March 2011 | Frontier Economics, Atkins, ITS 1 Appendix 6 – M1 Northern Motorway in Ireland This chapter presents the results of the ex post evaluation of the construction of the M1 motorway in Ireland between the Dublin Airport Interchange and the start of the Balbriggan Bypass. 6.1 Introduction 6.1.1 Project overview Location This project covers the construction of two sections of the M1 motorway in Ireland. Figure 1 shows the route under analysis. The M1 runs along the East Coast of Ireland and the existing N1. Figure 1. M1 Motorway Ireland (between the Dublin airport Interchange and the Balbriggan Bypass Balbriggan Bypass Lissenhall Interchange Airport Interchange Dublin Source: Openstreetmap.org The M1 corridor has been constructed in several phases over a period of 25 years. The M1 corridor belongs to the TEN-T Priority Axis 13 (Ireland – United Kingdom – Benelux). The main objective of the investments in this corridor is Appendix 6 – M1 Northern Motorway in Ireland 2 Frontier Economics, Atkins, ITS | March 2011 the reduction in journey times between Ireland, the UK and mainland Europe. Figure 2 show the route of the Priority Axis 13. Figure 2. Priority Axis 13: Ireland – United Kingdom – Benelux M1 Source: EC (2005) 1 Description This project comprises two subprojects, Section 1 and Section 2. Section 1 – 2000/16/CPT/002: Cloghran (Dublin Airport) to Lissenhall Section 2 – 2000/16/CPT/003: Lissenhall to Balbriggan Section 1 Section 1 (shown in Figure 3), involved linking the pre-existing M1 motorway at Dublin Airport to Section 2 (described below) at the Lissenhall Interchange. The total length of this section of dual 2-lane motorway is 6.52km. The motorway 1 European Commission (2005) Trans European Transport Network Ten- T priority axis and projects 2005. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 3 was constructed along with two interchanges (at Cloghran and Lissenhall) and Figure 3. Section 1 – New Route - M1 (A – B), Old Route - R132 (C - D) D B Existing Route New Route Airport C A Source: Openstreemap.org nine bridges (including one elevated bridge). As it can be seen from the map, one of the key destinations for vehicles using this route is Dublin Airport. This is one of the key reasons for the large increase in traffic along this route. Moreover, this is one of the main routes down the East Coast of Ireland to Dublin. Prior to the construction of this section of the M1, the then-N1 (now the R132) provided the infrastructure for these trips and was becoming heavily congested. The Cohesion Fund contributions were used initially in the planning and preconstruction phases. This covered initial design, detailed design, site surveys and investigation, the Environmental Impact Assessment, a public consultation process and the preparation of contract documentation. EC contributions were then used to cover building and construction costs, including earthworks, Appendix 6 – M1 Northern Motorway in Ireland 4 Frontier Economics, Atkins, ITS | March 2011 pavement, drainage and fencing and the construction of nine bridges. Interchanges, side roads and land acquisition were not covered. From an environmental point of view, one of the key concerns with this section was that it was due to run through the Broadmeadow Estuary, which was defined in the County Development Plan as an Area of Scientific Interest because of its Ornithological, Botanical and Zoological importance. For this reason, the plan considered a number of possible options, including a range of tunnels and bridges. Section 2 Section 2 (shown in Figure 4) provides the link between Lissenhall (Section 1) and the Balbriggan Bypass section of the M1. The Balbriggan Bypass section of the M1 was previously opened in 1998. The project involved building a 9.86km-long section of dual 2-lane motorway (with hard shoulder) as well upgrading an existing interchange. Figure 4. Section 2 – New Route - M1 (A – B), Old Route - R132 (C - D) B D New Route A Existing Route C Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 5 This section of the route crosses four side roads. When turned into a motorway, it required grade separation, by means of four overbridges. Also in this case, prior to the construction of the M1, the then-N1 (now the R132) was carrying most of the traffic. In linking up with Section 1, Section 2 provides a better connection to Dublin, the Airport and the Port, as well as to the South and to Northern Ireland. The Cohesion Fund contribution was used for the building and construction costs the motorway, including the earthworks, pavement, drainage, fencing, and the construction of 4 bridges. It was not used for structures, interchanges, side roads and land acquisition. As can be seen from Table 1 the total cost of the project was €232.4m of which €173m was eligible for Cohesion Fund assistance. Costs by section are as follows: Section 1: Cloghran to Lissenhall (total cost – €162.9m) Cohesion funding of (€97.9m); and, Section 2: Lissenhall to Balbriggan (total cost – €69.4m) Cohesion funding of (€54.0m) The Cohesion Fund contributed €151.8m which is approximately 88% of the eligible project costs. Both sections were opened to traffic at the end of June 2003. Table 1. M1 Northern Motorway Costs (€millions) National contribution EU Funding Sub-total Total Sect 1 Cloghran to Lissenhall 52.1 12.9 97.9 110.8 162.9 Sect 2 Lissenhall to Balbriggan 7.2 8.2 54.0 62.2 69.4 59.4 21.2 151.8 173.0 232.4 Total 6.1.2 Eligible costs Noneligible costs Context In this section, we present the context in which this project was conceived and developed. The first part focuses on the evolution of the socio-economic context in the run up to the project application. In the second part, we present the strategic policy context and the key objectives of the project. Appendix 6 – M1 Northern Motorway in Ireland 6 Frontier Economics, Atkins, ITS | March 2011 Socio-economic context Since joining the EU in 1973, Ireland has experienced a long period of economic growth. Figure 5 shows the evolution of GDP per capita since the early 1980s. GDP per capita continued to grow until 2008, when it fell due to the global economic crisis. Confirming a well-known relationship between GDP and travel volumes, this rapid economic growth was matched by a growth in total vehicle kilometre, as shown in Figure 6. Over the period 1999-2009, due to a net increase in immigration, population has grown by 19%. Figure 5. GDP per capita (Constant Prices, Euros) in Ireland (1980 – 2009) GDP per Capita (Constant Prices, Euros) 50,000.00 45,000.00 40,000.00 35,000.00 30,000.00 25,000.00 20,000.00 15,000.00 10,000.00 5,000.00 0.00 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 Source: Eurostat Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 7 Figure 6. Change in Vehicle Kms (2000 – 2008) 50,000 All 45,000 Private cars Goods vehicles Million vehicle kms 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 0 2000 2001 2002 2003 2004 2005 2006 2007 2008 Source: CSO (2009) Strategic policy context The 1994-1999 Irish National Development Plan set out a strategy of achieving greater economic and social cohesion. In this plan, the two sections being considered in this report (otherwise known as the M1 northern Motorway) were identified as one of the four key corridors in Ireland to be improved. We note that they were not originally seen as two separate entities, but as a single route. The project was then broken up into two separate subprojects for the purpose of the Funding Applications. The Final Report for this project states that “High quality transport infrastructure is vital to economic development in Ireland as roads are the dominant mode of internal transport, accounting for 90% of freight traffic and 96% of passenger traffic. Because of Ireland‟s peripheral location, an island beyond an island, sea and air routes fulfil the same role for Ireland as cross frontier land transport links fulfil for other EU Member States. Therefore the attainment of social and economic advancement for Ireland requires significant improvement of access to and from the principal exit/ entry airports and seaports. The development of the M1 route is vital in this regards as it links key commercial seaports and airports.” The two sections are believe to fulfil this key objects on a number of levels. European level. They are part of the Trans – European Road Network; Appendix 6 – M1 Northern Motorway in Ireland 8 Frontier Economics, Atkins, ITS | March 2011 National Level. They provide a new section of EO1 linking the major commercial seaports at Larne, Belfast, Dublin and Rosslare and the major airports of Dublin and Belfast; Regional level. They form an essential part of the M1 extending orth from Dublin and along the principal cross border route providing access to Belfast and Northern Ireland ports; and, Local level. They provide a more reliable service for towns in the areas of Swords, Balbriggan, Drogheda and Dundalk. Table 2 summarises the key objectives for both sections, as stated in both the Funding Applications and the Final Report. Out of the following objectives, those relevant for the cost benefit analysis are the reductions in transport costs and improvements in the safety levels. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 9 Table 2. Objectives for the M1 Northern Motorway Objectives 1. Help alleviate the impact of Ireland’s peripheral location, particularly by reducing transport costs by facilitating the competitiveness in the production and export of goods 2. Provide essential infrastructure support for economic (particularly industrial and tourism) development by improving access to Dublin Port, Dublin Airport and the main domestic markets. 3. Improve access to the less developed Border Midland and Western Region thereby enhancing its attractiveness as a location for investment and economic development 4. Improve transit times, safety levels and level of service 5. Reduce travel times and improve access between Dublin and Belfast. Both Cities have important trading links and these should be strengthened as a result of the improvements. 6. Contribute to the provision of a consistent standard of motorway 7. Overcome the inadequacies of the existing N1 in facilitating long distance international and national traffic, as well as the longer journeys of traffic generated locally 8. Reduce transport costs and facilitate competitiveness in the transport of goods 9. Improve environment quality and reduce vehicle/ pedestrian and cyclist conflict Source: Application forms and Final Report 6.1.3 Sources Stakeholders To carry out the analysis, we have relied on a variety of different sources, provided by various stakeholders in Ireland. The stakeholders that we consulted for this evaluation were: National Roads Authority (NRA); Department of Finance (EU Cohesion Fund); Representative of Fingal County Council (promoters of the project); AECOM – Consultants (formerly Faber Maunsell) who conducted the Year 1 ex post appraisal; Road Safety Association (RSA), and; Appendix 6 – M1 Northern Motorway in Ireland 10 Frontier Economics, Atkins, ITS | March 2011 DG REGIO (Irish Desk Officer) Table 3 provides the list of the documents we have used for this evaluation. Table 3. Summary of project-related documentation Documents Obtained from Funding Applications DG REGIO Funding Decisions and Financing Memoranda DG REGIO Ex ante CBA (Fingal County Council – An application of Economic appraisal methods to the northern motorway project, Airport Motorway to Rowan’s road exchange) Irish NRA Final Reports DG REGIO Ex post CBA reports Roughan & O’Donovan Faber Maunsell (2004a) Cloghran - Lissenhall / 200016 CPT002 Roughan & O’Donovan Faber Maunsell (2004b) Lissenhall – Balbriggan / 2000IE16CPT003 DG REGIO and NRA For the ex post analysis we have also relied on a series of information. These are listed in Table 4. Table 4. Summary of Primary & Secondary Data sources Data Source Traffic Count Data and Traffic Speeds http://www.n3.ie/NetworkManagement/Tr afficCounts/TrafficCounterData/ Traffic Count Data Consultants Own Accident data Post Opening http://www.rsa.ie/RSA/Road-Safety/OurResearch/Ireland-Road-Collisions/ Accident data (pre opening) Local Data on accidents Appraisal Parameters Irish National Roads Authority One year ex post appraisal Consultants Reports and outputs Surveys No surveys were commissioned as part of this work as observed ex post data on traffic levels and journey times were available from the NRA. Interviews In addition to obtaining the relevant documentation and data, we had a meeting with key stakeholders in Ireland. The meeting had four key objectives: Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 11 discuss the role and usefulness of the ex ante CBA in the decisionmaking process that led to the development of the project under evaluations; clarify our understanding of the calculations and assumptions underpinning the ex ante CBA; identify missing data needed for the ex post analysis and make agreements relative to the provision or sourcing of this information; and, discuss the project‟s wider economic, social and environmental impacts which are not captured by the standard core CBA. Throughout this evaluation, we have also received regular support and advice (via email and telephone) from the NRA in Ireland. 6.1.4 Issues and challenges with the evaluation As a full ex post evaluation had already been carried out following the opening of the two sections of the M1 motorway the evaluation involved updating this work to take account of the changes that have happened since 2003. One of the key challenges was in using data and models that had been developed in 2004, and updating them in a consistent manner. 6.2 Ex post cost-benefit analysis This section presents the results of the ex post cost-benefit analysis for the two subprojects. In May 2004, one year after the opening, a comprehensive ex post appraisal was completed for both sections of the M1. This was in line with current Irish guidelines, according to which a Post Project Review should be completed for all projects costing more than €30m. An alliance of consultants (Roughan & O‟Donovan and Faber Maunsell – now AECOM) completed the Economic Assessment. The economic evaluation reports, one for each section, note that that “one objective of the phase 7 [Ex Post] assessments has been to determine how the observed benefits of a project compare with those predicted at Phase 3 [Route Selection] and Phase 4 [Preliminary Design]. For the current project, this is difficult due to the length of time since undertaking the phase 4 modelling and the significant changes in the recommended parameter values in the interim. As such a direct comparison [with the ex ante analysis] would be of limited value to the work” The ex post reports that were produced in 2004 for the two sections did not draw on the results if the ex ante cost benefits analysis. Appendix 6 – M1 Northern Motorway in Ireland 12 Frontier Economics, Atkins, ITS | March 2011 First, we present the results from the 2004 ex post appraisal (Year One ex post evaluation). We then show how these results change when considering additional ex post traffic data for the period 2004-2009 (Year Five ex post evaluation). 6.2.1 Headline results from the analysis The key economic benefits from this project were the reduction in travel costs (both journey times and vehicle operating costs) and the improvement of safety on the route. Before this project, the N1 route was heavily congested. The project has played a significant role in reducing congestion, hence time savings are one of the main benefits in the ex post analysis. The key costs of this project considered in the ex post appraisal are construction costs and maintenance costs. It should be noted that in the original ex ante appraisal maintenance costs were omitted from the analysis. Economic analysis Year One ex post evaluation Table 5, Table 6 and Table 7 below summarise the results of the one year ex post appraisal for, respectively, Section 1, Section 2 and the entire project. The ex post analysis considers both a Low case and a High case, determined by the assumption about future traffic levels. The evaluation assumed a project economic life of 30 years. In the original analysis, the NPV had been calculated using a 4% discount rate. We have updated this analysis by using a 5.5% discount rate, in accordance with EC guidelines. The original ex post evaluation included a value for the shadow price of capital (or marginal cost of public funds). The implication of such a shadow price is that the welfare cost of public funds is greater than the financial costs. The use of a shadow price of capital was common practice in Irish appraisal in 2004. At present a shadow price factor of unity is applied to government funds and labour. Our update to the one year ex post appraisal therefore uses a shadow price of capital of unity. This results in the NPV, BCR and IRR all increasing relative to the ex post analysis conducted for the NRA. The results indicate that both sections offer very good value for money. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 13 Table 5. One year ex post Appraisal: Section 1 (€m, 2002 prices) Low Case High Case 2,643 2,877 Economic IRR (%) 55 56 Benefit-cost ratio 16.9 18.35 Net Present Value (€m) Source: Ex Post Report for M1 Northern Motorway: Contract 1: Cloghran to Lissenghall Table 6. One year ex post Appraisal: Section 2 (€m, 2002 prices) Low Case High Case Net Present Value (€m) 652 755 Economic IRR (%) 39 42 Benefit-cost ratio 10.4 11.9 Source: Ex Post Report for M1 Northern Motorway: Contract 2: Lissenhall to Balbriggan Table 7. One year ex post Appraisal: Total (€m, 2002 prices) Low Case High Case 3632.4 3295 Economic IRR (%) 52 53 Benefit-cost ratio 15.04 16.45 Net Present Value (€m) Source: Own calculation Year five ex post evaluation As mentioned above, we have updated the analysis carried out in 2004 with more up-to-date values, including outturn traffic data for the period 2004-2009. The results are summarised in Table 8, Table 9 and Table 10. The updated analysis shows that the two subprojects offer an even greater value of money than what identified in the one year ex post evaluation. Appendix 6 – M1 Northern Motorway in Ireland 14 Frontier Economics, Atkins, ITS | March 2011 Table 8. Five year ex post Appraisal: Section 1 (€m, 2002 prices) Low Case High Case 3082 3160 Economic IRR (%) 56 56 Benefit-cost ratio 19.5 20.1 Net Present Value (€m) Source: Ex Post Report for M1 Northern Motorway: Contract 1: Cloghran to Lissenghall updated with outturn data Table 9. Five year ex post Appraisal: Section 2 (€m, 2002 prices) Low Case High Case Net Present Value (€m) 722 745 Economic IRR (%) 42 42 Benefit-cost ratio 11.4 11.8 Source: Ex Post Report for M1 Northern Motorway: Contract 2: Lissenhall to Balbriggan updated with outturn data Table 10. Five year ex post Appraisal: Total (€m, 2002 prices) Low Case High Case 3805 3905 Economic IRR (%) 53 53 Benefit-cost ratio 17.2 17.6 Net Present Value (€m) Source: Own calculation Annexe I provides the detailed results of the analysis Financial analysis The project does not generate any operating revenues, however, for completeness we have carried out a financial analysis of the project. Table 11 Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 15 presents both the return on investment and the return on capital (2002 prices, 5% discount rate, 30 year appraisal period). Clearly as no revenues are generated the FNPV indicators are negative. Furthermore, as no revenues are generated at any point in the lifetime of the project neither of the Financial IRR indicators can be calculated. The lack of revenues also means that the low and high growth results are the same. Table 11. Summary of ex post financial analysis (2002 prices) Low/High case Net Present Value – Investment (€m) Financial IRR – Investment (%) Net Present Value – Capital (€m) Financial IRR – Capital (%) -234.8 N/A -81.4 N/A Source: Own calculation Wider socio-economic impacts It is difficult to establish a link between the project and wider socio-economic impacts as the project was implemented during a period of rapid growth in the Irish economy and significant in-migration. It is however clear that the project has formed an important component of the general upgrade of the Ireland‟s transport network. The construction of the project was also a key factor in facilitating the construction of the second terminal at Dublin Airport. Furthermore there is evidence of substantial growth in the towns adjacent to the project and where the congestion levels have dropped as a result of the M1 Northern Motorway. 6.2.2 Traffic volumes Traffic volumes largely influence the benefits of a transport project. We first present the traffic volume assumptions that underpinned the Year One ex post evaluation. We then show the updated outturn data for the period 2004-2009 and the assumptions we have used for the Year Five ex post evaluation. Year One ex post evaluation For this evaluation, traffic counts were undertaken at 13 locations along the existing route. Traffic counts for the new sections of the M1 were taken from the NRA traffic counter sites. The existing route was split into 12 separate links. The proportions for different vehicle types were estimated based on the observed data for two of these links. The proportions used for the analysis were as follows: Appendix 6 – M1 Northern Motorway in Ireland 16 Frontier Economics, Atkins, ITS | March 2011 Cars – 79.1% LGVs – 7.9% HGVs (2 categories) – 11.2% PSVs – 1.8% The 2003 traffic volumes were then increased using the NRA traffic growth factors, shown in Table 12. The table shows the growth factors for vehicle-kms for different types of vehicles, year bands and scenarios (Low case and High case). Table 12. Traffic Growth Factors Cars and LGV HGV1 AND HGV2 PSV Low High Low High Low High 2002-2007 2.999 4.187 2.702 3.781 0.340 0.982 2007-2012 2.167 2.884 2.277 3.043 0.354 1.006 2012-2017 1.504 1.943 1.584 2.052 0.428 1.090 2017-2022 1.226 1.554 1.476 1.871 0.518 1.190 2022-2027 0.921 1.201 1.371 1.759 0.604 1.288 2027-2032 0.677 0.905 1.267 1.628 0.660 1.360 2032-2037 0.534 0.727 1.163 1.490 0.660 1.360 Source: NRA Appraisal Guidelines Year Five ex post evaluation We have updated the data used for the Year One appraisal using actual traffic volume data. The NRA maintains a network of approximately 140 traffic counters on National Roads throughout Ireland.2 We have obtained information on Average Annual Daily Traffic (AADT) in both directions for the two sections of the M1 under analysis. Table 13 shows the updated historic traffic data we have used. As can be seen the motorway is well used with around 80,000 on Section 1 and just over 50,000 vehicles per day on Section 2. We have also validated the data, using data from a Quality Bus study in the area. The vehicle category proportions were taken from 2 http://www.n3.ie/NetworkManagement/TrafficCounts/TrafficCounterData/ Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 17 NRA guidelines and validated using the known percentages of HGVs taken from the traffic count data. Table 13. AADT(Vehicles) along the new sections of M1 Year Section 1 Section 2 2004 Not Available 41,869 2005 Not Available Not Available 2006 70,752 49,253 2007 77,856 51,821 2008 80,232 53,479 2009 79,847 52,543 Source: http://www.n3.ie/NetworkManagement/TrafficCounts/TrafficCounterData/ In Section 1, over the period 2003-2007, traffic grew by 9.8% per annum. This was considerably higher than the traffic forecasts used for the Year One ex post evaluation. However on average in the period 2008-2009 traffic volumes fell by –1%. This was below the forecasts. In Section 2, traffic grew at a slower rate than in section 1. The average annual growth rate was 5.5% in the period 2003-2007. This was still higher than the original forecast. However, during the period 2008-2009 traffic volumes only grew by 0.7%, significantly below the forecast. Figure 7 shows both historic traffic growth (in vehicle kilometres) and the traffic projection for the period after 2009, for both ex post analyses that have been undertaken. We have used the same growth rate used in the NRA‟s Year One ex post evaluation as the NRA has not yet released updated forecasts. In order to carry out the appraisal, we have converted AADT in annual vehiclekms using the following formula VehicleKms AADT * 365* SectionLength Appendix 6 – M1 Northern Motorway in Ireland 18 Frontier Economics, Atkins, ITS | March 2011 Figure 7. Growth in vehicle kms over complete project 1500 1400 Vehicle kms (millions) 1300 1200 1100 1000 1 year ex post low 900 1 year ex post High 5 year ex post Low 800 5 year ex post High 700 2031 2029 2027 2025 2023 2021 2019 2017 2015 2013 2011 2009 2007 2005 2003 600 Source: Own calculation 6.2.3 Costs One-off costs Table 14 provides a break down of the outturn costs by cost category for both sections of the M1 Northern Motorway. Whilst Section 2 is longer (9.56 km) than Section 1 (6.52 km), the latter was more expensive. This is because nine bridges were required to bypass the urban area of Swords. This included a specialist bridge that was needed to bypass the environmentally sensitive estuary. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 19 Table 14. Outturn costs for both sections (€m, resource costs, 2002 prices) Year Section 1 Design Costs Section 2 Total 3.5 3.3 6.8 36.9 6.9 43.8 Construction 122.4 59.1 181.5 Total 162.8 69.3 232.1 Land Acquisition Source: Ex Post Report and Financial Reports Only Level 1 unit costs are available for the M1 Northern Motorway. As can be seen from Table 15 these are higher for Section 1 than for Section 2 due to the larger number of structures in that section of the route. Table 15. Unit costs (€m, resource costs, 2002 prices) Road Indicators Unit Section 1 Section 2 Combined 24.99 7.04 14.19 Level 1 'All in' unit cost EURm/km Source: Own calculation Ongoing costs Maintenance costs were not included in the ex ante appraisal nor in the Year One ex post evaluation. However, we have included them in the Year Five ex post evaluation, using the parameter (cost per kilometre) provided by the NRA‟s appraisal guidelines and considering the differences in length of road to maintain between the do-nothing counterfactual and the do-something scenario. Table 16 summarises the difference between counterfactual and do-something scenario. Appendix 6 – M1 Northern Motorway in Ireland 20 Frontier Economics, Atkins, ITS | March 2011 Table 16. Lengths of the Existing Network (Do – Nothing) and New Network (DoSomething) Do – Nothing Do- Something 10.39 km Single Carriageway The Do – Nothing scenario + 4.61km Dual Carriageway 16.38km Motorway 0.82km Motorway Source: Ex post evaluation reports Based on these values, we have calculated that the construction of these two sections of the M1 has led to an increase in maintenance costs equal to €0.36m in NPV terms. We have included this cost in the Year Five ex post evaluation. 6.2.4 Direct benefits In this section we present the direct benefits of the project, namely time savings and vehicle operating costs (VOC) savings. For each, we present both the results of the Year One ex post evaluation and the updated values of the Year Five ex post evaluation. Time savings Journey time savings are the largest source of benefits from this project. The construction of these sections has brought much need relief to a highly congested part of the road network. Year One ex post appraisal Journey times were calculated using the COBA model, taking into account the types of roads, speeds, geometry and traffic volumes. In addition, the consultants undertook a number of journey time surveys on the new M1 and on the old N1 road to validate the modelling results. The model used the following inputs to calculate journey time savings: traffic volumes; proportions of business and leisure purpose journeys; vehicle occupancy rates by vehicle purpose and type, and traffic flow group; values of time by purpose (business and leisure); growth factors for the values of time. To calculate journey time savings, the traffic volume data was split into vehicle categories (car, LGV, HGV and PSV) as well as journey purpose (business or Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 21 leisure). In addition, vehicle-kms were converted into passenger-kms using the NRA‟s standard vehicle occupancy rates. This was done because the value of time is provided on a per-passenger basis. The initial values of time used were €17.55 per person per hour for business trips and €7.06 per person per hour for leisure trips. We note that commuting trips are normally treated as leisure trips. These values were then increased on an annual basis using the growth rates shown in Table 17. Table 17. Value of time Growth Factors (per annum) Year Both business and leisure time 2002 - 2010 1.0270 2011 - 2015 1.0237 2016 and thereafter 1.0229 Source: NRA Appraisal Guidelines Year Five ex post appraisal We have updated the COBA modelling using updated traffic data, while keeping the other inputs constant. We have used the data on the average traffic speeds collected at the two traffic counters on the M1 to validate the average speeds along the route. The updated analysis shows that time savings benefits are higher than what was originally estimated in the 2003 ex post evaluation. Table 18 summarises the results. Appendix 6 – M1 Northern Motorway in Ireland 22 Frontier Economics, Atkins, ITS | March 2011 Table 18. Summary of ex post time savings benefits (€m, 2002 prices) Year One ex post Year Five ex post Low High Low High Section 1 891 963 1,050 1,097 Section 2 682 756 747 768 1,574 1,719 1,797 1,865 Total Source: Ex Post Reports for M1 Northern Motorway (for Year One analysis) and own calculations (for Year Five analysis) Vehicle Operating Costs This project has also had a beneficial impact on vehicle operating costs, although to a much lesser extent if compared with time savings. The VOC savings contribute to fulfilling one of the key objectives of this project, which aimed at improving transport efficiency. Year One ex post appraisal The VOC calculation was done separately for non-fuel costs and for fuel-costs using the NRA guidelines. For non-fuel related costs, the formula used to calculate is: C a1 b1 V where: C is the operating cost per vehicle-km V is the average link speed (obtain from the COBA model) a1 and b1 are vehicle-specific parameters. For fuel-related costs instead, the formula is the following: C a bV cV 2 The values of the equation parameters (a1, b1, a, b and c) have been defined by the NRA. They vary by vehicle type but they do not change over time. Table 19 summarises the parameters used in the analysis. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 23 Table 19. a1 and b1 parameters for non fuel costs and a, b and c parameters for fuel costs (2002 prices, resource costs, euros) Non fuel Fuel Parameters Category a1 b1 a b c Car 5.11 26.10 5.15 -0.08623 0.000585 LGV 7.28 64.29 6.99 -0.08623 0.000585 OGV1 14.83 224.60 16.195 -0.26155 0.000907 OGV2 16.56 454.97 32.86 -0.51011 0.003478 PSV 30.71 514.89 26.38 -0.41334 0.002606 Source: NRA appraisal guidelines Year Five ex post appraisal We have updated the VOC savings calculation using outturn traffic volumes. The other parameters have not changed. As in the case of time savings, the updated analysis shows that the VOC savings are higher than what was originally calculated in the Year One ex post evaluation. Table 20 summarises the results. Table 20. Summary of ex post VOC benefits (€m, 2002 prices) Year One ex post Year Five ex post Low High Low High Section 1 59 65 72 76 Section 2 20 23 31 32 Total 79 88 103 98 Source: Ex Post Reports for M1 Northern Motorway (for Year One analysis) and own calculations (for Year Five analysis) 6.2.5 Externalities Safety The project has also led to a reduction in the total number of accidents. As for direct benefits, we first present the analysis that was carried out for the Year One Appendix 6 – M1 Northern Motorway in Ireland 24 Frontier Economics, Atkins, ITS | March 2011 ex post evaluation and then show the updated results from the Year Five ex post analysis. Year One ex post appraisal For this analysis, the total number of accidents was calculated by taking the NRA accident rates, updating them with observed local accident rates. These parameters provide the number of personal injury accidents per million vehicle kms by road type and speed. The NRA guidelines assume an annual reduction factor, to take into account a general downward trend in accident rates and severity. However, the analysis of historical data showed that this trend did not exist in the study area. Therefore, Roughan & O‟Donovan Faber Maunsell decided not to apply this correction. We also note that damage-only accidents were not included in the evaluation. Table 21 shows the historic number of accidents along the old route (N1). Table 21. Observed accident rates (before opening) Section 1998 1999 2000 2001 2002 Section 1 10 6 4 12 7 Section 2 17 9 15 10 17 Total 27 15 19 22 24 Source: Roughan & O’Donovan Faber Maunsell (2004a) Accident costs and cost growth factors were taken from the NRA parameter guidelines. These are summarised in Table 22 and Table 23. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 25 Table 22. Accident costs (€, 2002 prices) Fatality Serious injury Slight injury Damage only 1,694,481 190,400 14,681 n/a 312 194 118 57 Urban 8,103 4,342 2,562 1,833 Rural 13,741 6,263 4,153 2,737 Motorway 17,480 14,915 7546 2631 Urban 19,83 165 60 4 Rural 1,880 462 60 4 Motorway 2,752 434 60 4 Personal cost Insurance / admin Damage to property Police costs Source: NRA appraisal guidelines Table 23. Accident Costs growth factors per annum Years Rate 2002-2010 1.0270 2011 -2015 1.0237 2016 onwards 1.0229 Source: NRA appraisal Guidelines Based on the modelling, the consultants estimated that, depending on the scenario considered, between 228 and 265 accidents in total over 30 years would be avoided on Section 1, while the reduction in accidents on Section 2 would be between 44 and 60 accidents. These values were then applied to the accident costs to calculate the safety benefits delivered by the project. Appendix 6 – M1 Northern Motorway in Ireland 26 Frontier Economics, Atkins, ITS | March 2011 Year Five ex post evaluation We have updated the Year One ex post evaluation by using actual traffic volumes, updated speeds and actual accident rates. Table 24 shows the observed accident data for the period 2005-2008. This shows that across the new network the accident rate is on average lower than the observed accident rates before the new road was opened. This suggests that, despite the growth in vehicle-kms and the addition of a new stretch of road, the accident rate on the network has actually declined. This is consistent with the observation that motorways are typically safer roads than other road types due to a mixture of grade separation and segregated directional carriageways. Table 24. Observed Accident rate per annum (2005 – 2008) Section 2005 2006 2007 2008 Section 1 (N1 equivalent) 3 2 1 6 Section 1 (M1) 2 1 n.a. 3 Section 2 (N1 equivalent) 3 2 1 5 Section 2 (M1) 2 0 1 3 Total 10 5 3 16 Source: Road Safety Authority (http://www.rsa.ie/RSA/Road-Safety/Our-Research/Ireland-Road-Collisions/) The updated COBA modeling shows that, based on the observed accident rates, the total number of accident saved is larger than estimated in the Year One ex post evaluation. According to the updated analysis, the total number of accidents saved over 30 years should be between 322 and 340 on Section 1 and about 56 on Section 2. We applied these values to the cost factors presented above to calculate the total safety benefits. Table 25 summarises the results. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 27 Table 25. Summary of ex post safety benefits (€m, 2002 prices) Year One ex post Year Five ex post Low High Low High Section 1 21 25 31 32 Section 2 17 21 21 23 Total 38 46 52 55 Source: Ex Post Reports for M1 Northern Motorway (for Year One analysis) and own calculations (for Year Five analysis) Other externalities The framework set up for the ex post analysis did not consider any other externality, positive or negative. Environmental impacts were addressed in a separate Environmental Impact Assessment. The mitigation measure that were implemented, and their costs, are described in the next section. The transport model calculated changes in fuel consumption. However, the ex ante appraisal and the Year One ex post evaluation did not include a calculation for changes in CO2 emissions. This calculation has since become a requirement in Irish appraisal practice. For consistency with the previous ex post analysis, we have not estimated this benefit. Nonetheless, the results from the model indicate that the do-something scenarios generate benefits in terms of reduced fuel use. This result indicates that in the do-something scenario, CO2 emission would be less than that in the do-nothing counterfactual. Utilisation This section of the M1 was built as a 2 lane dual carriageway at motorway standard. It was designed to allow it to be converted into a 3 lane motorway at some point in the future. We have used the congestion reference threshold indicator from UK standards3 as a measure of the theoretical capacity of the M1. This formula utilises data on the traffic flow composition and how the traffic flow varies from one hour to another. Based on the M1‟s design standard the 3 DMRB (1997) Traffic Flow Ranges for the Use in the Assessment of New Rural Roads. TA 46/97. http://www.standardsforhighways.co.uk/dmrb/vol5/section1/ta4697.pdf [accessed 25th September 2010] Appendix 6 – M1 Northern Motorway in Ireland 28 Frontier Economics, Atkins, ITS | March 2011 estimate for the Annual Average Daily Traffic (AADT) flow at which the carriageway is likely to be „congested‟ in the peak periods on an average day is 65,000. If the road were to be widened in the future this would increase to an estimate of 97,000 AADT. As can be seen from Table 13 traffic flows on Section 1 (the southern section near to Dublin Airport) exceed this measure, whilst that on Section 2 is lower than this threshold. The road in its existing standard is therefore approaching capacity, even though it is only 7 years into its lifetime. Traffic growth, particularly on the southern section of the route, has been much higher than was originally anticipated. Uncertainty and sensitivity analysis The principle element of uncertainty in this ex post study is that associated with benefits that have yet to be realised. These benefits are intrinsically linked to the travel demands. To this end we have used the Ireland national road traffic growth estimates to give a high and low estimate of future traffic volumes and benefits. Broadly speaking there is about a 0.3% per annum difference in the respective traffic growth rates (see Table 12). As can be seen from the preceding analysis both the high and low NPV estimates are large. The low estimate of the NPV is €3.8 billion, whilst the high estimate is €3.9 billion. These estimates are similarly and arise as a consequence of the large traffic growth prior to 2009 (and this occurred over the whole of Ireland) and the fact that the traffic growth forecasts under the low and high scenarios are similar (see Figure 7). As a consequence of the similarity in low and high growth rates we have undertaken an additional sensitivity test. This is a very conservative test. We have assumed that traffic volumes and benefits will not grow beyond 2009 (the last year for which we have ex post data). This test gives an NPV of €2.7 billion, a BCR of 12.65 and an IRR of 52%. Clearly the M1 is a very good project as, in this most unlikely of pessimistic outcomes, the M1 shows a very good economic return. 6.2.6 Wider socio-economic impacts In this section, we present the ex post impacts of this project over and above those considered in the core CBA. The impacts presented in this section were identified in our discussion with key stakeholders. As part of a key TEN-T route, the key objectives of the project were: to improve access both internally within Ireland and externally north of the border to Northern Ireland; and, to reduce the transport costs for access to and from key airports and ports in Ireland. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 29 This project is relatively small (16 km of new motorway) with respect to the overall level of investment in the transport network in Ireland since the start of Cohesion Fund. This makes it difficult to establish a causal relationship between this project and the wider impacts of the investment on the economy, society and the environment. However, as the ex post evaluation has identified significant travel time and VOC savings, especially during a period of sustained traffic growth, we can assume that the project has contributed to fulfilling these strategic objectives. As noted by one of the stakeholders, the investment in the M1 had already been planned prior to the availability of contributions from the Cohesion Fund. However, the Fund helped bring forward these investments and therefore support Ireland‟s rapid economic growth more effectively. Socio-economic impacts While it is difficult to pinpoint the specific socio-economic contributions of this investment, the stakeholders provided anecdotal evidence of some positive impacts. Dublin Airport has been experiencing an exponential growth in passengers. However, before the construction of the M1, the Dublin Airport expansion was in doubt due to the need to have high quality transport access. At the time, this was an issue due to the congestion levels on the old route. Improving the speed and reliability of the route to the airport was one of the contributing factors to Fingal County Council‟s decision in 2006 to give the go-ahead for the construction of the second terminal. The opening of the M1 and the expansion of the airport have contributed to the rapid growth of the town of Swords. The two sections of the M1 essentially provide a bypass around Swords for vehicles travelling from the North down to Dublin and from the south towards the border. The Irish census data shows that in 2002 the resident population in Swords was 27,175. By 2006 this had increased to 33,998, an increase of over 25% in four years, well above the national average. Swords acts as a base for a large number of the airport staff. The opening of the M1 also had a negative impact. The reduced travel time have led to people moving further out of Dublin. This has had a knock on effect on house prices in the conurbations along the route, leading to local people being priced-out of the housing market. Appendix 6 – M1 Northern Motorway in Ireland 30 Frontier Economics, Atkins, ITS | March 2011 Environmental impacts An extensive Environmental Impact Assessment was carried out for this project in March 1998. This detailed the required mitigation measures that were to be put in place. These are summarised below. On both sections: The motorway was landscaped with large numbers of trees and shrubs in order to help the project blend into the existing landscape whilst preserving views for motorway users. The landscaping, which provides new habitat for the local flora and fauna, has added more hedges and vegetation cover than was lost during the construction phase. Culverts were provided to allow badgers and other small animals to cross the motorway. A full time ecologist was also based on site during construction to help protect the wildlife and vegetation. Barriers in the form of walls and earth mounds were provided at certain locations to reduce the projected maximum noise level. Archaeologists surveyed the route before construction. They uncovered a large Iron Age early Christian site about 200 metres west of Blake‟s Cross. On Section 1: For the bridge crossing the Broadmeadow Estuary, which is a protected area because of its large population of migrationary birds, as well as resident swans and other birds, plants and animals. A number of measures were put in place to protect the Estuary, specifically: two petrol interceptors were installed north and south of the Estuary to block any oil spillage from the motorway; the bridge was designed so to protect the marsh area; asbestos was removed from the site; and, Ponds were installed to protect the watercourses along the project road. The Final Report quantified the cost of these measures, as summarised in Table 26. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 31 Table 26. Estimated cost of the environmental measures (€m, 2002 prices)) Section Cost Section 1 2.8 Section 2 5.9 Total 8.8 Source: Final Reports (Both sections) Other projects Since the opening of the M1 Northern Motorway between Cloghran and Balbriggan Bypass a number of additional sections have been opened along the route. The M1 now provides a complete motorway standard link from Dublin to Northern Ireland. 6.3 Review of ex ante cost-benefit analysis This section presents the results of the ex ante cost-benefit analysis which was prepared to support the funding applications. The original ex ante CBA was produced for the two Sections together. As noted, the project was divided into two sections to aid in the phasing of the funding for the route. To support the Funding Application, Fingal County Council carried out a full ex ante appraisal. The original document states that “the department of Finance has recognised the need for proper programme appraisal and evaluation. In its stated guidelines, it recommends that new projects should only be undertaken where there is a clearly established public need” (Final County Council). Fingal County Council prepared a detailed report, which describes the full CBA analysis. 6.3.1 Quality of ex ante CBA At the time the ex ante CBA was undertaken (1995) the analysis was regarded as „state-of-the-art‟ in Ireland. It was unusual at that time for CBAs to be undertaken during the development of a transport project. The ex ante appraisal was set up as a six link model, four links on the existing network and two links on the new planned M1. Table 27 provides the details. Appendix 6 – M1 Northern Motorway in Ireland 32 Frontier Economics, Atkins, ITS | March 2011 Table 27. Description of ex ante network Road Type Links Section Existing Network Link 1 1 Airport to Swords Link 2 1 Swords to Lissenhall Interchange Link 3 2 Lissenhall interchange to Blakes Cross Link 4 2 Blakes Cross to Five Roads Link 5 1 Airport Interchange to Lissenhall Interchange Link 6 2 Lissenhall Interchange to Rowan’s Road M1 Description Source: Ex ante Report – Fingal County Council In the analysis the „do-something‟ option (the construction of links 5 and 6) was compared with the „do-nothing‟ (the existing network – links 1 to 4). The analysis considered the following costs: land acquisition; planning and design; construction; and supervision. The following benefits were included: time savings; VOC savings; and, reduction in total number of accidents on the network. Table 28 summarises the key assumptions underpinning the ex ante analysis. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 33 Table 28. Summary of the key assumptions used in the ex ante CBA Key Assumptions Summary Discount Rate 5% (as recommended by the Department of Finance (1994). Other discount rates of 10% and 8% were also tested. Appraisal Period 30 years (2000 – 2030) - (but 31 years appears to have been used). Construction phase (1997 – 2000) Opening Date It was assumed that the opening date was going to be 2000 Base year 1994 Currency Irish Pounds (Punts) Source: Ex ante Report – Fingal County Council Our review of the ex ante CBA is that the analysis meets best practice in appraisal for that time (1995). Against current standards however the CBA itself would be viewed as acceptable but the traffic modelling input to it would be regarded as inadequate. By today‟s standards in our view it would be necessary to: 6.3.2 model junction delays; model re-assignment of traffic between the N1 and the M1 (instead of using a fixed diversion approach as was used in the ex ante analysis); and undertake an assessment of induced traffic, even if that assessment determined that induced traffic was unlikely to be an issue. Headline results from the analysis Table 29 provides a summary of the ex ante results for both sections. The analysis shows that the project as a whole was expected to achieve a high value for money. Appendix 6 – M1 Northern Motorway in Ireland 34 Frontier Economics, Atkins, ITS | March 2011 Table 29. Results of ex ante cost benefit analysis (IR£m, 1994 prices) Net Present Value Economic IRR (%) BCR 303 16.08% 5.49 Do-something Source: Fingal County Council – An application of economic appraisal methods to the northern motorway project 6.3.3 Key aspects of ex ante CBA In this section we discuss the key aspects underpinning the ex ante cost-benefit analysis. Costs The project costs included in the ex ante appraisal totalled IR£ 80.6m at 1994 prices (equivalent to €144m at 2002 prices), summarised in Table 30. The figures were calculated on the basis of previous highway contracts undertaken in Fingal County. The ex ante analysis does not consider any other cost, such as changes in annual maintenance costs. Table 30. Summary of estimated ex ante construction costs (IR£m, 1994 prices). Completed in 1995 and then updated to Euro million, 2002 prices IR£m, 1994 €m, 2002 prices % of total construction cost Construction Cost 55 97 68.2% Land and property Costs 18 32 21.8% Planning and design costs 6 11 10.5% Supervision 2 4 2.7% TOTAL 81 144 100% Cost category Source: Fingal County Council – An application of economic appraisal methods to the northern motorway project Note: Rounding leads to slight differences between the reported total and a summation of the constituent elements. These costs were then updated for the submission to the EU for funding. The total cost for the whole route, excluding expenditure during phase one which was completed prior to submission for funding, was estimated to be €170.5m. This was broken down as follows: Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS €102.5m for M1 Cloghran to Lissenhall (Section 1) €68.0 for M1 Lissenhall to Balbriggan ( Section 2) 35 Traffic Volumes As noted above, traffic volumes are one of the key inputs needed to calculate the benefit of the project. Traffic flows were determined for the base year (1994) using traffic count and origin destination survey data completed in 1993 and 1994. It was recognised that traffic was growing at a higher rate for traffic to and from Dublin airport compared to the national trend. The ex ante analysis assumed an annual 3.4% growth in traffic from opening in 2000 to 2020. Based on these projections of potential future traffic levels it was proposed to build a dual 2-lane motorway with hard shoulder, to allow it to be extended in the future. Table 31 shows the predicted AADT on the two Sections for year 2020. The ex post outturn traffic data presented in the previous section shows that if the current trend continues the forecasts used in the ex ante analysis will be easily surpassed. The primary reason for this underestimation is the unanticipated large growth, since 1995, in traffic volumes in Ireland (due to higher than expected economic and population growth). Table 31. Predicted AADT on the M1 in the year 2020 Road Section AADT (Vehicles) Section 1 45,000 Section 2 30,000 Source: Fingal County Council M1 northern Motorway EIA Benefits Table 32 provides a summary of the benefits included in the ex ante appraisal. These were reported in Irish punds (1994 prices) in the original ex ante study and for ease of comparison we have converted them to euros (2002 prices). We discuss each in turn in the remainder of this section. Appendix 6 – M1 Northern Motorway in Ireland 36 Frontier Economics, Atkins, ITS | March 2011 Table 32. Summary of estimated ex ante costs and benefits (IR£m, 1994 prices) discounted by 5% Benefit category Estimated benefits % of PVB Time savings 292 78.6 VOC savings 28 7.5% Accidents reduction 51 13.9% TOTAL 371 100.0% Source: Fingal County Council – An application of economic appraisal methods to the northern motorway project Time savings Time savings are the largest source of benefits included in the ex ante CBA. They accounts for 78.7% of the total benefits present value. This should be expected given that the project was being justified on the grounds of reducing journey times along the route. The methodology used to calculate time savings is similar to the approach used in the ex post analyses, albeit with different traffic volumes and different parameters. Table 33 provides a summary of the value of time used, the vehicle occupancy rates and the proportions of different types of vehicles. The values of time were assumed to grow at 3% per annum in line with expected GDP. Table 33. Values of Time (IR£, 1994 prices), vehicle proportions and occupancy rates Type of Vehicle Cost £ per hour per occupant Occupancy of vehicles Proportion of vehicles Car (Business) £7.17 1.24 0.12 Car (Leisure) £1.79 1.53 0.66 LGV and HGV £7.17 1.28 0.22 Source: Fingal County Council – An application of economic appraisal methods to the northern motorway project Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 37 VOC savings Vehicle operating costs were calculated for fuel consumption and non fuel consumption, as in the ex post calculations. The results indicate that compared to the other benefits these were undervalued in the ex ante appraisal. Safety The number of future accidents was calculated using the national historic figures on Personal Injury Accidents (PIA), which provided accident rates per million vehicle-kms. The COBA model was then used to estimate the number of accidents by type of road and severity according to accident rates for the UK. Table 34 provides a summary. Table 34. Accident and casualty rates Link Type PIA per million vehicle-km Casualties per Accident Fatal Serious Minor Existing Rural 0.23 0.068 0.499 1.409 New Motorway 0.11 0.048 0.367 1.233 Source: Fingal County Council – An application of economic appraisal methods to the northern motorway project The predicted accident rates were then multiplied by unit accident costs (see Table 35). The analysis does not include damage-only accidents and does not include a value for police and administrative costs. Appendix 6 – M1 Northern Motorway in Ireland 38 Frontier Economics, Atkins, ITS | March 2011 Table 35. Accident costs for ex ante analysis (IR£, 1994 prices) Personal costs Unit cost per type of road Fatality 834,718 Serious injury 29,841 Slight injury 2,880 Accident cost Existing rural road New motorway 90,401 65,158 Source: Fingal County Council – An application of economic appraisal methods to the northern motorway project The ex ante analysis estimated that, compared to the counterfactual, over the course of the entire appraisal period the project would have avoided 60 fatal injuries, 437 serious injuries and 1,233 minor injuries. When compared with the actual outturn data these estimates appear exceedingly optimistic. Sensitivity analysis A comprehensive set of sensitivity tests were conducted to explore the range of results achievable. These are summarised in Table 36. Test 1 formed the basis for the central case All the tests, with the exception of Test 4 (zero growth), indicate a positive NPV. Moreover, the analysis identified that even Test 4 would have retuned a positive NPV if a 5% test discount rate had been used, as recommended by the Department of Finance in Ireland. Test 1 that was also used in the Environmental Impact study was believed at the time to be conservative. Overall, the sensitivity analysis confirmed that the project offered good value for money. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 39 Table 36. Summary of sensitivity analyses (IR£m, 1994 prices) Test Title Assumptions NPV (Discount Rate) 10% 8% 5% IRR (%) 1 Basic Test Traffic Growth, 3% income growth, fuel price growth 72.4 131.2 303.2 16.08 2 Basic + fixed fuel price Traffic Growth, 3% income growth, fixed fuel price 71.9 130.6 301.9 16.04 3 Zero Value leisure Traffic Growth, 3% income growth, fuel price growth 36.4 76.8 195.3 13.52 4 Zero Growth Zero traffic and income growth, fixed fuel price -17.95 -9.5 14.1 6.53 5 High Time Savings Basic assumptions with vehicle operating speeds increased by on proposed network 86.9 151.8 340.2 17.15 6 Low Time Savings Basic assumptions with vehicle operating speeds increased by on existing network 46.4 93.2 231.5 14.15 7 High Accidents Basic assumptions with ‘combined’ accident rate on existing network 92.5 159.7 354.5 17.57 8 Low Accident Value Basic Assumptions with accident costs decreased by 25% 67.4 124.1 290.3 15.69 9 Low Income Growth Traffic growth, 2% income growth, fuel price growth 50.8 96.9 230.5 14.80 Source: Fingal County Council (ex ante appraisal report) 6.4 Differences between ex post and ex ante analysis In this section, we compare the results of the ex ante and ex post analysis, highlighting the reasons for any discrepancies. Table 37 provides a comparison between the ex ante and ex post analyses. As can be seen from the results in the table the values are very different between the initial study (completed in 1995) and for the two sets of ex post studies. Whilst Appendix 6 – M1 Northern Motorway in Ireland 40 Frontier Economics, Atkins, ITS | March 2011 the investment costs increased beyond those estimated in 1995 the benefits have more than compensated for this. The net result is that the NPV, the IRR and the BCR are all higher than was anticipated. Table 37. Comparison of ex ante and ex post economic CBA for the full route (2002 prices, Euro millions) Ex ante Ex Post Year 1 Ex post 2009 Low case High case Low case High case Net Present Value 534 3,295 3,633 3,805 3,905 Economic IRR (%) 16 53 53 53 53 Benefitcost ratio 5.49 16.45 15.04 17.19 17.61 Source: Ex ante Report and Ex post As can be seen from Table 38, there were a number of differences between the assumptions underpinning the ex ante and ex post analyses. However, both analyses found that the project provided good value for money, with time savings being the most important benefit component. The ex post analysis therefore validates the expected results from the ex ante appraisal. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 41 Table 38. Summary of the key parameter between the ex ante and ex post CBA Difference Ex ante analysis (1995) Ex post analysis 5% 4% and 5.5% Currency £Irish Euros Price Base 1994 2002 Project open year 2000 2003 Appraisal period 31 years ( due to error) 30 years Spreadsheet COBA4 None 1 year/ 5 years Forecast In some cases observed e.g. average accident value e.g. Accident value by fatal/ serious and slight injuries 6 links 13 key links + junctions Discount rate Model Knowledge after opening Traffic Growth Rates Complexity of calculations Complexity of model used Costs The capital costs used in the original ex ante appraisal were developed in 1995. Converting to 2002 prices and euros gives an estimate of €147m. The outturn cost was €232m. This represents an increase of 58% compared to the estimates that were produced in 1995. There are a number of reasons why there was an overspend compared to the original ex ante and compared to the original costs submitted to the EC. These include: The discovery of a number of archaeological sites leading to the contractors‟ contract being extended. Only 2 of the 24 sites that were found were documented in the original contract. This increased the costs. Delay and disruption. A long list of reasons for delays and disruption were submitted. These include lack of possession of parts of the site outside and within the motorway reservation, flooding caused by blockages upstream and off site. The redesign of culverts (designed to protect the badgers) Appendix 6 – M1 Northern Motorway in Ireland 42 Frontier Economics, Atkins, ITS | March 2011 Re-measurement Clause – The Irish Government has a clause by which the costs can be re-measured once the contract has been awarded to pick up any changes. This meant that the costs that were submitted to the EC were not the final costs (as was expected by the EC), but had the ability to be updated. This lead to a dispute between the EU and Ireland, which was only resolved in June 2010 in Ireland‟s favour. It is not common practice across the EC to re-measure costs after they have been approved. Changes due to the price variation clause. Due to these increases in costs the ex post costs were greater than the ex ante costs submitted. Traffic Volumes As can be seen by the discussion within this case study the traffic volumes both in the ex ante report calculated in 1995 and the original ex post analysis produced in 2004 underestimated the realised growth in traffic volumes. Two key drivers of the traffic growth have been the larger than forecasted increase in GDP and population growth in Ireland over the period. The ex ante report identified that traffic growth was going to be highest for trips to Dublin Airport. Dublin airport has seen an exponential growth in passengers over the period of study far in excess of that forecast. These differences resulted in an underestimation of the ex post traffic growth levels. Travel Time Savings Both the ex ante and the two ex post analyses found that travel time savings formed the largest benefits that would arise from the construction of the M1. The key differences between the studies are the sophistication in the model that was used to determine these benefits, the disaggregation of the vehicles on the network, the values of time used and ultimately the key differences in the traffic volume as described above. The ex ante model comprised of a six link model. The ex post was designed as a junction and link model with a total of 25 links. This more detailed analysis in the ex post studies found that for Section 2 (Lissenhall to Balbriggan) there was little to no impact of the project on junction delays, whilst for Section 1 (Cloghran to Lissenhall) the impact of the project on relieving delays at junctions was significant. This impact was not considered in the ex ante study. These differences resulted in an under prediction of the travel time saving benefits in the ex ante. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 43 Maintenance Costs Maintenance costs of the network were not included in the original ex ante and the 2004 ex post analysis. Whilst small, at €0.36m (present value), this has lead to an underestimate of the true costs of the M1. Accidents In terms of accidents, in the ex post appraisal in 2004 it was estimated that between 272 (low) and 285 (high) would be saved over the 30 year appraisal period. This is compared to the ex ante appraisal which seems optimistic at 60 fatal injuries saved, 437 serious injuries and 1233 minor injuries. Even when the ex ante casualties are converted to accidents they are still far in excess of the ex post figures. Parameters As summarised in the Table 38 there are a number of other key differences listed that have affected the results. Firstly there is a difference in discount rate. The ex ante used a 5% discount rate. The ex post produced in 2004 used a 5% discount rate, which we updated to 5.5%. The ex post produced in 2009 used a 5.5% discount rate. These rates are all different to the one that is currently used by the Irish Government (4%). The higher discount rate has the impact of reducing the NPV compared to the lower discount rate used in the ex ante. Another difference is that the ex ante assumed a starting year of 2000 rather than the actual opening year of 2003. The sophistication of the model that was used to calculate the ex post results has meant that a greater level of data and detail could be generated on the effects of the project. This has had an impact on the values that have been produced (e.g. journey purpose and vehicle category proportions). 6.5 Role of CBA in the decision-making process We discussed the role of ex ante and ex post cost-benefit analysis with the National Roads Authority in Ireland and other stakeholders. Regarding ex ante CBA, in short, the role that it plays in decision-making has altered since 1995. In 1995 it is apparent that CBA played no role in the decision making process of the M1 Northern Motorway, but today ex ante CBA forms an integral part of current transport appraisal methods used in Ireland (and therefore the decision-making). There is still scope for improvement today, as not every decision made by government and its institutions is based on CBA but the situation is very different from 1995. In 1995 when the ex ante CBA was undertaken the preferred route, alignment and design standard and already been selected. This selection was based on a Appendix 6 – M1 Northern Motorway in Ireland 44 Frontier Economics, Atkins, ITS | March 2011 series of engineering studies. The CBA therefore played no role in the definition of the project. What the CBA did do was confirm the view held by decisionmakers that the project was good value for money. At the time of the ex ante CBA Ireland had already implemented a framework for road transport appraisal, and whilst the project design process had already occurred, at this point in time, the ex ante CBA followed these guidelines. These guidelines have since been updated and the current guidelines for national road subprojects are described in full on the National Roads Authority‟s website4. These guidelines are in full compliance with the Department of Finance (DoF) guidance on the appraisal and management of capital expenditure proposals in the public sector5. The DoF guidance also provides details on how Ireland complies with the regulations associated with the Cohesion Funding. For example, the document states that „programmes co-financed by Structural Funds must be subject to ex ante, interim, including mid-term and ex post evaluation designed to appraise their impact on EU Structural Fund Objectives. Implementation of these requirements is a matter for the programme managing authorities in conjunction with the implementing bodies and subject to consideration by each programme monitoring committee.‟ P13 DoF(2005) The guidance requires a CBA to be undertaken at the following stages: route selection (phase 3) preliminary design (Phase 4) final account/ close out (Phase 7) The comprehensiveness of the CBA increases as the stages progress. The Irish NRA has developed its own version of the COBA model, based on the UK version. The model is used to determine the results of a CBA for roads projects. In terms of ex post appraisal, the NRA guidelines require that “ a post project completion report be prepared”. This report is designed to verify that all aspects have been completed, to confirm the budget information and to identify any issues that might have arisen in the planning and implementation of the project (especially those issues that may have repercussions for future projects). The Department of Finance guidelines require, in addition to this report, a Post Project Review (PPR) for all projects costing more than €30m. The PPR must consider whether: “the basis of a project were proven correct; 4 For the NRA website see http://www.nra.ie/Publications/ProjectAppraisal/ 5 http://www.finance.gov.ie/documents/publications/other/capappguide05.pdf Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 45 the expected benefits and outcomes materialised; the planned outcomes were the appropriate responses to actual public needs; the appraisal and management procedures adopted were satisfactory and, conclusions can be drawn applicable to other projects, to the ongoing use of the asset , or to associated policies.‟ The NRA also told us that the timing of the ex post appraisal was critical to the success and usefulness of the process. However it was noted that it takes longer than one year for the safety benefits to be realized. It was suggested that a 5 to 10 year interval would be better to ensure that all the project impacts are taken into account. This notwithstanding, the NRA guidelines state that „a PPR should be undertaken once sufficient time has elapsed to allow the project to be properly evaluated with sufficient evidence of the flow of benefits and costs from it. It is envisaged that, except in special circumstances, the PPR should be commenced one year after project opening. This timing ensures that at least a full year‟s experience of operation of the road and of the traffic volumes arising is available to inform the analysis. At the same time, it also enhances the likelihood that personnel engaged in the project planning and implementation are still available to help address data and information gaps” The NRA also provided comments on the EC appraisal guide (2008). It was felt that the guidelines were worded „cautiously‟ in the sense that a strong steer isnot always been given. Moreover, it was noted that requiring Member States‟ institutions to undertake CBA analysis without ensuring an understanding of transport modelling was potentially problematic. Whilst the parameters quoted in the guidelines are appropriate, the guide does not bridge the potential knowledge gap in terms of modelling. One stakeholder drew our attention to the level of auditing associated with ISPA/Cohesion Fund. It was felt that there was sometimes a conflict between national audits being different to the DG REGIO audits. One example raised was the issue of the re-measurement of contracts, which led Ireland to believe that they were due more money than the European Court of Auditors did. The re-measurement process allows construction costs in Ireland to be updated to reflect true costs after the contract has been awarded (after the money had been granted by the EC at certain rates). The EC disputed this arrangement. This was resolved in Ireland‟s favour for the two subprojects considered by this study only in June 2010. Appendix 6 – M1 Northern Motorway in Ireland March 2011 | Frontier Economics, Atkins, ITS 47 Detailed results Figure 8. M1 Northern Motorway – Ireland. Economic analysis (€m, 2002 prices) – Low case 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Time Benefits 0.0 0.0 0.0 0.0 0.0 96.1 129.2 153.3 177.1 204.1 210.3 216.7 Vehicle Operating Costs 0.0 0.0 0.0 0.0 0.0 3.5 4.0 4.5 5.2 5.9 5.9 5.9 0.0 0.0 0.0 0.0 0.0 1.7 1.9 2.1 2.4 2.7 2.7 2.8 --- --- --- --- --- --- --- --- --- --- --- 0.0 0.0 0.0 0.0 0.0 101.3 135.1 159.9 184.7 212.6 218.9 225.4 Investment Costs 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL COSTS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 -3.8 -3.8 -14.6 -59.1 -75.4 29.1 131.4 159.9 184.6 212.6 218.9 225.4 2010 2011 2012 2013 229.7 241.9 254.8 264.7 274.8 285.1 295.9 307.0 318.2 329.9 342.8 356.1 6.2 6.4 6.7 6.8 6.9 7.1 7.2 7.4 7.5 7.6 7.8 7.9 3.0 3.1 3.3 3.4 3.6 3.7 3.9 4.0 4.2 4.3 4.5 4.7 --- --- --- --- --- --- --- --- --- --- --- --- 238.9 251.5 264.8 275.0 285.3 295.9 307.0 318.4 329.9 341.8 355.1 368.7 Investment Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 238.8 251.4 264.8 275.0 285.3 295.9 307.0 318.4 329.8 341.8 355.0 368.7 BENEFITS (Undiscounted) Consumers Surplus Externalities Accident Reduction Environment TOTAL BENEFITS COSTS (Undiscounted) NET BENEFITS (Undiscounted) 2014 2015 2016 2017 2018 2019 2020 2021 BENEFITS (Undiscounted) Consumers Surplus Time Benefits Vehicle Operating Costs Externalities Accident Reduction Environment TOTAL BENEFITS COSTS (Undiscounted) NET BENEFITS (Undiscounted) 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Total BENEFITS (Undiscounted) Consumers Surplus Time Benefits Vehicle Operating Costs 369.9 383.2 396.7 410.1 423.1 438.3 453.6 469.4 486.1 503.3 521.1 9542.3 8.1 8.2 8.4 8.5 8.7 8.8 8.9 9.1 9.2 9.3 9.5 217.1 4.9 5.0 5.2 5.4 5.6 5.8 6.0 6.2 6.4 6.7 6.9 126.3 --- --- --- --- --- --- --- --- --- --- --- --- Externalities Accident Reduction Environment TOTAL BENEFITS 382.9 396.4 410.2 424.1 437.3 453.0 468.6 484.7 501.7 519.3 537.5 9885.7 COSTS (Undiscounted) Investment Costs Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 232.4 0.8 TOTAL COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 233.1 382.8 396.4 410.2 424.0 437.3 452.9 468.5 484.7 501.7 519.3 537.4 9652.6 NET BENEFITS (Undiscounted) Discount rate ENPV ERR B/C Ratio 5.5% 3804.53 52.80% 17.19 Source: Own calculations Detailed results 48 Frontier Economics, Atkins, ITS | March 2011 Figure 9. M1 Northern Motorway – Ireland. Financial return on investment (€m, 2002 prices) – Low case 1998 1999 2000 2001 TOTAL REVENUES 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENT COSTS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OPERATING COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OUTFLOWS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 -3.8 -3.8 -14.6 -59.1 -75.4 -72.1 -3.6 0.0 0.0 0.0 0.0 0.0 2010 2011 2012 2013 TOTAL REVENUES 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENT COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OPERATING COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CASH FLOW 2002 2003 2014 2004 2015 2016 2017 2018 2019 2020 2024 2025 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENT COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 232.4 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 TOTAL OPERATING COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 TOTAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 233.1 CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -233.1 Detailed results 2031 2021 0.0 Source: Own calculations 2030 2009 2023 N/A 2029 2008 0.0 5.0% -234.8 2028 2007 2022 FRR (C) 2027 2006 TOTAL REVENUES Discount rate FNPV (C) 2026 2005 2032 Total March 2011 | Frontier Economics, Atkins, ITS 49 Figure 10. M1 Northern Motorway – Ireland. Financial return on capital (€m, 2002 prices) – Low case 1998 1999 2000 2001 0.0 0.0 0.0 0.0 Revenues Residual values 2002 2003 0.0 2004 0.0 2005 0.0 2006 0.0 2007 0.0 2008 0.0 2009 0.0 0.0 --- --- --- --- --- --- --- --- --- --- --- --- TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Local contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Regional contrintribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 National contribution 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Operating Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL FINANCIAL OUTFLOWS 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 -0.6 -0.6 -5.7 -21.2 -25.8 -24.1 -2.7 0.0 0.0 0.0 0.0 0.0 2010 2011 2012 2013 0.0 0.0 0.0 0.0 NET CASH FLOW Revenues Residual values 0.0 0.0 2014 2015 0.0 2016 0.0 2017 0.0 2018 0.0 2019 0.0 2020 0.0 2021 0.0 0.0 --- --- --- --- --- --- --- --- --- --- --- --- TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Local contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Regional contrintribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 National contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Operating Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL FINANCIAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2022 2023 2024 2025 Revenues Residual values TOTAL FINANCIAL INFLOWS 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 --0.0 0.0 0.0 0.0 0.0 0.0 0.0 Local contribution Regional contrintribution National contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 80.5 Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 80.5 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Operating Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 TOTAL FINANCIAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 81.3 NET CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -81.3 Discount rate FNPV (K) FRR (K) 2026 2027 2028 2029 2030 2031 2032 Total 0.8 5.0% 81.4 N/A Source: Own calculations Detailed results 50 Frontier Economics, Atkins, ITS | March 2011 Figure 11. M1 Northern Motorway – Ireland. Financial sustainability (€m, 2002 prices) – Low case 1998 1999 2000 2001 EU Grant Local contribution Regional contrintribution National contribution 3.2 0.0 0.0 0.6 3.2 0.0 0.0 0.6 8.9 0.0 0.0 5.7 37.9 0.0 0.0 21.2 2002 49.7 0.0 0.0 25.8 48.1 0.0 0.0 24.1 0.9 0.0 0.0 2.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Operating subsidies FINANCIAL RESOURCES Passenger vehicles Goods vehicles TOTAL REVENUES TOTAL INFLOWS 0.0 3.8 0.0 0.0 0.0 3.8 0.0 3.8 0.0 0.0 0.0 3.8 0.0 14.6 0.0 0.0 0.0 14.6 0.0 59.1 0.0 0.0 0.0 59.1 0.0 75.4 0.0 0.0 0.0 75.4 0.0 72.1 0.0 0.0 0.0 72.1 0.0 3.6 0.0 0.0 0.0 3.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENTS COSTS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance TOTAL OPERATING COSTS TOTAL OUTFLOWS 0.0 0.0 3.8 0.0 0.0 3.8 0.0 0.0 14.6 0.0 0.0 59.1 0.0 0.0 75.4 0.0 0.0 72.1 0.0 0.0 3.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW CUMULATED CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -0.1 0.0 -0.1 0.0 -0.1 0.0 -0.1 0.0 -0.2 0.0 -0.2 0.0 -0.2 0.0 -0.2 0.0 -0.3 0.0 -0.3 0.0 -0.3 2022 2005 2023 2006 2024 2007 2025 2008 2026 2009 2027 2010 2028 2011 2029 2012 2030 2013 2031 2014 2016 2017 2018 2019 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Operating subsidies FINANCIAL RESOURCES Passenger vehicles Goods vehicles TOTAL REVENUES TOTAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENTS COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance TOTAL OPERATING COSTS TOTAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW CUMULATED CASH FLOW 0.0 -0.3 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.5 0.0 -0.5 0.0 -0.5 0.0 -0.5 0.0 -0.6 0.0 -0.6 0.0 -0.6 0.0 -0.6 0.0 -0.7 0.0 -0.7 0.0 -0.7 0.0 -0.8 Detailed results 2021 2004 EU Grant Local contribution Regional contrintribution National contribution Source: Own calculations 2020 2003 2032 2015 March 2011 | Frontier Economics, Atkins, ITS 51 Figure 12. M1 Northern Motorway – Ireland. Economic analysis (€m, 2002 prices) – High case 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Time Benefits 0.0 0.0 0.0 0.0 0.0 96.1 129.2 153.3 177.1 204.0 210.3 216.7 Vehicle Operating Costs 0.0 0.0 0.0 0.0 0.0 3.5 4.0 4.5 5.2 5.9 5.9 5.9 0.0 0.0 0.0 0.0 0.0 1.8 2.0 2.2 2.5 2.7 2.8 2.9 --- --- --- --- --- --- --- --- --- --- --- 0.0 0.0 0.0 0.0 0.0 101.3 135.1 160.0 184.7 212.7 219.0 225.5 Investment Costs 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL COSTS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 -3.8 -3.8 -14.6 -59.1 -75.4 29.2 131.5 160.0 184.7 212.7 219.0 225.5 2010 2011 2012 2013 229.7 241.9 254.8 265.9 277.2 288.9 301.1 314.3 327.0 340.1 354.4 368.7 6.2 6.4 6.7 6.9 7.0 7.2 7.4 7.6 7.8 8.0 8.2 8.4 3.1 3.3 3.4 3.6 3.7 3.9 4.1 4.3 4.4 4.6 4.8 5.0 --- --- --- --- --- --- --- --- --- --- --- --- 239.0 251.6 264.9 276.4 288.0 300.1 312.6 326.2 339.2 352.7 367.4 382.2 Investment Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 BENEFITS (Undiscounted) Consumers Surplus Externalities Accident Reduction Environment TOTAL BENEFITS COSTS (Undiscounted) NET BENEFITS (Undiscounted) 2014 2015 2016 2017 2018 2019 2020 2021 BENEFITS (Undiscounted) Consumers Surplus Time Benefits Vehicle Operating Costs Externalities Accident Reduction Environment TOTAL BENEFITS COSTS (Undiscounted) TOTAL COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 238.9 251.5 264.9 276.3 288.0 300.0 312.6 326.2 339.2 352.7 367.4 382.1 2022 2023 2024 2025 382.2 397.1 413.2 429.8 447.0 461.0 482.2 500.1 518.7 536.7 553.7 9872.4 8.7 8.9 9.1 9.3 9.5 9.8 10.0 10.2 10.4 10.6 10.9 230.0 5.2 5.4 5.7 5.9 6.1 6.4 6.6 6.8 7.1 7.4 7.6 135.2 --- --- --- --- --- --- --- --- --- --- --- --- 396.1 411.4 427.9 444.9 462.6 477.1 498.8 517.2 536.2 554.7 572.2 10237.6 Investment Costs Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 232.4 0.8 TOTAL COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 233.1 396.0 411.4 427.9 444.9 462.6 477.1 498.8 517.1 536.2 554.6 572.1 10004.4 NET BENEFITS (Undiscounted) 2026 2027 2028 2029 2030 2031 2032 Total BENEFITS (Undiscounted) Consumers Surplus Time Benefits Vehicle Operating Costs Externalities Accident Reduction Environment TOTAL BENEFITS COSTS (Undiscounted) NET BENEFITS (Undiscounted) Discount rate ENPV ERR B/C Ratio 5.5% 3905.03 52.83% 17.61 Source: Own calculation Detailed results 52 Frontier Economics, Atkins, ITS | March 2011 Figure 13. M1 Northern Motorway – Ireland. Financial return on investment (€m, 2002 prices) – High case 1998 1999 2000 2001 TOTAL REVENUES 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENT COSTS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OPERATING COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OUTFLOWS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 -3.8 -3.8 -14.6 -59.1 -75.4 -72.1 -3.6 0.0 0.0 0.0 0.0 0.0 2010 2011 2012 2013 TOTAL REVENUES 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENT COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OPERATING COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2022 2023 2024 2025 TOTAL REVENUES 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENT COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 232.4 Maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 TOTAL OPERATING COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 TOTAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 233.1 CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -233.1 CASH FLOW Discount rate FNPV (C) 5.0% -234.8 FRR (C) Source: Own calculations Detailed results N/A 2002 2014 2026 2003 2015 2027 2004 2016 2028 2005 2017 2029 2006 2018 2030 2007 2019 2031 2008 2020 2032 2009 2021 Total March 2011 | Frontier Economics, Atkins, ITS 53 Figure 14. M1 Northern Motorway – Ireland. Financial return on capital (€m, 2002 prices) – High case 1998 1999 2000 2001 Revenues Residual values 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Local contribution Regional contrintribution National contribution 0.0 0.0 0.6 0.0 0.0 0.6 0.0 0.0 5.7 0.0 0.0 21.2 0.0 0.0 25.8 0.0 0.0 24.1 0.0 0.0 2.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 Maintenance Total Operating Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL FINANCIAL OUTFLOWS 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 -0.6 -0.6 -5.7 -21.2 -25.8 -24.1 -2.7 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW 2002 2006 2018 2012 2013 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Local contribution Regional contrintribution National contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance Total Operating Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL FINANCIAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2022 2023 2024 2025 Revenues Residual values 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 --- 0.0 0.0 0.0 0.0 TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Local contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Regional contrintribution National contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 80.5 Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 80.5 Maintenance Total Operating Costs TOTAL FINANCIAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 0.8 81.3 NET CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -81.3 2030 2031 2020 2009 0.0 --- 2029 2019 2008 2011 2028 2017 2007 0.0 --- 2027 2016 2005 2010 2026 2015 2004 Revenues Residual values Discount rate FNPV (K) FRR (K) 2014 2003 2032 2021 Total 5.0% 81.4 N/A Source: Own calculations Detailed results 54 Frontier Economics, Atkins, ITS | March 2011 Figure 15. M1 Northern Motorway – Ireland. Financial sustainability (€m, 2002 prices) – High case 1998 1999 2000 2001 EU Grant Local contribution Regional contrintribution National contribution 3.2 0.0 0.0 0.6 3.2 0.0 0.0 0.6 8.9 0.0 0.0 5.7 37.9 0.0 0.0 21.2 2002 49.7 0.0 0.0 25.8 48.1 0.0 0.0 24.1 0.9 0.0 0.0 2.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.6 0.6 5.7 21.2 25.8 24.1 2.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Operating subsidies FINANCIAL RESOURCES Passenger vehicles Goods vehicles TOTAL REVENUES TOTAL INFLOWS 0.0 3.8 0.0 0.0 0.0 3.8 0.0 3.8 0.0 0.0 0.0 3.8 0.0 14.6 0.0 0.0 0.0 14.6 0.0 59.1 0.0 0.0 0.0 59.1 0.0 75.4 0.0 0.0 0.0 75.4 0.0 72.1 0.0 0.0 0.0 72.1 0.0 3.6 0.0 0.0 0.0 3.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENTS COSTS 3.8 3.8 14.6 59.1 75.4 72.1 3.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance TOTAL OPERATING COSTS TOTAL OUTFLOWS 0.0 0.0 3.8 0.0 0.0 3.8 0.0 0.0 14.6 0.0 0.0 59.1 0.0 0.0 75.4 0.0 0.0 72.1 0.0 0.0 3.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW CUMULATED CASH FLOW 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -0.1 0.0 -0.1 0.0 -0.1 0.0 -0.1 0.0 -0.2 0.0 -0.2 0.0 -0.2 0.0 -0.2 0.0 -0.3 0.0 -0.3 0.0 -0.3 2022 2005 2023 2006 2024 2007 2025 2008 2026 2009 2027 2010 2028 2011 2029 2012 2030 2013 2031 2014 2016 2017 2018 2019 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Operating subsidies FINANCIAL RESOURCES Passenger vehicles Goods vehicles TOTAL REVENUES TOTAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 TOTAL INVESTMENTS COSTS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Maintenance TOTAL OPERATING COSTS TOTAL OUTFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 NET CASH FLOW CUMULATED CASH FLOW 0.0 -0.3 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.5 0.0 -0.5 0.0 -0.5 0.0 -0.5 0.0 -0.6 0.0 -0.6 0.0 -0.6 0.0 -0.6 0.0 -0.7 0.0 -0.7 0.0 -0.7 0.0 -0.8 Detailed results 2021 2004 EU Grant Local contribution Regional contrintribution National contribution Source: Own calculations 2020 2003 2032 2015 March 2011 | Frontier Economics, Atkins, ITS 55 Detailed results
© Copyright 2026 Paperzz