The political leaders would enter into discussions with the provincial government, seeking a directive from the Minister of Energy and Infrastructure indicating that a new transmission system to service the people of the remote communities in Northwestern Ontario is good for Ontario and should be included as part of the transmission pool, • The leaders need to put a process in place to undertake their due diligence in regard to the following questions about the electricity transmission solution for the communities. This due diligence process will answer, at minimum, the following questions: o How will the system be paid for? o How will the system be maintained? o Who will build operate and maintain the system? Partnership with and existing transmitter Development of a new transmitter to be licensed by the OEB Determine which transmitter best serves the needs of the people and invite them in to build the new line. • Funding applications to carry out a feasibility study and business plan • Completion of a detailed feasibility study and business plan that would include: o More accurate estimates of the costs to build and operate the system o More detailed system planning and design including route selection o Development of necessary financial system(s) Page 46 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities • • • o Development of policies and procedures so that power can be delivered to each community in a safe, reliable and cost effective manner, and o Determination of the appropriate kind of business entities that will distribute power to community members and businesses Independent power authorities which buy their power from the transmission company and reselling it in the community Or regional single entity serving all customers Application for a leave to construct with the Ontario Energy Board Provincial environmental assessment and possibly a federal EA if federal funding is part of the funding package Negotiations with Hydro One Remote Communities and the Independent Power Authorities to take over the distribution systems in their communities which may include distribution system assessments and environmental sampling to determine if there is contamination at the sites due to diesel fuel spills Page 47 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 11.0 Recommendations The recommended configuration, Option 5, should be subjected to further analysis once support or buy-in has been obtained from off-grid communities impacted, and they have agreed in principle to the routing and connectivity of the proposed transmission line. In making the decision to move forward with additional analysis of the proposed concept, the following benefits should be considered. The proposed concept provides remote communities with: • Reliable, safe electricity at a reasonable cost • Broadband fibre optic telecommunications (tele-health, distance education, high speed internet, cable TV, improved telephone service, etc.) if appropriate equipment is available at both termination points to the HONI network. • An electricity supply that is no longer an impediment for community growth, including building of: • Homes • Schools • Arenas • Community businesses • Construction jobs and spin-off economic benefits created during the building of the network • Long term employment opportunities in the local electricity systems: • skilled distribution tradesmen • power line trades staff • electricians • vegetation management • management & administrative staff • Opportunity for First Nations to have equity to share in the project • Lower environmental emissions The proposed project also enables: • Development of renewable generation projects– up to 200 MW of small hydro and wind projects identified in the area • Potential mining projects that are not economically viable without availability of an affordable electricity supply The following sections outline a process for moving this project forward with the First Nations communities. Page 48 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 12.0 Next Steps This section provides an overview of the recommended next steps for the project based on the recommended configuration contained in this report. Since both the technical and cost evaluation (Class C) presented in this report have been done at a preliminary level, additional follow-up analysis at a more detailed level is required before any final decision can be made to move forward with this concept. Step 1 – Consultations with Stakeholders • Support or buy-in by the Off-Grid communities impacted, in order to move forward; • Discussions with interested parties should be conducted to obtain technical feedback on the transmission line concept; • On-going communications and/or preliminary consultations with First Nations communities using the process outlined in Section 13.0 of this report; • Discussions with the owner of the private line at the termination point at Musselwhite Mine (Goldcorp Inc.); and, • Discussions with sources of funding to support more detailed analysis including: MEI, INAC, FedNor, and potential transmission partners. Step 2 – More Detailed Analysis • If the transmission line routing as presented in this report is accepted by stakeholders, then a more detailed analysis should be conducted that would include the following: - load flow analysis that would test the system with up to 200 MW of generation development and increased mining loads; - more accurate line routing and cost estimate; - on-going and enhanced communications with Off-Grid communities; and - at the present time no assessment has been made as to the environmental impact of the proposed solution; some preliminary study is required in this area. • If, as a result of discussions with stakeholders, other configurations or modifications to the route are proposed, then these options could be assessed at a high level to eliminate options that are not feasible. Page 49 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Step 3 – Pursue Other Incentives and Financial Assistance • The Feed-in Tariff (FIT) Program could also be used to make this project more attractive by assisting in the development of the hydro resources required to support this project. • HONI is looking at a radial supply to Whitesands and Gull Bay from the 230-kV line at Little Jackfish. If this goes forward, the cost of Option 5 would be reduced. • Reduction of carbon footprint and carbon credits. Page 50 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 13.0 Proposed Process for Community Engagement 13.1 Purpose The purpose of an engagement plan is to: • Provide information to the remote community members about their supply of electricity; • To develop a community information base that will allow the decision makers to receive effective community advice in the selection of an electricity supply option to meet their present and future community electricity needs in a safe, reliable and cost effective manner; and • Enable community decision makers to select and support the transmission option as the preferred option for electricity supply. 13.2 Key Messages 1. Cost of Generation and its’ impact on the community 2. Electricity Rates and their impact on the community 3. Independent Power Authority communities and Hydro One Remote Communities - the differences and why 4. Local economic impact 5. Why transmission? 13.3 Message Format The information that will need to be provided to the communities will be sourced from the report and should be prepared in the following formats: 1. Briefing Notes 2. Community Presentations 3. Press Releases a. Newspaper b. Radio c. Community Television 4. Question and Answers for community consumption Page 51 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 13.4 1. 2. 3. 4. Specific Message Content Financial Cost of Generation solutions in a kWh cost Environment and its potential indirect benefits Fibre optic extension Description of Technology(s) with associated human resource requirements to operate: a. Transmission, and b. Fibre Optic Telecommunications 5. Other Factors: a. Rates Structures b. Independent Power Authorities c. Hydro One Remote Communities Inc. d. Regulation 6. Potential Developments a. Hydro Electric b. Mining c. Tourism d. Forestry 13.5 Audience 1. Electricity rate payers in the communities: a. Residential b. Commercial c. Governments 2. Chiefs and Councils and their supporting organizations 3. Ontario and Canadian Politicians and their policy and program staff. 13.6 Specific Engagement Strategy The delivery of the messages concerning electricity supply in the remote communities needs to reflect the regional nature of the issue and how each community is serviced from their various internal organizations. Therefore, we suggest the following structure for information dissemination and response from the communities: Page 52 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities 1. Development of a website that would contain all information that will be used on community visits. Summaries of the community visits would also be placed on the site. 2. Development of a 2 page glossy handout for inclusion with the final report to outline highlights and to heighten awareness of the transmission option for the communities. 3. Development and translation of materials will be used by Nishnawbe Aski Development Fund (NADF) and or by the Nishnawbe Aski Nation (NAN) and other organizations. The purpose of this process is to ensure that all communications get to the communities and that the purpose is consistent. 4. Engagement with community members will be undertaken by the First Nations and their organizations. a. Request and advertise information sessions in the community from Chief and Councils, preferably soon after general information is released in the press, b. Set up briefing session(s) with Chief and Council, c. Set up information question and answer community sessions with community, d. Prepare reports following the community information sessions which will be distributed to the community leadership. Discuss the outcome(s) of community meetings and the reports with the Community leadership and determine the support for the transmission project. It is also expected that if there any issues identified, they will be clearly communicated to the project team. 5. If the direction from the communities is positive, or positive with concerns, then appropriate First Nation and Independent First Nation resolution(s) will be developed which will outline the go forward strategy for the development of a regional transmission based electricity supply option. Page 53 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX A MAP Page 54 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX B TECHNICAL DATA Page 55 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX B1 – ESTIMATED LINE LENGTHS FOR POWER FLOW ANALYSIS Table B1.1: Line Segments Comprising the 115-kV Backbone “From” Station RED LAKE Hydro‐Gen site W1 Pikangikum Poplar Hill Deer Lake Hydro‐Gen site W2 Hydro‐Gen site W3 Sandy Lake Keewaywin (Couchiching) Hydro‐Gen site W4 Muskrat Dam Hydro‐Gen site W5 Bearskin Lake Kitchenuhmaykoosib Inninuwug Wapekeka Kasabonika Lake Wunnumin Kingfisher Lake “To” Station Hydro‐Gen‐W1 Pikangikum Poplar Hill Deer Lake Hydro‐Gen‐W2 Hydro‐Gen‐W3 Sandy Lake Couchiching Hydro‐Gen‐W4 Muskrat Dam Hydro‐Gen‐W5 Bearskin Lake Kitchenuhmaykoosib Inninuwug Wapekeka Kasabonika Lake Wunnumin Kingfisher Lake Musselwhite Total Length of the backbone (km) Page 56 Length (km) 30 20 40 60 35 40 20 50 35 45 25 50 65 35 60 80 40 65 795 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Table B1.2: Line segments comprising 44-kV Radials off the 115-kV backbone “From” Station “To” Station Length (km) North Spirit Lake Keewaywin Wawakapewin Nibinamik/Summer Beaver Webequie North Caribou Lake/Weagamow Sachigo Lake 55 15 20 45 75 70 75 Total length of 44‐kV radials off the 115‐kV backbone (km) 355 Hydro‐Gen Site W2 Couchiching Kasabonika Lake Wunnumin Nibinamik/Summer Beaver Muskrat Dam Muskrat Dam Table B1.3: Line Segments comprising 44-kV Radials off the extension of the 240-kV HONI line “From” Station “To” Station Landsdowne House/Neskantaga Whitesands Gull River 25 60 70 55 Total length of 44‐kV radials off 240‐kV line extension (km) 210 Albany River Hydro Gen Site W6 Eabametoong Little Jackfish Substation Whitesands Eabametoong Length (km) Page 57 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX B2 – DETAILS OF THE TECHNICAL ANALYSIS B2 System Performance Analysis The performance of the proposed transmission concept is studied under a variety of situations, including different system loading conditions and transmission facilities being out of service (contingencies), to establish its suitability for operating as an integral part of the Hydro One power grid. For a feasibility study, system performance is typically assessed by conducting power flow analysis of the integrated system. B2.1 Scenarios for System Performance Assessment In this study, performance of the proposed concept has been assessed for sets of demand, generation, and network configuration scenarios, described below. Load and Generation Scenarios Two sets of load and generation scenarios have been considered. The chosen load scenarios are: • • • 2029 peak demands, Base demands (50% of 2029 peak demands), Low demands (0% of 2029 peak demands) The selected generation scenarios are • • • All demands are supplied by the ISEO-controlled grid Demands are supplied primarily by hydro plants at Muskrat Dam Lake and Wunnumin (with some power exported to the south) Demands are supplied by many small power plants across the system (with some power exported to the south) All 9 combinations of the above load and generation scenarios have been considered. Two cases have special significance: 1) low demand with no local generation; and, 2) peak demand with no local generation. The first case corresponds to system cold start, while the second correspond to winter peak load conditions when hydro generation resources may not be available. These two conditions are used to set the upper and lower limits on VAR requirements at compensation points. Page 58 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The scenarios where local generation (due to the two relatively large, strategically located hydro plants, or many small ones) exceed the local demand significantly are important as they allow an examination of the backbone’s capability to export power to the south under different outage conditions. Network Contingency Scenarios Seven important lines have been selected for performing contingency analysis based on occurrence of a single line outage within the system (known as a Category B event). These contingency cases are also divided into two groups: those involving the proposed network solution and those concerning the IESO-controlled power grid. Cases belonging to the first group are: • • • Loss of the line segment connecting Red Lake to Pikangikum Loss of the line segment connecting Kingfisher Lake to Musselwhite Mine Loss of the line segment connecting Muskrat Dam Lake to Bearskin Lake The first two outages disconnect the arc from the IESO-controlled power grid at its points of interconnection, while the last outage breaks up the arc, forcing generation of the strategically located Muskrat Dam to be diverted to one side of the arc. The contingency cases falling under the second group are: • Loss of the line M1M, connecting Pickle Lake to Musselwhite Mine • Loss of the line E2R, connecting Red Lake to Ear Falls • Loss of the line E1C, connecting Ear Falls to Pickle Lake • Loss of the line LJF, connecting Little Jackfish hydro plant to Pickle Lake The first two outages are important as they target lines that establish electrical connection between the IESO-controlled power grid and the proposed transmission solution. The last two outages are included since the affected lines are involved in transferring power to the proposed transmission concept. B2.2 System Performance under Normal Conditions The power flow results for the above load and generation scenarios are too voluminous to be included here. A summary of the results is provided below: • For all tested scenarios, the loadings of the transmission facilities forming the proposed solution (Fig. 6.6) are well within their prescribed thermal limits; Page 59 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities • There is need for voltage support at only four points within the system to have an excellent voltage profile under all 9 scenarios. It is possible to satisfy voltage limit requirements with only three VAR compensation points. That, however, leads to larger VAR sources and increased spread between the lowest and the highest voltage levels in the area; • Some voltage support is needed at Pickle Lake and Ear Falls under most simulated conditions; • Transmission losses are generally small. This is irrespective of the fact that more than 500 km of lines are operating at 44-kV. The power flow analysis did not include radial connections to Marten Falls, Peawanuck or Fort Severn at this time. Further analysis would be required if these communities are connected. B2.3 System Performance under Contingencies The performance of the system has been analyzed for the seven contingency cases with the communities demand set at their 2029 peak power demands and the required generation provided according to the three generation scenarios (see Section 7.2.1). When the analysis is performed for the two generation scenarios that allow for local generation, the results are quite encouraging. They indicate that: • The proposed concept can withstand losing any one of its own line segments and maintain service to the connected communities. All equipment remains operating within the applicable operational limits under the contingency conditions. • The system survives the loss of M1M, E1C, E2R, or LJF line, with the help of some extra VAR support at Ear Falls and Pickle Lake. Some complications arise for certain contingency cases when the required generation is entirely supplied by the Hydro One network (i.e. when no local generation is present). For this generation scenario: • The proposed transmission solution can endure loss of any one of its own line segments; • Loss of the lines E1C and LJF can be tolerated by the system, although some buses take on relatively high voltages levels following the line outage; and Page 60 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities • The power flow fails to converge to a solution following loss of the lines M1M and E2C, indicating potential voltage stability problem. The encountered difficulty is due to the significant loads connected to the grid at Musselwhite and Red Lake buses. These loads are normally served by the HONI network (see Fig. B2-1). As shown in Fig. B2-2 and B2-3, the loss of either line E2R or M1M opens the proposed arc at one end and make the arc the sole supplier of power to these relatively large loads; thus, making the arc prone to voltage collapse. The situation is not, however, hopeless and there are several possible remedies for that, including: a) The construction of the proposed solution could be coordinated with developments of hydro generation sites within the area. In particular, Muskrat Dam with 53MW generation capacity has a highly strategic location within the proposed supply arc and can serve either of the two end-loads in emergencies. Assuming standard synchronous generators at the dam, their presence can also significantly reduce VAR compensation requirements within the arc. The Wunnumin hydro site with 14MW generation capacity is also important, as it is located relatively close to the Musselwhite Mine and can supply part of the Mine’s demand; thus, reducing line flows on E1C and M1M and drastically decreasing their losses. Proposed Transmission Concept Red Lake E2R Musselwhite Mine 40 MW 33 MW M1M Ear Falls Pickle Lake E1C E1D LJF Fig. B2-1: Large loads at Musselwhite and Red Lake with E2R & M1M in service Page 61 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Proposed Transmission Concept Red Lake E2R Musselwhite Mine 40 MW 33 MW M1M Ear Falls Pickle Lake E1C E1D LJF Fig. B2-2: System configuration following loss of E2R Proposed Transmission Concept Red Lake E2R Musselwhite Mine 40 MW 33 MW M1M Ear Falls Pickle Lake E1C E1D LJF Fig. B2-3: System configuration following loss of M1M b) Using Special Protection Schemes (SPS) will enable the proposed concept to operate until hydro generation developments within the area take place. Two separate SPSs will be needed at Musselwhite and Red Lake substations to operate upon losing M1M or E2R, respectively. These SPSs are simply Load Rejection Schemes, shedding loads at these sites following loss of their monitored lines. Page 62 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities These schemes will be temporary as they become unnecessary once generation resources within the area are developed. c) Reinforcing E2R and M1M. The needed reinforcement will be in the form of the “twining” the two lines. These reinforcements will be expensive, but they could be justified if extensive development of wind generation resources in the area happens, and the need for larger power transfers between the proposed network and the Hydro One network arise. Page 63 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX B3 - Diesel Generation Capacities at Remote Communities 2009 First Nations Community Keewaywin (Couchiching) Marten Falls Nibinamik/Summer Beaver Pikangikum** Poplar Hill Wawakapewin Peawanuck Keewaywin (Niska) Eabametoong Muskrat Dam North Spirit Lake Wunnumin Bearskin Lake Kitchenuhmaykoosib Inninuwug Deer Lake Fort Severn Kasabonika Lake Kingfisher Lake Landsdowne House/Neskantaga North Caribou Lake/Weagamow Sachigo Lake Sandy Lake Wapekeka Gull Bay Whitesands Webequie 2029 Population Existing capacity (kW) Peak demand (kW) ‐‐ ‐‐ ‐‐ Population Required Capacity (kW) Peak demand (kW) ‐‐ ‐‐ ‐‐ 371 675 548 817 ‐530.4 1205.4 398 2322 482 27 291 408 1411 365 485 588 608 705 1250 600 55 600 350 1565 650 365 1115 650 402 1193 463 61 341 292 883 591 511 772 835 876 5108 1061 59 640 897 3105 804 1066 1294 1337 ‐179.0 ‐1375.1 ‐417.9 ‐78.9 ‐150.0 ‐292.9 ‐377.0 ‐649.2 ‐760.0 ‐583.3 ‐1187.6 884.0 2625.1 1017.9 133.9 750.0 642.9 1942.0 1299.2 1125.0 1698.3 1837.6 1075 974 547 1050 381 1600 675 650 1000 650 1371 820 634 941 594 2365 2143 1203 2309 838 ‐1416.2 ‐1127.8 ‐745.6 ‐1070.6 ‐657.2 3016.2 1802.8 1395.6 2070.6 1307.2 365 705 739 804 ‐921.0 1626.0 855 560 2571 415 550 447 757 650 650 2250 705 550 1450 650 1169 938 2784 424 250 509 754 1880 1232 5655 913 1211 983 1666 ‐1921.5 ‐1412.6 ‐3873.5 ‐227.2 0.9 330.3 ‐1008.1 2571.5 2062.6 6123.5 932.2 549.1 1119.7 1658.1 **For reference only - not included in financial calculations Page 64 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Appendix C Community Engagement Contacts Page 65 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Address Independent First Nations Mishkeegogamang First Nation Mocreebec Council of the Cree Nation Sandy Lake First Nation Weenusk First Nation Chief Connie GrayMcKay New Osnaburgh ON P0V 2HO 807-928-2148 807-928-2077 Chief Randy Kapashesit P.O. Box 4 Moose Factory ON P0L 1W0 705-658-4769 705-658-4487 Chief Adam Fiddler P.O. Box 12 Sandy Lake ON P0V 1V0 807-774-3421 807-774-1040 Chief George Hunter P.O. Box 1 Peawanuck ON P0L 2H0 705-473-2554 705-473-2503 Independent First Nations Alliance Muskrat Dam First Nation Pikangikum First Nation Lac Seul First Nation Chief Gordon Beardy P.O. Box 140 Muskrat Dam ON P0V 3B0 807-471-2573 807-471-2540 Chief Peter Quill General Delivery Pikangikum ON P0V 1L0 807-773-5578 807-773-5536 Chief Clifford Bull P.O. Box 100 Hudson ON P0V 1X0 807-582-3211 807-582-3493 Page 66 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Address Keewaytinook Okimakanak Deer Lake First Nation Fort Severn First Nation Keewaywin First Nation MacDowell Lake First Nation North Spirit Lake First Nation Poplar Hill First Nation Chief Roy Dale Meekis P.O. Box 39 Deer lake ON P0V 1N0 807-775-2141 807-775-2220 Chief Matthew Kakekaspan P.O. Box 149 Fort Severn ON P0V 1W0 807-478-2572 807-478-1103 Chief Joe Meekis P.O. Box 90, 202 Band Office Road Keewaywin ON P0V 3G0 807-771-1210 807-771-1053 Chief Eli James Chief Rita Thompson Chief Dennis King P.O. Box 321 Red Lake ON P0V 2M0 807-735-1381 807-735-1383 General Delivery North Spirit Lake ON P0V 2G0 807-776-0021 807-776-0026 P.O. Box 1 Poplar Hill ON P0V 3E0 807-772-8856 807-772-8876 Matawa First Nations Aroland First Nation Chief Sam Kashkeesh P.O. Box 10 Aroland ON P0T 1B0 807-329-5970 807-329-5750 Constance Lake First Nation Chief Arthur Moore P.O. Box 4000 Calstock ON P0L 1B0 705-463-4511 Page 67 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Address 705-463-2222 Eabametoong First Nation Ginoogaming First Nation Hornepayne First Nation Long Lake #58 First Nation Marten Falls First Nation Neskantaga First Nation Nibinamik First Nation Webequie First Nation Chief Lewis Nate Chief Celia Echum P.O. Box 298 Eabamet Lake ON P0T 1L0 807-242-7221 807-242-1440 P.O. Box 89 Long Lac ON P0T 2A0 807-876-2242 807-876-2495 Chief Laura Medeiros P.O. Box 1553 Hornepayne ON P0M 1Z0 807-868-2306 Chief Allen Towegishig P.O. Box 609 Long Lac ON P0T 2A0 807-876-2292 807-876-2757 Chief Harry Baxter General Delivery Ogoki Post ON P0T 2L0 807-349-2509 807-349-2511 Chief Roy Moonias Neskantaga Reserve #239 P.O. Box 105 Lansdowne House ON P0T 1Z0 807-479-2570 807-479-1138 Chief Judas Beaver General Delivery Summer Beaver ON P0T 3B0 807-593-2131 807-593-2270 Chief Cornelius Wabasse P.O. Box 268 Webequie ON P0T 3A0 807-353-6531 807-353-1218 Page 68 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Address Mushkegowuk Council Attawapiskat First Nation Chapleau Cree First Nation Fort Albany First Nation Kashechewan First Nation Missanabie Cree First Nation Moose Cree First Nation Taykwa Tagamou Nation (New Post) Chief Theresa Hall P.O. Box 248 Attawapiskat ON P0L 1A0 705-997-2166 705-997-2116 Chief Keith Corston P.O. Box 400 Chapleau ON P0M 1K0 705-864-0784 705-864-1760 Chief Andrew Solomon P.O. Box 1 Fort Albany ON P0L 1S0 705-278-1044 705-278-1193 Chief Jonathan Solomon P.O. Box 240 Kashechewan ON P0L 1S0 705-275-4440 705-275-1023 Chief Glenn Nolan 174B Hwy 17E Garden River ON P6A 6Z1 705-254-2702 705-254-3292 Chief Norm Hardisty P.O. Box 190 Moose Factory ON P0L 1W0 705-658-4619 705-658-4734 Chief Dwight Sutherland R.R.#2 - Box 3310 Cochrane ON P0L 1C0 705-272-5766 705-272-5785 Shibogama First Nations Council Kasabonika Lake First Nation Chief Gordon Anderson Page 69 P.O. Box 124 Kasabonika Lake ON P0V 1Y0 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Address 807-535-2547 807-535-1152 Kingfisher Lake First Nation Wapekeka First Nation Wawakapewin First Nation Wunnumin Lake First Nation Chief James Mamakwa P.O. Box 57 Kingfisher Lake ON P0V 1Z0 807-532-2067 807-532-2063 Chief Norman Brown P.O. Box 2 Wapekeka ON P0V 1B0 807-537-2315 807-537-2336 Chief Joshua Frogg Shibogama First Nations Council, P.O. Box 449 Sioux Lookout ON P8T 1A5 807-442-2567 807-442-1162 Chief Rod Winnipetonga P.O. Box 105 Wunnumin Lake ON P0V 2Z0 807-442- 2559 807-442-2627 Wabun Tribal Council Flying Post First Nation Beaverhouse First Nation Brunswick House First Nation Chief Murray Ray P.O. Box 1027 Nipigon ON P0T 2J0 807-887-3071 807-887-1138 Chief Gloria McKenzie 26 Staion Road North P.O. Box 1022 Kirkland Lake ON P2N 3L1 705-567-2022 705-567-1143 Chief Rene Ojeebah P.O. Box 117 Chapleau ON P0M 1K0 705-864-0174 705-864-1960 Page 70 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Chapleau Ojibwe First Nation Matachewan First Nation Mattagami First Nation Wahgoshig First Nation Address Chief Anita Stephens P.O. Box 279 Chapleau ON P0M 1K0 705-864-2910 705-864-2911 Chief Richard Wincikaby P.O. Box 160 Matachewan ON P0K 1K0 705-565-2230 705-565-2585 Chief Walter Naveau P.O. Box 99 Gogama ON P0M 1W0 705-894-2072 705-894-2887 Chief David Babin RR#3 Matheson ON P0K 1N0 705-273-2055 705-273-2900 Windigo First Nations Council Bearskin Lake First Nation Chief Rodney McKay P.O. Box 25 Bearskin Lake ON P0V 1E0 807-363-2518 807-363-1066 Cat Lake First Nation Chief Mathew Keewaycabow P.O. Box 81 Cat Lake ON P0V 1J0 807-347-2100 807-347-2116 Koocheching First Nation Chief William Harper P.O. Box 32 Sandy Lake ON P0V 1V0 807-774-1576 807-737-3133 North Caribou Lake First Nation Chief Jowin Quequish General Delivery Weagamow Lake ON P0V 2Y0 807-469-5191 Page 71 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Community Contact Address 807-469-1315 Sachigo Lake First Nation Slate Falls First Nation Whitewater First Nation Chief Titus Tait P.O. Box 51 Sachigo Lake ON P0V 2P0 807-595-2577 807-595-1119 Chief Glen Whiskeyjack 48 Lakeview Dr. Slate Falls ON P0V 3C0 807-737-5700 1-888-431-5617 Chief Arlene Slipperjack 307 Euclid Avenue, Suite 414 Thunder Bay ON P7E 6G6 807-622-8713 807-577-5438 Page 72 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX D SUMMARY OF STATION COSTS Page 73 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Summary of Station Costs - NADF Off-Grid Power* Item All Stations 44kV- Nibinamik, Eabametoong, North Spirit Lake, Neskantaga, Weagomow, Sanchigo Lake, Gull Bay, White Sands, Webequie Cost Each Qty Total $1,587,600 9 $14,288,400 $1,821,600 9 Muskrat Dam 115 – 44 kV station $4,224,600 Bear Head Lake Station 115/44 kV With Redundancy Each (3-phase) Qty Total $2,835,000 9 $25,515,000 $16,394,400 $3,312,000 9 $29,808,000 1 $ 4,224,600 $6,840,000 1 $6,840,000 $4,044,600 1 $ 4,044,600 $6,660,000 1 $6,660,000 Wunnumin Station 115/44 kV $8,004,600 1 $ 8,004,600 $11,160,000 1 $11,160,000 Bearskin Lake, 115 – DV $2,631,600 1 $ 2,631,600 $2,997,000 1 $2,997,000 Albany River Station 230/44 kV $4,935,600 1 $ 4,935,600 $8,271,000 1 $8,271,000 Little Jackfish Station $2,070,000 1 $ 2,070,000 $2,070,000 1 $2,070,000 Red Lake Station Add SVC $5,274,000 1 $ 5,274,000 $5,274,000 1 $5,274,000 $5,610,600 1 $ 5,610,600 $67,478,400 $7,380,000 1 $7,380,000 $105,975,000 All Stations 115kV – Pikangikum, Poplar Hill, Wawakapewin, Keewaywin, Kitchenhmaykoosib,Deer Lake, Kasabonika Lake, Kingfisher Lake, Wapekeka Sandy Lake Station 115/ DV Total Station & SVC Costs Additional Cost to add Redundancy *Class C estimates Page 74 $38,496,600 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX E REGULATORY IMPACTS Page 75 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities E.0 REGULATORY IMPACTS The twenty five “remote communities” in Northwestern Ontario (i.e. those currently not connected to the Ontario transmission system) are provided with electricity either by HORCI or via an IPA that is community owned. Most of the electricity supplied to the remote communities is generated by diesel generators, with a few exceptions. Diesel generators have a low initial cost, and are generally reliable, but have drawbacks due to their high operating costs, frequent maintenance requirements, greenhouse gas emissions, and production of noise pollution. The main drawback to the diesel generators in the remote community environment is the significant risk associated with getting diesel fuel to the communities, as there are no all weather roads over which to bring the fuel. Hauling truckloads of diesel fuel over seasonal winter roads has resulted in a number of diesel fuel spills. There are also environmental risks associated with the transfer of the fuel to tanks in the communities, and many communities have contaminated ground surrounding their diesel fuel tank farms as a result. In some communities this has affected the health of the residents, and has affected the community’s water sources. The remote communities have no all-season road system over which to bring diesel to the communities, and the winter road season is generally 30 to 60 days at best. Reliance on a road system that is only open a short period of time means that if a community underestimates the amount of diesel fuel required to keep the diesel generators operating, the community can be left without power until fuel can be flown into the community at a significantly higher cost. Climate change has led to shorter winter road seasons, and some communities have encountered years when they have been unable to transport adequate fuel into the community when the winter road system has failed due to warm weather. The cost of flying fuel to the communities is very high, and is always an unbudgeted expense. The remote communities are in need of a less expensive and more reliable source of power. E.1 Regulatory Issues In Ontario, the responsibility for energy lies with the Provincial Government. The Ministry of Energy is responsible for setting electricity policy for the energy sector in the province. Prior to 1998, electricity customers in Ontario had a single source of electricity supply. The electricity system in Ontario was a monopoly and was publicly owned. The power produced by Ontario Hydro was purchased and distributed by about 300 local, municipally owned utility companies to consumers, who were charged a fixed price per kilowatt hour (kWh) that bundled together generation, transmission and distribution costs. Page 76 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities Prior to 1998, Ontario Hydro carried out most of the aspects of electricity production and distribution including generation, transmission, and some distribution (to some large industrial and rural customers and the Remote Communities). Ontario Hydro also acted as the central market operator, set the pricing and also for the most part, set the market rules. The electricity industry was substantially restructured with the passing of the new Electricity Act in 1998, with the former monopoly Ontario Hydro being split into several corporations, each responsible for an aspect of the electricity industry: • The Ontario Energy Board (OEB) is the regulator of the electricity industry and natural gas industries, licensing the various participants in the industry, and approving rates for licensed participants. • The Independent Electricity System Operator (IESO) acts as the central market operator, runs the electricity exchange for the sale and purchasing of power and arranges for the dispatch of electricity to distribution companies. The IESO also performs the financial settlements on behalf of the industry. • The Ontario Power Authority (OPA) is responsible for central planning for the industry. • The Electrical Safety Authority is responsible for setting the safety standards for wiring installations and equipment and appliance certification. • The Ontario Electricity Financial Corporation owns “stranded assets” and holds the former Ontario Hydro's $36 Billion debt. The dismantling of Ontario Hydro had a significant effect on the ongoing operations of the remote community system. For the first time, HORCI began to account for its fueling costs separate and distinct from the corporate fuel bill that had included coal, natural gas and nuclear fuels for all of Ontario. The fueling costs for the remote communities began to attract attention when measured against other remote community costs, as fuel was now a significant line item. While electricity is considered to be a provincial responsibility, First Nations in Canada have a unique fiduciary relationship with the federal government. The bulk of funding in First Nations communities comes from Indian and Northern Affairs Canada. E.2 The Remote and Rural Rates Assistance Program Hydro One Remote Communities Inc. (HORCI) is one of the successor companies of the former Ontario Hydro, and is owned by the Province of Ontario as its sole shareholder. Page 77 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities HORCI operates diesel generation and distribution facilities in twenty remote Communities, and anticipates the addition of the community of Marten Falls to its system sometime during the next year. HORCI also owns and operates two run-of-the-river hydro electric generating facilities and has four demonstration wind generators. HORCI is a licensed generator and distributor, and is considered to be unique within Ontario’s regulatory regime. It is exempt from a number of the legal and regulatory requirements imposed on most distributors. As a licensed generator/distributor, HORCI is regulated by the Ontario Energy Board (OEB), which means that HORCI has to submit their rates to the OEB for approval. The current rates are based on the cost of service, with no regulated return on assets for the utility. Remotes functions in a unique environment. Extremely low customer densities, a harsh climate, and logistical challenges related to transportation, along with the absence of an integrated transmission system and complex funding arrangements with third parties, set Remotes apart from other Ontario electricity distributors. This unique operating environment has a profound impact on operations and costs throughout Remotes’ service area. 1 In 2007, HORCI provided electricity to 3 332 customers, most of which (87% according to EB-2008-0232, HORCI’s most recent rates application) pay electricity rates below the cost of providing service. The rates structure in the HORCI communities is based on a structure developed by the former Ontario Hydro Remote Communities and Indian and Northern Affairs Canada. Electrification of the remote First Nation communities began during the 1960’s with Electrification Agreements signed between the former Ontario Hydro and Indian and Northern Affairs Canada. Under the Agreements, the federal government paid for the initial capital costs of the generating and distribution equipment. Indian and Northern Affairs Canada (INAC) is responsible for funding new generation/capital upgrades and connections associated with load growth in the communities, and HORCI is responsible for funding capital replacements, and for any capital improvements that are not associated with load growth. A unique cost structure known as the Standard A rate was developed, where residential and commercial customers are subsidized by those entities receiving government funding from either the provincial or federal government. The “Standard A” rate continues to exist, and is approximately ten times the rates charged to residential and commercial customers, or $0.8418 per kWh (EB-2008-0232). The Standard A rate structure is not only used in the HORCI system, but also has served as a basis for the development of the rate structures in the community owned IPAs. The basic principal of this rate structure was to ensure that the residential customer on a remote Indian reserve is charged rates similar to all other residential customers in Ontario, 1 EB-2008-0232 – Hydro One Remote Communities 2009 Distribution Rate Application – Evidence Update Filing Page 78 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities while ensuring that this operating subsidy was contained within the Ontario Hydro operated remote community system. This system of rates was originally developed to meet the needs of a community where the residential customer was restricted to service in the 15 to 20 amp range. Therefore, the high rate charged to government customers which was, at the time, substantially higher than the generation cost, allowed the total revenues in the system to equal residential plus commercial plus Standard A billing. The amperage restriction was removed in 1992, and the growth associated with that removal accounts for the majority of the operating losses incurred by HORCI. In addition to the Standard A rate structure, the HORCI system is further subsidized under the Remote and Rural Rates Assistance Program (RRRP). Remote and Rural Rate Protection is a program developed to assist in supporting affordable and reliable electricity supply to rural and remote areas of the province, and is funded by all Ontario electricity consumers through a charge of $0.001 per kilowatt hour, as part of the regulatory charges on each consumer’s bill. This allows HORCI to charge their residential and commercial customers rates approximately equivalent to the rates paid by an electricity customer in an urban setting, so that customers in remote and rural areas are not penalized by the higher cost to provide services to them. Since 2002, HORCI has received RRRP funding of $21.1 million per year. In its most recent rates application, HORCI is proposing to recover a total revenue requirement of $42.5 million from its customers and from the Rural and Remote Rate Protection fund for the 2009 test year. This represents an increase of $6.9 million, or 20% over the 2006 approved revenue requirement. In its rates submission (EB-2008-0232), HORCI is seeking increased RRRP funds in the amount of $27.845 million per year, with the explanation that the increase is needed due to the increased cost of diesel fuel. This amount represents approximately 66% of the revenue requirement for the utility. Additionally the utility is seeking to develop a variance account for the RRRP in the amount of $ 4,031,000 to enable the utility to mitigate risks related to increased costs and to recover the existing deficit balance from prior years. This would increase the charge to Ontario electricity consumers to $0.0013 per kWh. RRRP protection is set out in section 79 of the Ontario Energy Board Act, 1998 (the “OEB Act”) and in Regulation 442/01, made under the OEB Act. Subsection 79(1) provides that “The Board” in approving just and reasonable rates for a distributor, who delivers electricity to rural or remote consumers, shall provide rate protection for those consumers or prescribed classes of those consumers by reducing the rates that would otherwise apply in accordance with the prescribed rules. The rules are set out in section 79 and Regulation 442/01. Subsection 79(3) provides that “A distributor is entitled to be compensated for lost revenue resulting from the rate reduction provided under subsection (1)”. The rationale underlying the RRRP Regulation is that economically challenged communities in Ontario should be financially assisted by wealthier urban regions to ensure that their residents have access to affordable electricity. The Ontario Government has set Page 79 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities the criteria in deciding who should be eligible to receive financial assistance under the RRRP Regulation looking at a mix of social, political, and economic factors. Currently, there are five categories of consumers in Ontario who are eligible to receive the RRRP funding. The Nishnawbe Aski Nation (NAN) continues to lobby the Ontario Government, seeking to extend coverage under the RRRP Regulation to the communities whose electricity is supplied by IPAs. E.3 Issues facing Independent Power Authorities Twelve community owned and operated IPAs provide diesel generated electricity to their communities. Some community systems are operated by outside contractors, some are a separate corporation from the First Nation, and some are operated by employees of the First Nation. The IPAs are not regulated by the Province of Ontario, and operate outside of the provincial regulatory environment. As such, they are free to set their own standards, working protocols and rates. Some of the IPA diesel generator and distribution systems were not built to Ontario standards and do not follow Ontario distribution code protocols. Electricity rates differ in each IPA community, and are set based on various factors including social concerns such as affordability for elders and other community residents. In some communities, residents are charged a flat rate, regardless of how much electricity they use, with elders receiving a further discounted rate. Some communities have flat demand based charges, and others charge a monthly service fee plus a demand charge. Some communities have maintained a rates structure similar to the Standard A structure, where residents and businesses are subsidized by government customers. Since 2004, the commodity price for diesel fuel has more than doubled. These significantly increased costs have been compounded by the shortages of trained staff, and higher costs of doing business in remote communities. This has had a devastating impact on the IPA’s who do not have access to the RRRP subsidies available to HORCI in order to break even. IPA’s are reliant on the electricity revenues collected plus any subsidies that are available from Indian and Northern Affairs Canada to operate, and despite the fact that some of the IPA’s have rates structures that are more than double those charged by HORCI, they are still operating at a loss. Unfortunately the reality of many First Nation communities is extremely high unemployment rates, and a high reliance on social assistance. Many community residents are simply unable to afford their hydro bills, as many of the houses have electric heat in the winter. Collection issues are a persistent challenge for the IPA’s. The IPA’s provide a source of employment to some First Nations residents. In some remote First Nations communities, unemployment rates frequently range from 65% to 95% of the workforce, so any jobs are critical. Page 80 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities The increased price of diesel has meant that some of the IPA communities do not have the necessary funds to pay for diesel fuel and properly maintain generating and distribution equipment at the same time. As a result, the electrical power supply for local residents has become unreliable. Back-up generators, which should ordinarily be reserved for emergencies, are frequently being used to ensure an adequate supply of power on a daily basis. Important maintenance work on the diesel generators and distribution systems has been delayed due to a lack of funding, which could be disastrous from a health and safety perspective. Recently, as a result of the significant challenges faced, the IPA’s have decided to form their own IPA agency to work collectively, and have agreed to sign a Memorandum of Understanding to form this agency. E.4 Potential Impacts of Grid Connection There has been much discussion about how to deal with the deficiencies in the IPA systems, including becoming part of the HORCI system, banding together to operate as a regional entity, and purchasing HORCI to take over the entire system. There has also been much discussion and lobbying to connect the remote communities to the IESO grid. Currently, the IPA’s operate and maintain the diesel generators, operate and maintain the distribution systems, perform billings and collections and connection and disconnections, but are not regulated by the Ontario Government. Connecting to the IESO controlled grid would almost certainly involve becoming regulated by the Ontario Energy Board, and having to comply with the rules and regulations associated with grid connection, including becoming licensed distributors and generators, and bringing the system up to Ontario’s transmission and distribution code standards. This would require quite a bit of capacity building for the system operators, as well as a significant influx of funding to pay for the required system upgrades. Connecting most of the remote communities to the IESO controlled grid would have a number of impacts. The diesel generators in the communities could be placed on standby for back up generation, significantly reducing air and noise pollution in the communities. Rates charged to residential customers would likely be standardized, depending on which entity took over distribution in the community. The distribution system in each community would need to be brought up to Ontario Standards, and Ontario’s Distribution System Code would apply. The transmission company that built the line to connect the communities would add the cost of building the new transmission line to its rates base, and would likely become part of the transmission pool in the province. The Transmission System Code would apply to the transmitter. This is the key element to the building and operations of a transmission line to service the communities. A licensed transmitter operating an IESO controlled asset would be able to distribute the capital costs of building the system over a 40 year debt financing model. Page 81 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities E.5 Smart Meter Initiative In November 2005, the Ontario Government passed measures that will see smart meters installed in all Ontario homes by 2010. The existing meters in most communities measures the total amount of electricity used over an entire billing period. A Smart Meter automatically records when electricity is used, recording the consumers’ total electricity consumption hour by hour, allowing for time of day electricity billing. This will allow the government to move from a standardized price for electricity to time of use pricing, where different prices would apply at different times of the day. Prices rise and fall over the course of the day and tend to drop overnight and on weekends based on the amount of supply available and our levels of demand. When demand is highest, prices will be higher, as sometimes the province has to import electricity from other jurisdictions at a higher price during these times. At times of low demand, prices will be lower. It has been estimated that each smart meter costs approximately $500 2. The Ontario Energy Board has decreed that the cost of the Smart Meter initiative will be recovered over time through the electricity rates paid by customers over time. The board expects it to cost more than $1 billion to install the meters across the province, which is expected to add between one and four dollars a month to the average electricity bill. It is unlikely that the remote communities, particularly the IPA’s could comply with this legislation as they do not have the financial resources required to carry out the changeover of the meters, and associated software/hardware. They could ask to be exempted from the Smart Meter legislation if they are connected to the IESO controlled grid. E.6 Potential Impact of Grid Connection on the Winter Road System Funding for construction and maintenance of the winter roads systems to the remote communities is provided by the provincial and federal governments, but not in adequate amounts to subsidize the entire costs of building the road system. The tolls charged to trucks hauling diesel fuel to the remote communities subsidizes the costs associated with building the winter road system, which allows residents to be charged reduced rates (or no tolls at all) to use the winter roads in the province. One of the impacts of connecting the James Bay communities of Attawapiskat, Fort Albany and Kashechewan to the IESO controlled grid was a reduction of tolls on the winter road, and alternative funding had to be sourced. In the case of these three communities, approximately five million liters of fuel per year were removed from the goods hauled on the winter road system. 2 INDEPTH: ENERGY, Smart meters: FAQ’s, CBC News Online | November 3, 2005 Page 82 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities E.7 Green Energy Act In May 2009, the Government of Ontario passed the Green Energy and Green Economy Act (GEA). The Act is intended to facilitate the development of additional “Green Energy” in the province and further encourage energy conservation in the province. The Act also is designed to facilitate the involvement of First Nations and Metis communities in the renewable energy sector of the province. The Green Energy Act amends twenty one statues, including the Electricity Act, the Ministry of Energy Act, the Ontario Energy Board Act, the Clean Water Act and the Environmental Bill of Rights Act, among others. The Act repeals the Energy Efficiency Act and Energy Conservation Leadership Act. The Act should streamline approvals of renewable energy projects, including water, wind, solar, biomass and geothermal energy projects. Renewable energy projects will go through one approval process under the Environmental Protection Act, replacing the past requirements of various approvals under various pieces of legislation. Renewable energy projects will be exempted from municipal controls and approvals, although the government has retained the right to set rules and standards for planning, notice and consultation, design, siting, and reporting for renewable. A Renewable Energy Facilitation Office will be created within the Ministry of the Environment to assist proponents through the approvals process, and the government is hoping to guarantee a six month review process (not including any appeals). A Feed in Tariff (FIT) process has been developed that will enable the development of renewable resources through long term contracts. The FIT program provides a simple standardized method of procuring contracts for renewable energy supply. The FIT includes standard rules, standard contracts, standard pricing and provisions for domestic content and Aboriginal and community involvement. Different prices will be offered for different technologies and project sizes. Generators of renewable energy will no longer be competing to be a lowest cost producer of power. It is unclear whether renewable energy projects that are not connected to the IESO controlled grid will be eligible for the FIT program. One of the intentions of the Green Energy Act is to offset greenhouse gas emissions, so the OPA would likely be very interested in projects that could replace the high-cost diesel generators in the remote communities. The OPA indicated that they are considering a specific pricing schedule under the FIT program for the remote communities that would facilitate renewable energy development and remove diesel generators from Ontario’s electricity mix. The representative acknowledged that the cost of working in the remote communities was significantly higher than the rest of Ontario, and that the OPA was attempting to determine what the specific pricing schedule for the remotes should be. Under the Green Energy Act, the Minister of Energy has been given increased power, including the power to direct the Ontario Government Ministries on energy and Page 83 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities environmental standards in Government buildings, to direct the Ontario Power Authority to develop renewable resources, transmission and distribution, and to direct the Ontario Energy Board to facilitate development of a “Smart Grid”. The Minister may also direct the Ontario Energy Board to enable the connection of renewable projects to the grid, through system reinforcements or expansions. Further, the Minister of Energy also could, if he chooses, to issue a shareholders directive to the provincially owned transmitter, Hydro One Networks Inc. to undertake the expansion of the IESO grid. The GEA is a significant shift away from the previous mandate of the Ontario Energy Board which was to “ensure adequacy, safety, sustainability and reliability of electricity supply in Ontario through responsible planning and management of electricity resources, supply and demand. Effectively, the Ontario Energy Board acted as a watchdog for the monopoly businesses of transmission and distribution, and ensured that Ontario consumers were protected. Under the GEA, transmitters and distributors must connect renewable energy projects that make a written request for connection and meet all technical, economic and other requirements. The transmitters and distributors must provide priority connection to renewable energy projects that meet these requirements. Transmitters and distributors are also required by their respective licenses to prepare plans for the expansion of their systems to accommodate renewable generation and the smart grid. The GEA is now putting the OEB in the position of encouraging system growth and expansion, as compared to its previous mandate of providing a prudent financial check on expansions. This may be very advantageous for the remote communities that are seeking to be connected to grid power. It appears that the Minister of Energy has the power to direct the Ontario Energy Board to facilitate connection of the remote communities to the grid. His rationale could be that the greenhouse gas emissions that will be offset by construction of a transmission system to the remotes and putting the diesels on standby is considerable. The Ontario Power Authority’s Integrated Power System Plan (IPSP) identified potential renewable energy projects in the North West of Ontario that have not been economically viable without a method to deliver the electricity to the main grid. A transmission line extension to the remote communities would potentially facilitate the development of some or all of these projects. The OPA recently commissioned a wind study in the northwest of Ontario to further define the wind generation potential of the area. Page 84 Transmission Line Concept (TLC) for Northern Ontario Off-Grid Communities APPENDIX F GLOSSARY OF TECHNICAL TERMS Load Flow (Power Flow) Study: A load flow study entails electrical modeling of the power system components (generators, loads, transmission lines, transformers, etc.) and simulation of the system line flows and bus voltages for a specific set of load and generation values. For the system to be operationally acceptable, the resulting line flows and bus voltages must stay within their IESO prescribed limits. Category B Event: Refers to a single power system component being out-of-service. The event could be caused by a power system fault, resulting in the protection system disconnecting the component. Impacts of a Category B event on a power system are assessed by comparing pre- and post-event system conditions, obtained by performing load flow studies. Contingency Analysis: Is performing systematic load flow studies for a set of Category B events to identify weaknesses in the power grid. A power system that can withstand the impacts of all selected Category B events is deemed to be operationally robust (strong). Load Rejection Scheme: A protection system strategy that, when some power system components approach their operational limits, starts disconnecting loads from the system to bring the components back within their acceptable operating limits. Protection System: A set of relays which command breakers to disconnect a power system component when that component operates outside its operational limits. Special Protection Schemes (SPS): A protection system strategy that, when some power system components approach their operational limits, start to disconnect specific components from the system to bring back the components into their limits. Static VAR Compensator (SVC): An electrical component added to the transmission system to ensure that substation voltages stay within their limits during normal operations, and also following any Category B event, under different load conditions VAR Compensation: This term defines the action of any controllable/switchable power system device that can produce or absorb reactive power. Static VAR Compensators are one example of such devices. Page 85
© Copyright 2026 Paperzz