quote request - City of Dodge City

QUOTE SHEET
SCHOOL ZONE IMPROVEMENTS –HAWK SIGNAL UPGRADE & SOLAR
POWERED FLASHING BEACON INSTALLATIONS
(ST 1705)
TO:
City of Dodge City
806 Second Avenue
P.O. Box 880
Dodge City, Kansas 67801
The City of Dodge City and USD 443 are looking to make safety upgrades to three school zones
through the installation of solar powered flashing 20 mph beacons and the conversion of a
crosswalk signal to a HAWK signal. These improvements call for the installation of 7 solar
powered beacons with an add alternate of one beacon (8 total with add alternate) and one
crosswalk signal conversion to a HAWK.
This work is to be completed in the summer months while school is out. All signal materials are
to be purchased from Gades Sales out of Wichita, KS. Material estimates for the beacons and the
signal conversion are attached, along with approximate beacon locations and concrete signal
base specs (KDOT pedestal bases).
ANTICIPATED START DATE:
CONSTRUCTION DAYS NEEDED:
The undersigned hereby proposes to comply with the City of Dodge City’s Standard
Specifications and complete the project for the following prices:
DESCRIPTION
UNIT
QUANTITY
1. Solar School Beacon, Installed
2. HAWK Signal Upgrade
Each
L.S
7
1
UNIT
PRICE
$
$
AMOUNT
$
$
BASE BID AMOUNT
BID ALTERNATE
1. Solar School Beacon, Installed
Each
1
$
$
TOTAL BID AMOUNT
The above unit prices should include all costs associated with installation, including mobilization
and traffic control. These costs will be considered incidental for which no additional payment
will be made. Each submitted quote shall remain valid for at least 45 days from the due date of
this quote.
The City reserves the Right to Refuse any and all Quotes. Per City policy, Performance Bonds are
not required on projects under $50,000.
Q-1
FIRM: ___________________________________
BY:
___________________________________
POSITION: _______________________________
ADDRESS: _________________________________
_________________________________
_________________________________
PHONE: _________________________________
DATE:
_________________________________
Questions about the existing crosswalk signal may be directed to Corey Keller at
[email protected]
Quote Sheet needs to be returned to the Engineering Office by 2:00 pm on Tuesday, March
14th, 2017. Quote sheet may be mailed, hand delivered, or emailed to [email protected].
Q-2
Quote
Date:
Quote to:
Mr. Tanner Rutschman
City of Dodge City
Job:
10/04/16
6th Street Pedestrian Crossing
"Hawk" Signal Upgrade
[email protected]
Qty
4
2
2
2
1
1
1
Description
3 Section Signals "Hawk" Configuration
with Backplates and Mast Arm Mounting
Brackets
Pedestrian Signals w/Countdown LED's
and Clamshell Mounting Brackets
Standard ADA Pushbuttons w/Signs
R10-23 Signs w/Mast Arm Mounting Brackets
EPAC Controller, Conflict Monitor, Load
Switches, Flash Transfer Relays, and
Miscellaneous Equipment to Convert
Existing Cabinet to "Hawk" Configuration
Technical Assistance to Modify Cabinet
Lot Price
Unit Price
Line Total
$7,860.00
$7,860.00
Upgrade to Audible Pedestrian Stations
would cost an additional $986.00
Price reflects re-using the existing controller
cabinet, pedestal pole, mast arms and
signal poles. If any of this equipment needs
to be replaced, additional pricing will be
provided.
Total
Delivery is approximately 30 - 45 days after approval and release of order.
By: Sharon Quaney
[email protected]
PO Box 9003, Wichita, KS 67277 - 316-943-1219
$7,860.00
Quote
Date:
Quote to:
Mr. Tanner Rutschman
City of Dodge City
Job:
10/04/16
School Beacons
[email protected]
Qty
2
Description
Solar School Beacon Pedestal Assembly:
(1) 15' Aluminum Pedestal w/Collar
and Anchorage
(3) 12" Yellow LED Beacons w/Mounting
(1) S5-1 Fluorescent Green School Sign
(1) S5-2 End School Zone Sign
(2) SH0206 Sign Mounting Brackets
(1) Solar Controls w/85 Watt Solar
Panel, Mounting Bracket, Battery/
Control Cabinet w/100 Amp Gel
Cell Battery, Flasher, Regulator and
Time Clock
Unit Price
$3,465.00
Please note that the unit price above is Per Pedestal
Pole. There are two poles per School Zone.
Total
Delivery is approximately 30 - 45 days after approval and release of order.
By: Sharon Quaney
[email protected]
PO Box 9003, Wichita, KS 67277 - 316-943-1219
Line Total
$6,930.00
$6,930.00
57