TULLAMORE FLOOD RISK ASSESSMENT AND MANAGEMENT STUDY FINAL HYDROLOGY REPORT 1794/RP/003/D June 2008 FRAM Section Engineering Services Office of Public Works PROJECT TULLAMORE FLOOD RISK ASSESSMENT AND MANAGEMENT STUDY PROJECT No. 1794 PROJECT ENGINEER: GREG RYAN, ENGINEER GRADE II CLIENT: ENGINEERING SERVICES OFFICE OF PUBLIC WORKS DOCUMENT TITLE: TULLAMORE FRAM STUDY FINAL HYDOLOGY REPORT DOCUMENT No.: F:1794 – Tullamore FRAM Study Doc. No. 1794/RP/003/D 1794/RP/003/D June 2008 INDEX OF CONTENTS Section_ Page 1. Introduction _________________________________________________________ 1 2. Background _________________________________________________________ 1 3. Study area___________________________________________________________ 2 4. Objective of hydrological investigation____________________________________ 3 5. Data collection _______________________________________________________ 3 5.1. Historical flood events ________________________________________________ 3 5.2. Catchment hydrological characteristics ___________________________________ 5 5.3. Rainfall ___________________________________________________________ 7 5.4. River level and flow __________________________________________________ 9 5.5. Long-term catchment changes _________________________________________ 13 6. Derivation of design peak flood flows ____________________________________ 15 6.1. Estimation of design flood flows using the available flow dataset ______________ 15 6.2. Estimation of design flood flows using alternative flow datasets _______________ 16 6.3. Adoption of design flood flows ________________________________________ 19 7. Inclusion of allowances for long-term catchment changes ___________________ 20 8. Grand Canal________________________________________________________ 21 9. Conclusion _________________________________________________________ 24 10. Recommendations ___________________________________________________ 24 11. References__________________________________________________________ 25 Appendices _____________________________________________________________ 26 Appendix A _____________________________________________________________ 27 Appendix B _____________________________________________________________ 29 Appendix C _____________________________________________________________ 31 Appendix D _____________________________________________________________ 33 Appendix E _____________________________________________________________ 35 Appendix F _____________________________________________________________ 37 D1794 – Tullamore FRAM Study Doc. No. 1794/RP/003/D iii June 2008 INDEX OF TABLES Table Page Table 1: Relevant rain gauges. ________________________________________________ 7 Table 2: Summary of analysis using Thiessen Polygons. ____________________________ 8 Table 3: Relevant river level recorders. _________________________________________ 9 Table 4: Rating Equation 1 and 2. ____________________________________________ 11 Table 5: Rating Equation 3. _________________________________________________ 12 Table 6: Smoothed ratings. _________________________________________________ 12 Table 7: Estimation of mean annual flow using continuous flow record. _______________ 15 Table 8: Estimation of design flood flows using the regional growth curve _____________ 16 Table 9: Summary of mean annual flows alternative water level recorders._____________ 17 Table 10: Mean annual flood flow factors.______________________________________ 17 Table 11: Summary of statistical analysis and resulting peak flood flow estimations. _____ 18 Table 12: Design flood flow estimates at the Tullamore water level recorder. ___________ 18 Table 13: Design flood flow estimates at the Tullamore water level recorder. ___________ 19 Table 14: Summary of growth factors _________________________________________ 20 Table 15: Adopted design flood flows at the Tullamore water level recorder. ___________ 20 Table 16: Future design flood flows at the Tullamore water level recorder _____________ 21 Table 17: Dimensions of canal overflow weir ___________________________________ 22 Table 18: Grand Canal overflows relative to adopted design flood flows. ______________ 23 D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page iv of 59 June 2008 INDEX OF FIGURES Figure Page Figure 1: Aerial photo of the Tullamore urban area.................................................................. 1 Figure 2: The Tullamore urban area and the Tullamore River floodplain................................. 2 Figure 3: The Tullamore River during a moderate flood event (William Waller Weir) ........... 3 Figure 4: The Tullamore River floodplain (upstream of the Tullamore urban area)................. 4 Figure 5: Site of the Tullamore water level recorder................................................................. 9 Figure 6: Vegetation downstream of the Tullamore water level recorder............................... 13 Figure 7: Overflow weir from the Grand Canal. ..................................................................... 21 INDEX OF EQUATIONS Equation Page Equation 1: Calculation of FSR stream frequency parameter. ________________________ 6 Equation 2: Calculation of FSR SOIL parameter. _________________________________ 6 Equation 3: Calculation of FSR Rsmd parameter. __________________________________ 7 Equation 4: General rating equation in the Republic of Ireland.______________________ 11 Equation 5: FSR six variable equation using Rsmd. ________________________________ 16 Equation 6: FSR six variable equation using SAAR. ______________________________ 16 Equation 7: Flow across a broad crested weir. ___________________________________ 22 D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page v of 59 June 2008 1. Introduction The Office of Public Works (the ‘OPW’) is undertaking a flood risk assessment and mitigation study (FRAM Study) in the vicinity of Tullamore, Co. Offaly. The primary output from this study is a flood risk management plan (FRM Plan) that presents a recommended strategy to reduce the flood risk within the Tullamore urban area. The FRAM Study consists of the following stages: 1. Hydrological investigation. 2. Hydraulic investigation. 3. Strategic Environmental Assessment (SEA). 4. Flood damage assessment. 5. Flood risk mitigation option appraisal and recommendation. 6. Flood risk management plan. This report details the hydrological investigation completed as part of the FRAM study, and is focused on the derivation of design flood flows relevant to the Tullamore River within the Tullamore urban area. 2. Background Tullamore is located within the Tullamore River catchment, approximately 6 km upstream of the confluence with the Clodiagh River. The Tullamore urban area has a population of approximately 10,000 and includes residential, commercial and industrial land uses. Figure 1: Aerial photo of the Tullamore urban area D1794 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 1 of 59 June 2008 Three significant waterways pass through the Tullamore urban area: - The Tullamore River is a tributary to the Clodiagh River, which is in the Brosna River catchment. It has a catchment area of 114.8 km2 at the Tullamore water level recorder (refer to Appendix D for location), which consists primarily of farmland, but also includes part of the Tullamore urban area. - The Grand Canal is a transport link between the east coast (Dublin) and west coast (Shannon River) of Ireland that is retained for recreational users. The water level in the Grand Canal is artificially controlled by the series of locks that are operated and maintained by Waterways Ireland (refer to Section 8 for further comment on the impact that the Grand Canal has on flood flows in the Tullamore River catchment). - The Barony River is a tributary to the Tullamore River. It has a catchment area of 16.9 km2 above the Grand Canal, all of which is within the Tullamore River catchment referred to above. Part of the Tullamore urban area is located on the Tullamore River floodplain, and as a result it has been historically subject to inundation. This has resulted in residential, commercial and industrial properties being subject to an ongoing flood risk, hence the need for this FRAM Study. The need for this FRAM Study is further justified by urban development pressure on the Tullamore River floodplain upstream and downstream of the existing urban area. Figure 2: The Tullamore urban area and the Tullamore River floodplain 3. Study area The study area for the Tullamore FRAM study was generally described as the existing Tullamore urban area, including areas that could be subject to future development (refer to Appendix A). The study area for this hydrological investigation was the Tullamore River catchment upstream of the OPW Tullamore river level recorder (refer to Appendix B). D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 2 of 59 June 2008 4. Objective of hydrological investigation The objective of this hydrological investigation is to estimate design peak flood flows relevant to the Tullamore River within the Tullamore urban area. These estimates are required for inclusion in the one and two dimensional numerical hydraulic models that are to be constructed as part of the FRAM Study. 5. Data collection The objective of this data collection exercise is to obtain sufficiently detailed and accurate data sets that describe: 5.1. - Historical flood events in the Tullamore River catchment. - The hydrological characteristics of the Tullamore River catchment. - Rainfall over the Tullamore River catchment. - Flow in the Tullamore River. Historical flood events Based on reports gathered from the Design Section Press Archive and local authorities, there have been five significant flood events in the Tullamore River catchment over the past century: - Late 1844. - Late 1924. - Early 1946. - Late 1954. - Early 1990. - Early 1995. - Early 2001. Figure 3: The Tullamore River during a moderate flood event (William Waller Weir) D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 3 of 59 June 2008 As the Tullamore water level recorder was commissioned after the early 2001 flood event, the information available on these flood events is limited to: - Press reports: The OPW Design Section Press Archive identified eleven articles covering the 1924, 1954 and 1995 flood events. These press reports focused on the damage to rural land, rather than damage sustained within the Tullamore urban area. - Data collected by local councils: The Offaly County Council and Tullamore Town Council were asked to provide any data that was available describing historical flood events. At the time of preparing this report, the data available included a long section of the flood level through the Tullamore urban area during the winter 1844 flood event, a plan of the flood extent between Charleville Demesne and Springfield Bridge during the February 1946 flood event, a long section of the flood level through the Tullamore urban area during the February 1990 flood event and a plan of flood levels in the vicinity of the Whitehall Estate taken during the February 1990 flood event. - Data collected by the OPW: The OPW East Region provided flood levels surveyed during the February 2001 flood event. Figure 4: The Tullamore River floodplain (upstream of the Tullamore urban area) D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 4 of 59 June 2008 5.2. Catchment hydrological characteristics The FSR outlines a number of methods that are suitable for assessing flood flows in Irish rivers. These methods require a number of inputs that represent various hydrological characteristics of a catchment. These inputs were abstracted for the Tullamore River catchment, as outlined in the following sections. 5.2.1 Catchment area The catchment area for the Tullamore River at the OPW water level recorder was measured as 114.8 km2. This value was directly adopted by the hydrological methods used in this investigation. This value was measured using MapInfo GIS and the contours presented on the OS 1:50,000 map of the area. A diagram of this catchment area is presented in Appendix B of this report. 5.2.2 Urban development of catchment The area of existing urban development within the Tullamore River catchment was measured as 6.918 km2. The corresponding catchment characteristic adopted by the hydrological methods used in this investigation, URBAN, was therefore assessed as 6 %. These values were measured using MapInfo GIS assuming that the area of existing urban development within the Tullamore River catchment was equal to the Tullamore urban area within the Tullamore River catchment as defined by the Offaly County Council Development Plan 2003 – 2009. A diagram of these urban areas is presented in Appendix C of this report. 5.2.3 Attenuating effect of lakes Based on the OS 1:50,000 map of the area, there are no significant lakes within the Tullamore River catchment. The corresponding catchment characteristic adopted by the hydrological methods used in this investigation, LAKE, was therefore assessed as 0 %. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 5 of 59 June 2008 5.2.4 Main channel length The length of the main channel within the Tullamore River catchment was measured as 16.1 km. This value was directly adopted by the hydrological methods used in this investigation. This value was measured using MapInfo GIS and the OS 1:50,000 map of the area. 5.2.5 Main channel slope The main channel slope (i.e. S1085) of the Tullamore River catchment was measured as 1.656 %. This value was directly adopted by the hydrological methods used in this investigation. This value was measured by using MapInfo GIS and the OS 1:50,000 map of the area to determine the position and elevation of two points on the main channel within the Tullamore River catchment. These points were located at 10% and 85% of the main channel length. 5.2.6 Stream frequency The stream frequency (i.e. Fs) within the Tullamore River catchment (i.e. a measure of the number of channel junctions relative to the catchment area) was measured as 0.319. This value was directly adopted by the hydrological methods used in this investigation. This value was measured using MapInfo GIS and the OS 1:50,000 map of the area to count the number of channel junctions shown. This measured value was then corrected to account for the lower resolution of channels shown on the 1:50,000 map when compared with a 1:25,000 map, as required by the FSR (refer to Equation 1). Equation 1: Calculation of FSR stream frequency parameter. Fs = 2.1318F”s – 0.1081 Where Fs F”s Parameter adopted by the FSR Stream frequency measured off 1:50,000 scale plan 5.2.7 Catchment soil characteristics The proportion of Soil Classes within the Tullamore River catchment was measured as 73 % Class 2 and 27 % Class 4. The corresponding catchment characteristic adopted by the hydrological methods used in this investigation, SOIL, was therefore assessed as 0.341. This value was measured using Figure I 4.18.1 and calculated using Equation 2, both of which are presented in the FSR. Equation 2: Calculation of FSR SOIL parameter. SOIL = 0.15 SOIL1 + 0.30 SOIL2 + 0.40 SOIL3 + 0.45 SOIL4 + 0.50 SOIL5 Where SOIL SOIL1 SOIL2 SOIL3 SOIL4 SOIL5 Parameter adopted by the FSR Soil class 1 (very high infiltration potential) Soil class 2 (high infiltration potential) Soil class 3 (moderate infiltration potential) Soil class 4 (low infiltration potential) Soil class 5 (very low infiltration potential) D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 6 of 59 June 2008 5.2.8 Empirical catchment wetness index The empirical estimate of the catchment wetness index (CWI) for the Tullamore River catchment was assessed as 121.9. This value was directly adopted by the hydrological methods used in this investigation. This value was taken from the FSR. 5.2.9 Standard annual average rainfall The standard annual average rainfall (SAAR) for the Tullamore River catchment was measured as 900 mm. This value was adopted directly by the hydrological methods used in this investigation. This value was measured using the Meteorological Service Ireland Mean Annual Rainfall Map (1951 - 1980). 5.2.10 Jenkinson’s Ratio Jenkinson’s Ratio for the Tullamore River catchment was assessed as 0.3. This value was directly adopted by the hydrological methods used in this investigation. This value was assessed using Figure II 3.5.1, which is presented in the FSR. 5.2.11 Measure of excess rainfall Excess rainfall (i.e. Rsmd) for the Tullamore River catchment was assessed as 34.4. This value was directly adopted by the hydrological methods used in this investigation. This value was measured using Equation 3, which is presented in the FSR. Equation 3: Calculation of FSR Rsmd parameter. Rsmd = (2.48 x SAAR0.5) – 40 Where 5.3. Rsmd Parameter adopted by the FSR SAAR Standard average annual rainfall Rainfall 5.3.1 Identification of potential data sources The rain gauges considered for inclusion in this investigation were limited to those managed and maintained by Met Éireann for reasons of reliability, accuracy and length of record. The Met Éireann rain gauges identified as being potentially relevant to this investigation are summarised in Table 1. The locations of these rain gauges are presented in Appendix D of this report. Table 1: Relevant rain gauges. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 7 of 59 June 2008 Name Data Frequency Approximate Location* Birr Hourly 38 km southwest Mullingar Hourly 29 km north Tyrrellspass Daily 14 km north Geashill Daily Within catchment Clonaslee Daily 15 km south-southwest *Relative to the centre of the Tullamore River catchment 5.3.2 Interrogation of available data sources The rainfall data sources identified as being potentially relevant to this investigation were interrogated by Met Éireann on behalf of the OPW over a period that is consistent with the water level and flow data that is available from the OPW Tullamore water level recorder (i.e. February 2001 onwards). The data sets obtained were forwarded electronically by Met Éireann to the OPW. 5.3.3 Manipulation of available data sets The data sets obtained from Met Éireann were manipulated to form one dataset that is representative of rainfall over the Tullamore River catchment using the following process: 1. With regard to the two hourly rain gauges, it was observed that both were located outside the Tullamore River catchment, with the actual catchment area located approximately half way between the two. It was therefore decided that the hourly rainfall data provided by these rain gauges would be combined using the method of Thiessen Polygons to give one hourly data set. The result of this analysis is summarised in Table 2. Table 2: Summary of analysis using Thiessen Polygons. Name Birr Mullingar Coverage area* Thiessen Coefficient 12.87 km2 0.11 2 101.93 km 0.89 * Area of Thiessen Polygon within the Tullamore River catchment 2. With regard to the three daily rain gauges, considered that the daily rainfall data provided by these three rain gauges could be combined using the method of Thiessen Polygons to give one daily data set. However, as the Tullamore River catchment boundary was located approximately half way between the daily rain gauge pairs, it was decided that it would not be necessary to combine the available daily rainfall data sets. Instead, the daily rainfall data set for the Tullamore River catchment was assumed equal to the data provided by the Geashill daily rain gauge. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 8 of 59 June 2008 3. In order to obtain a data set that was representative of rainfall in the Tullamore River catchment, it was considered essential that the daily rainfall totals of that data set should match those recorded by the Gleashill rain gauge, which was assumed to provided the best estimate of daily rainfall within the Tullamore River catchment given that it was the only rain gauge located within the Tullamore River catchment. To achieve this, the hourly dataset was first converted to a daily rainfall set, taking into account that the daily rainfall data provided by Met Éireann represented rainfall between 0900 on the day identified and 0900 the following day. The resulting two daily rainfall data sets were then compared, and the percentage difference between the two was applied as a correction to the hourly rainfall data set. The resulting hourly rainfall data set was considered representative of rainfall in the Tullamore River catchment, given that: 5.4. - The temporal pattern of the adopted rainfall record is consistent with the data collected by the Birr and Mullingar rain gauges, which were the closest rain gauges to the Tullamore River catchment that provided sufficient temporal resolution. - The adopted hourly rainfall record provided daily rainfall totals that were consistent with the daily rainfall total recorded by the Gleashill daily rain gauge, which was assumed to provide the best estimate of daily rainfall given that it was the only rain gauge located within the Tullamore River catchment. River level and flow 5.4.1 Identification of potential data sources Five river level recorders were identified as being potentially relevant to this investigation. The details of these are summarised in Table 3 and the location of each is presented in Appendix D of this report. Table 3: Relevant river level recorders. Name Owner Reference River Tullamore OPW 90501 Tullamore Ferbane OPW 25006 Brosna Gorteen OPW 25007 Clodiagh Millbrook Bridge OPW 25014 Silver Rahan OPW 25016 Clodiagh Figure 5: Site of the Tullamore water level recorder D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 9 of 59 June 2008 5.4.2 Interrogation of available data sources The river level and flow data sources identified as being potentially relevant were investigated by the OPW, as follows: - The Tullamore water level recorder was used to obtain an hourly water level data set over the available data period (i.e. February 2001 onwards). - The Ferbane water level recorder was used to obtain an annual maximum water level and flow data set over the available data period (i.e. 1953 to 2004), along with an hourly water level and flow data set over a period that is consistent with the Tullamore water level recorder (i.e. February 2001 onwards). - The Gorteen water level recorder was not used to obtain any data given that there was no flow data available (due to the lack of any rating) and the station was decommissioned in 2003. - The Millbrook Bridge water level recorder was used to obtain an annual maximum water level and flow data set over the available data period (i.e. 1951 – 2004) , along with an hourly water level and flow data set over a period that is consistent with the Tullamore water level recorder (i.e. February 2001 onwards). - The Rahan water level recorder was used to obtain an annual maximum water level and flow data set over the available data period (i.e. 1958 – 2004) , along with an hourly water level and flow data set over a period that is consistent with the Tullamore water level recorder (i.e. February 2001 onwards). D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 10 of 59 June 2008 5.4.3 Manipulation of available data sets In this instance, “manipulation” refers to converting the available water level data sets to flow data sets using rating equations. The general form of rating equation used in the Republic of Ireland is presented in Equation 4. Equation 4: General rating equation in the Republic of Ireland. Q = k(G + DG)α Where: Flow (m3/s) that corresponds to the gauged water level (G). Site specific constant determined by fitting gauged data points to a straight line on a log-log plot. The gauged water level (m) that corresponds to the flow (Q). Site specific correction to G, determined by fitting gauged data points to a straight line on a log-log plot. Site specific constant determined by fitting gauged data points to a straight line on a log-log plot. Q k G DG α The hourly water level data set obtained from the Tullamore water level recorder was converted to an hourly flow data set using this general equation and the following process: 1. Two rating equations were previously developed for the Tullamore water level recorder: - Rating Equation 1 was developed using fifteen gauged points between February 2001 and July 2001. - Rating Equation 2 was developed using three gauged points between February 2002 and November 2002. These existing rating equations were checked against the relevant gauged points to ensure that the estimates made for the variables outlined above were reasonable. As a result it was found that Rating Equation 1 was reasonable and Rating Equation 2 required a slight adjustment to the upper limits due to the change in the required DG. The details of the corrected and adopted Rating Equations 1 and 2 are summarised in Table 4. The plot of the applicable gauged points is presented in Appendix E. Table 4: Rating Equation 1 and 2. Rating Equation k DG α Upper Lim Finish Date Quality 1 A 21.0 -1.040 2.5 1.190 24/07/2001 56 1 B 21.0 -1.040 2.5 1.497 24/07/2001 16 1 C 9.6 -1.040 1.5 2.000 24/07/2001 16 1 D 9.6 -1.040 1.5 24/07/2001 56 2 I 21.0 -1.139 2.5 1.289 25/11/2002 56 2 J 21.0 -1.139 2.5 1.596 25/11/2002 16 2 K 9.60 -1.139 1.5 2.099 25/11/2002 26 D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 11 of 59 June 2008 2 L 9.60 -1.139 1.5 25/11/2002 56 2. The last gauged point used to derive the most recent rating equation (i.e. Rating Equation 2) was collected during November 2002. To ensure that this rating equation was still valid for the conversion of more recent water level data, additional gauged points were requested. As a result, four measurements were carried out during a flood event in October/November 2005. These additional gauged points were found to require a “DG” value that was not consistent Rating Equation 2. It was also found that the required “DG” value was not consistent between the four new gauged points. It was therefore determined that Rating Equation 2 was not valid for more recently collected water level data and that a new rating equation would be required, hence the derivation of Rating Equation 3 using a new “DG” value and the existing k and α values. The details of the newly derived Rating Equation 3 are summarised in Table 5. The plot of the applicable gauged points is presented in Appendix E. Table 5: Rating Equation 3. Rating Equation k DG a Upper Lim 3 Q 21.0 -1.290 2.5 1.440 3 R 21.0 -1.290 2.5 1.747 3 S 9.60 -1.290 1.5 2.250 3 T 9.60 -1.290 1.5 3. There is a significant shift in the relevant “DG” value between Rating Equation 1 and 2, and Rating Equation 2 and 3. To avoid a step in the derived hourly flow data set due to this shift, it was decided that smoothed ratings would be required, which involved steadily changing the relevant “DG” value (and upper limits) over the period that the change was observed. The details of the smoothed ratings are summarised in Table 6. Note: Refer to discussion below regarding the observed instability of the rating equation for the Tullamore water level recorder. Table 6: Smoothed ratings. Smoothed Rating DGstart DGfinish Datestart Datefinish ∆DG/∆T A (1 to 2) -1.040 -1.139 27/07/2001 14/02/2002 -2 x 10-5 B (2 to 3) -1.139 -1.290 25/11/2002 27/10/2005 -6 x 10-6 4. The significant shift in “DG” noted above caused some concern with regard to the reliability of the rating equations, particularly given that it was consistently increasing over a relatively short period of time (i.e. 4 years). There are a number of potential causes of this shift, including: D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 12 of 59 June 2008 - The vegetation in the Tullamore River channel is becoming more and more overgrown. Figure 6: Vegetation downstream of the Tullamore water level recorder. - The consistent increase in “DG” is coincidence and the variable rating is due to debris blockage behind the road bridge immediately downstream of the Tullamore River recorder. - There is a hydraulic control downstream of the recorder that only dominates during certain flood conditions (e.g. during recession). To address this issue in the short term, an alternative flow dataset was created by applying Rating Equation 1 (refer to Table 4) to the entire water level dataset. Given that Rating Equation 1 represents the Tullamore River channel at the highest recorded efficiency, the resulting flow estimates would be the highest and therefore most conservative out of those available from Rating Equations 1, 2 and 3. Note: The hourly and annual maximum water level data sets obtained from the Ferbane, Millbrook Bridge and Rahan water level recorders were converted to flow using the applicable rating equations without the above checks. This is because these water level recorders have relatively stable ratings. 5.5. Long-term catchment changes The Tullamore FRAM Study looks at the long-term management of flood risk. It is therefore important that this hydrological investigation gives consideration to how the hydrological characteristics of the Tullamore River catchment may change in 50 to 100 years. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 13 of 59 June 2008 The two most significant (and foreseeable) changes to the hydrological characteristics of the Tullamore River catchment are a change in the characteristics of rainfall due to climate change and a change in the catchment land use due to increased urbanisation. 5.5.1 Climate change The OPW has produced and implemented an internal policy to ensure that the predicted effects of future climate change are taken into account when completing hydrological and hydraulic investigations. The technical basis for this policy is contained in the report written by Michael Bruen (University College of Dublin) entitiled “Climate Change Impacts on Flooding in Ireland – A Desk Study/Literature Review (September 2003)”. 1. Sea level rise It is expected that future climate change will result in a general increase in global sea levels. To account for such an increase (but excluding the impact of changes in storm surge characteristics), the OPW internal policy recommends that the sea level should be increased by 300 to 350 mm, depending on geographic location. Given the inland location of the Tullamore River catchment and the resulting lack of any tidal influence, it was not necessary to incorporate this increase into this investigation. 2. Change in rainfall It is expected that future climate change will result in a change in rainfall intensity across the Republic of Ireland. The magnitude of this increase will depend on geographic location. Based on the location of the Tullamore Rive catchment (i.e. Midlands), and the data provided by the Tullamore water level recorder since February 2001 indicating that most significant flood events occur during winter season, the assessment of the impact of climate change on flood flows and extents was completed by increasing design flood flows by 20 %. 5.5.2 Land use change It is likely that the land use within the Tullamore River catchment will change, primarily due to urbanisation of the land surrounding the existing Tullamore urban area. Urbanisation of a catchment involves the covering of normally permeable surfaces with impermeable surfaces such as roofs, roads and footpaths. This is likely to result in an increase in direct runoff reaching the Tullamore River, which is also likely to increase peak flood flows in the Tullamore River. This change was quantified by considering the increase in the URBAN hydrological parameter. The existing URBAN estimation is 6 %, which is based on the existing Tullamore urban zone. It is likely that this will increase to 8 % based on the “future development” and “future development (long term)” zones that are defined by the Offaly County Council Development Plan 2003 – 2009. The resulting increase in the URBAN hydrological parameter is not considered significant given it’s magnitude and the fact that it doesn’t take into account the positive impact of sustainable urban drainage practises that reduce the impact of urbanisation on runoff. The impact of increased urbanisation within the Tullamore River catchment has therefore not been included in the future flood flows that are adopted by this hydrological investigation. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 14 of 59 June 2008 6. Derivation of design peak flood flows The FSR recommends a number of hydrological methods as being suitable for the derivation of design flood flows, including (in order of preference): 1. Annual maximum analysis (peak flood flows only). 2. Six variable empirical analysis and regional growth curves (peak flood flows only). 3. Unit hydrograph analysis (peak flood flows and hydrographs). The adoption of the above method depends on the availability of sufficiently accurate and detailed data describing rainfall, flow and catchment hydrological characteristics, with the preference given to methods that include data collected during observed flood events. 6.1. Estimation of design flood flows using the available flow dataset Given the preference for observed data, the mean annual flow at the Tullamore water level recorder was first estimated using the available 4 year record coupled with rating equation 1 (i.e. the most conservative conversion of water level data to flow data). The results of this analysis are summarised in Table 7. Table 7: Estimation of mean annual flow using continuous flow record. Hydrometric Year* Maximum Water Level (m) Maximum Flow (m3/s) 2002 1.92 7.86 2003 2.02 9.33 2004 1.82 6.55 2005 2.02 9.33 8.27 (average) *The hydrometric year runs from 1st October to 30 September The FSR Regional Growth Curve was then applied to this estimate of the mean annual flood flow to derive design flood flows with a 20%, 10%, 5%, 2%, 1% and 0.1% annual exceedance probability (AEP). The results of this application are summarised in Table 8. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 15 of 59 June 2008 Table 8: Estimation of design flood flows using the regional growth curve T (Years) AEP (%) Growth factor Design flow (m3/s) 6.2. 2.3 Mean Annual 1.00 8.27 5 20 1.20 9.92 50 10 1.37 11.33 20 5 1.55 12.82 50 2 1.77 14.64 100 1 1.96 16.21 1000 0.1 2.55 21.07 Estimation of design flood flows using alternative flow datasets Given the short flow dataset available at the Tullamore water level recorder, along with the low reliability of the applicable set of rating equations (refer to discussion in Section 5.4.3), an alternative set of design flood flows was derived using the longer flow datasets available from three alternative water level recorders on the Clodiah River system (i.e. Ferbane, Millbrook Bridge and Rahan). The steps followed to derive this alternative set of design flood flows are as follows: 1. The mean annual flow at the Tullamore water level recorder was estimated using the FSR six variable empirical equations (refer to Equation 5 and Equation 6) and the catchment characteristics described in Section 5.2. Equation 5: FSR six variable equation using Rsmd. Qbar = 0.0172 (AREA)0.94 (STMFRQ)0.27 (SOIL)1.23 (Rsmd)1.03 (1 + LAKE)-0.85 (S1085)0.16 Equation 6: FSR six variable equation using SAAR. Qbar = 0.00042 (AREA)0.95 (STMFRQ)0.22 (SOIL)1.18 (SAAR)1.05 (1 + LAKE)-0.93 (S1085)0.19 These equations provided an estimate for the mean annual flow at the Tullamore water level recorder of 12.03 m3/s using Equation 5 and 11.55 m3/s using Equation 6. 2. The mean annual flows at alternative water level recorders were estimated using the same FSR six variable empirical equations (refer to Equation 5 and Equation 6) and the catchment characteristics described in Carroll (1981). These estimations are summarised in Table 9. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 16 of 59 June 2008 Table 9: Summary of mean annual flows. Variable Ferbane Millbrook Br. Rahan Tullamore Area (km2) 1207 165 274 114.8 STMFRQ 0.85 1.92 0.84 0.319 SOIL 0.382 0.300 0.304 0.341 Rsmd 30.2 34.2 29.1 34.4 SAAR 919 941 987 900 LAKE 0.169 0.000 0.080 0.000 S1085 0.87 5.55 0.87 1.656 Mean Annual Flow (Rsmd) 113.84 28.34 21.89 12.03 Mean Annual Flow (SAAR) 119.98 27.47 25.92 11.55 3. Factors relating the estimate of the mean annual flow at the Tullamore water level recorder to the estimate of the mean annual flood flows at the alternative water level recorders were produced using the data presented above. These factors are summarised in Table 10. Table 10: Mean annual flood flow factors. Water level recorder Factor (Rsmd) Factor (SAAR) Tullamore 1.000 1.000 Ferbane 0.1057 0.0963 Millbrook Bridge 0.4244 0.4204 Rahan 0.5496 0.4455 The factors derived using Rsmd were adopted as they produce the highest flow estimates and are therefore most conservative. 4. The design flood flows at the alternative water level recorders were estimated by completing a statistical analysis of annual maximum flow data assuming the EV1 statistical distribution. This statistical analysis and the resulting design flood flow estimates are summarised in Table 11. Charts demonstrating the appropriateness of the EV1 statistical distribution are presented in Appendix F. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 17 of 59 June 2008 Table 11: Summary of statistical analysis and resulting peak flood flow estimations. Peak Flood Flow at the Tullamore Water Level Recorder (m3/s) T (Years) AEP (%) Ferbane Millbrook Bridge Rahan - u 77.10 15.88 3.10 - α 16.75 3.10 4.02 2.3 Mean Annual 86.79 17.67 23.49 5 20 102.22 20.53 27.19 50 10 114.79 22.85 30.21 20 5 126.84 25.08 33.10 50 2 142.45 27.97 36.85 100 1 154.14 30.13 39.66 1000 0.1 192.77 37.28 48.93 5. The peak flood flows for the alternative water level recorders (refer to Table 11) were translated to the Tullamore water level recorder using the factors presented in Table 10. The resulting peak flood flow estimates for the Tullamore water level recorder are presented in Table 12. Table 12: Design flood flow estimates at the Tullamore water level recorder. Peak Flood Flow at the Tullamore Water Level Recorder (m3/s) T (Years) AEP (%) Ferbane Millbrook Bridge Rahan 2.3 Mean Annual 9.17 7.50 12.91 5 20 10.80 8.71 14.94 50 10 12.13 9.70 16.60 20 5 13.40 10.65 18.19 50 2 15.05 11.87 20.25 100 1 16.29 12.79 21.79 1000 0.1 20.37 15.82 26.89 Table 12 shows a variation in design flood flow estimates for the Tullamore water level recorder depending on the alternative water level recorder. To overcome this variation, an average of the three estimates could be adopted. Instead however, the design flow estimates using the Rahan water level recorder have been directly adopted, given that: - The Ferbane catchment is more than eighty times the Tullamore River catchment. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 18 of 59 June 2008 6.3. - The hydrological characteristics of the Millbrook Bridge catchment are significantly different from the Tullamore River catchment (refer to Table 9). - The Rahan water level recorder provides the largest and therefore most conservative estimate for design flood flows at the Tullamore River recorder. Adoption of design flood flows The two methods used to estimate design flood flows at the Tullamore water level recorder produced different estimates (refer to Table 13). Table 13: Design flood flow estimates at the Tullamore water level recorder. Design flood flows (m3/s) T (Years) AEP (%) Method A* Method B** 2.3 Mean Annual 8.27 12.91 5 20 9.92 14.94 50 10 11.33 16.60 20 5 12.82 18.19 50 2 14.64 20.25 100 1 16.21 21.79 1000 0.1 21.07 26.89 * Derived using the available flow dataset at the Tullamore River water level recorder. ** Derived using longer-term and more reliable flow datasets at Ferbane, Millbrook Bridge and Rahan water level recorders It was decided that the design flood flows adopted for the Tullamore FRAM Study would be those derived using Method B (refer to Section 6.2). The justification for this decision is: - It avoids the need to use the relatively unreliable flow dataset available from the Tullamore River water level recorder (refer to discussion in Section 5.4.3). - It utilises long and reliable flow datasets (i.e. around 50 years). - It utilises observed flow datasets that produce mean annual flood flow estimates that, as is the case with the Tullamore water level recorder, are consistently larger than estimates produced using the FSR six variable equations. - It places significant weight on the flow dataset available from the Rahan water level recorder (i.e. of the three alternative water level recorders, Rahan has a catchment that has the most similar hydrological characteristics when compared with the Tullamore River water level recorder). - It takes into account the consistent difference between the observed and regional growth factors (refer to Table 14). D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 19 of 59 June 2008 Table 14: Summary of growth factors Growth factor (Qbar indexed) T (Years) AEP (%) Ferbane Millbrook Bridge Rahan Regional 2.3 Mean Annual 1.00 1.00 1.00 1.00 5 20 1.18 1.16 1.16 1.20 50 10 1.32 1.29 1.29 1.37 20 5 1.46 1.42 1.41 1.55 50 2 1.64 1.58 1.57 1.77 100 1 1000 0.1 1.78 2.22 1.71 2.11 1.69 2.08 1.96 2.55 Therefore, to confirm, the adopted design flood flows at the Tullamore water level recorder are shown in Table 15. Table 15: Adopted design flood flows at the Tullamore water level recorder. T (Years) AEP (%) Design flow (m3/s) 7. 2.3 Mean Annual 12.91 5 20 14.94 50 10 16.60 20 5 18.19 50 2 20.25 100 1 21.79 1000 0.1 26.89 Inclusion of allowances for long-term catchment changes As noted in Section 5.5, the Tullamore FRAM Study looks at the long-term management of flood risk. It is therefore important that this hydrological investigation gives consideration to how the hydrological characteristics of the Tullamore River catchment will change in the 50 to 100 years. The foreseeable changes considered by this investigation are discussed in Section 5.5. The resulting future flood flows are presented in Table 16. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 20 of 59 June 2008 Table 16: Future design flood flows at the Tullamore water level recorder Flood flow (m3/s) T (Years) AEP (%) 8. Design (present) Future 2.3 Mean Annual 12.91 15.49 5 20 14.94 17.93 50 10 16.60 19.92 20 5 18.19 21.83 50 2 20.25 24.30 100 1 21.79 26.15 1000 0.1 26.89 32.27 Grand Canal The Grand Canal, which is operated by Waterways Ireland, runs through the Tullamore River catchment. Under normal operating conditions the Grand Canal would not be expected to significantly interact with the hydrology of the Tullamore River catchment. However, if the canal water level cannot be maintained during normal operation of the canal infrastructure (e.g. during significant rainfall), an overflow into the Tullamore River catchment is utilised to remove excess flow. This overflow consists of an arch culvert that discharges into a side channel controlled by a weir (See Figure 7). Figure 7: Overflow weir from the Grand Canal. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 21 of 59 June 2008 The overflow is located upstream of Tullamore between the 21st and 22nd lock of the Grand Canal. The channel that the Grand Canal overflows to flows south and discharges to the Tullamore River 2.5km downstream of the overflow. This channel discharges to the Tullamore River 5.5km upstream of the Tullamore Urban Area. The significance of this overflow into the Tullamore River catchment was determined by assessing the maximum flow that would be expected from the canal overflow. The steps followed were: 1. The overflow was modelled as a broad crested weir that was assumed to perform based on Equation 7. Equation 7: Flow across a broad crested weir. Q = 2/3 H ( 2/3 g H )½ L Where: Q Flow across the weir (m3/s) H Average depth of flow across the weir (m) L Length of the weir (m) 2. The dimensions of the weir were measured on-site by OPW staff, while the likely maximum flow depth across the weir was estimated by Waterways Ireland staff (refer to Table 17). Table 17: Dimensions of canal overflow weir D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 22 of 59 June 2008 Dimension Value Source Weir length 24 m Visual inspection Maximum water depth observed 0.1 m Waterways Ireland Note: Due to overgrown vegetation, the observed weir length was 10 m. However, given that Waterways Ireland may clear this vegetation, the weir length was retained at 24 m. 3. The expected maximum flow was calculated as 1.3 m3/s based on Equation 7 and the dimensions contained in Table 17. 4. The significance of this overflow from the Grand Canal relative to the adopted design flood flows at the Tullamore River water level recorder is summarised in Table 18. 5. The expected overflow from the Grand Canal was not included in the design flood flows adopted by this investigation given that: - Given that the overflow is located around the top of the Tullamore River catchment, the peak overflow is unlikely to coincide with the peak flood flow within the Tullamore urban area. - There is some uncertainty as to when the overflow will operate. Table 18: Grand Canal overflows relative to adopted design flood flows. T (Years) AEP (%) Adopted design flow (m3/s) Grand Canal overflow (%) 2.3 Mean Annual 12.91 10.0 5 20 14.94 8.7 50 10 16.60 7.8 20 5 18.19 7.1 50 2 20.25 6.4 100 1 21.79 5.9 1000 0.1 26.89 4.8 - 6. The impact of the overflow from the Grand Canal on flows in Tullamore requires further investigation and should be examined prior to the detailed design stage of the Tullamore FRAM, see Recommendations. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 23 of 59 June 2008 9. Conclusion The adopted design flows from this report are suitable for the purpose of the FRAM study; however for detailed design of flood relief measures further hydrological examination is required to increase confidence and accuracy, see Section 10 Recommendations. 10. Recommendations Before a detailed design can be produced three issues need to be addressed: 1. The ability to establish accurate design flows based on observed data. 2. The instability of the rating equation for the Tullamore water level recorder, see Section 5.4.3 Manipulation of available data sets. 3. Include the overflow from the Grand Canal in the upstream flow estimate.. In order to address these issues, the following steps should be taken as soon as possible: 1. At least one additional gauging station is required in the catchment. It is recommended that this station be located in the vicinity of Springfield Bridge and should be capable of collecting data suitable for project analysis, i.e. mid to high flows. A second station (should it be agreed) would be usefully employed at Riverside Bridge. 2. Additional flow measurements are required at the Tullamore Hydrometric Station to address the issues raised in Section 5.4.3 (Manipulation of available data sets). Should this data prove the lack of suitability of this station then it would be necessary to locate a new Hydrometric Station within the town. 3. A staff gauge should be placed on the canal overflow weir and readings taken during times of overflow and, if possible, flow measurements. These readings coupled with readings at the gauged station can then be used to assess the impact of the canal overflow on flows in Tullamore. D1791 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 24 of 59 June 2008 11. References Bruen, Michael (2003), “Climate Change Impacts on Flooding in Ireland – A Desk Study”. Carroll, D (1981), “Estimates of the Values of Catchment Characteristics for OPW Gauging Stations”. Hayes, Mark (2002). Unpublished research into the hydrology of the Tullamore River catchment. Houghton-Carr, Helen (1999), “Flood Estimation Handbook 4: Restatement and application of the Flood Studies Report rainfall-runoff method”. Meteorological Service Ireland (1980). “Mean Annual Rainfall Map (1951 - 1980)”. Natural Environment Research Council (1975). “Flood Studies Report”. Offaly County Council, “Offaly County Development Plan 2003 – 2009”. Office of Public Works Design Section Press Archive. Office of Public Works (2005). “Interim Report on Hydrology and Hydraulics, Tullow Flood Relief Feasibility Study”. D1794 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 25 of 59 June 2008 Appendices A. Plan of principle study area for the Tullamore FRAM Study B. Plan of the Tullamore River catchment C. Plan of the Tullamore urban area within the Tullamore River catchment D. Plan of relevant rain gauges and water level recorders E. Gauged points for the Tullamore water level recorder F. EV1 plots for Ferbane, Millbrook Bridge and Rahan D1794 – Tullamore FRAM Study Doc. No. 1794/RP/003/D Page 26 of 59 June 2008
© Copyright 2026 Paperzz