Who we are and why we are here 1

Who we are and why we are here
1
Levitt Bernstein Architects, GVA Grimleys, WSP
Masterplan of wider strategic are
Kinnear Landscape Architects
Masterplan for public realm & park areas only
What is our brief?
Why are we here?
Camden Council has commissioned a team of consultants to carry out a study of the Abbey Road area,
A public exhibition was held in July 2010 to show initial ideas for the strategic development framework for
from Loudoun Road in the east through to the Abbey Co-op and the Belsize Road Car park in the west.
the Abbey Area, along with 3 options for the redevelopment of the Abbey Co-op Estate.
The study will set out a clear vision for regeneration of the area which will include:
This exhibition presents more detailed proposals for one of the options for the Abbey Co-op Estate (Option
An over-arching Strategic Development Framework for the Abbey Road Area
B(1). It covers more detail on the number of new homes proposed, the heights of the buildings, and the
other commercial and community uses proposed.
A focussed Masterplan for the Abbey Co-op / Belsize Road Car Park area leading to an outline planning
application for any new development; and
The suggested framework for the wider area, including the Abbey Estate and the Alexandra and Ainsworth
Estate, previously shown to you is also presented to show how the new proposals for the Abbey Co-
A detailed development brief for the 1-8 Langtry Walk site on Loudoun Road.
op Estate could fit into the longer term changes in the wider area. A separate master planning study by
Kinnear Landscape Architects for the public realm and park areas within the Alexandra & Ainsworth Estate
will be presented separately.
Redevelopment of the Abbey Co-op / Belsize Road Car Park area will:
Provide new council homes for existing residents to modern standards which meet their current housing
needs
Why your views are important
The lease on the Belsize Road Car Park site is due to end in 2013. The council plan to submit an outline
Provide additional new affordable homes for rent, of a range of sizes and tenures, which should new
include 3 and 4 bedroom homes
planning application in early 2011 to enable redevelopment plans for this site to be prepared in good time.
This means that the Council will start to make decisions which will affect the redevelopment of the Car Park
Building, and potentially other areas of the Abbey Co-op Estate based on the response to this exhibition.
Provide a range of new shops and services which better respond to the needs of the local area than the
existing uses
Generate funds through the provision of new homes for private sale; which will help fund the above, and
Please fill out one of the feedback forms provided by officers if you can, or forward any comments to:
Estate Regeneration Team
London Borough of Camden
Investigate the opportunities to generate funds for improvements to the wider area, including Decent
Homes programme goals
33 - 35 Jamestown Road
London NW1 7DB
www.camden.gov.uk/abbey area
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
Camden
What we showed you last time: Wider Area
Existing
2
Towards Finchley Road
tube station
Towards West
Hampstead rail station
lk
Public open space
with play equipment
Railway line forms a barrier between
residential areas
Local retail area
0m
-6
in
wa
m
-7
KEY
50
d Lan
e
Community facility
West
En
Play space
Swiss Cottage
50
0m
-6
-7m
in w
alk
South Hampstead
K il
bu
rn
Hi
d
oa
R
gh
oad
ze R
si
Bel
e
Av
Entrance from east
to Alexandra and
Ainsworth estates
ad
Ro
oad
yR
ar
und
Bo
be
Ab
500m - 6
Kilburn High Road
-7min walk
Road
Finchley
Loudoun
Road
Public open space
with play equipment,
recreation courts and
seating spaces
50
0m
-6
-7
mi
nw
alk
d
oa
yR
St. John’s Wood
Play areas within
open spaces of the
estate
Local retail area
Proposed
Local retail area
Towards Edgware Road
and Marylebone tube
stations
Towards Finchley Road
tube station
Maintain and enhance the public open space creating a better play area and providing improved
visual and physical connection to Belsize Road
Towards West
Hampstead rail station
Maintain and enhance the public
open space - creating better play
areas and public spaces within the
park area, with improved northsouth pedestrian routes to better
link Alexandra and Ainsworth Estate
Lane
Creating a new hub at the junction of
Belsize Road and Abbey Road - redeveloping the Abbey Co-op site, reproviding existing facilities , improving
the public spaces and realm with the
potential to create a new mixed use
residential node at this junction
West
End
Swiss Cottage
South Hampstead
rn
bu
Kil
gh
Hi
Redevelop 1-8 Langtry Walk site to provide
a better entrance way into the estates - a
gateway building with a mixed use element of
retail and residential to compliment and add
to the retail offer of the hub to the north of
South Hampstead Station
d
a
Ro
oad
ze R
si
Bel
Improve and enhance entrance to the TRA
Hall, creating better north south pedestrian
link along its western edge
oad
yR
ar
und
Finchley
Loudoun
Road
Road
Bo
Kilburn High Road
The Abbey Estate has the long term
potential to be redeveloped into a new
neighbourhood along Abbey Road.
Currently, the estate feels cut off due to the
convoluted pedestrian pathways through
the area. Improving east - west access and
better linkages through the estate will prove
beneficial for the wider area.
St. John’s Wood
Redevelop the ‘Abbey Hive’ to create a
more sensitively designed building - one
which provides a better frontage to and
connection into the linear public open
space between Ainsworth and Alexandra
estates
At Home in the Abbey Area
Local retail areas should be improved and
well connected to each other - this can be
done through improving the public spaces
and sidewalks along Abbey Road and by
creating better visual and physical linkages
into the residential estates along this route.
Abbey Co-op Estate Regeneration Exhibition
Towards Edgware Road
and Marylebone tube
stations
Camden
What we showed you last time: Abbey Co-op Estate 3
Existing
Open space to the rear of Snowman &
Casterbridge: Valuable resource in area
Emminster Building: Existing retail along ground
floor - shops cut off from main road
Ab
be
yR
ize
Bels
oa
d
ay
ailw
d
Car Park facing Belsize Road - cuts off access to
the open space from the road
Roa
e
Lin
R
Community Centre along Belsize Road: No room
for expansion. Entrance not visible / welcoming
enough
ad
o
eR
Ab
iz
ls
Be
be
y
Ro
ad
Entrance to Snowman and Casterbridge: No
surveillance from above to help security. Very windy
at times due to open areas around the base of the
towers and no canopies to help deflect the wind
The Car Park Building: Mainly car based uses. Are
these appropriate in a mainly residential area?
Proposed
Belsize Road / Abbey Road Junction - Fast traffic,
unfriendly for pedestrians
Option A1
Car Park along Abbey Road / Belsize Road - Poor sense of local
character for such a important road junction marked by local shops and
services
Option B1
Option B2
Redevelop the car park site
Redevelop the car park site
As Option B1, plus;
New secure entry to Casterbridge & Snowman
New development at base of Casterbridge & Snowman
Create new tower landmark working with Casterbridge and
Retain and refurbish existing homes
Redevelop community centre, Hinstock & Emminster sites
Snowman
Total - 115 new homes
New public space and road junction
Create more new homes
Total - 235 new homes
Invest more in public space and community benefits
Total - 330 new homes
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
Camden
Results from the previous exhibition
What you said
Interest in the proposals at the previous exhibition was very high with 250 questionnaires received
4
What was decided
No new tower blocks to be proposed
covering a wide range of issues.
No loss of existing green space
Generally there was a very positive response to the consultation from those most affected by the
proposals
No loss of existing play spaces
Option B(1) was the most popular option in responses from residents currently living on the Abbey Co-op
No new buildings to the sides of Casterbridge and Snowman, with new facilities built between the towers
estate
No loss of existing parking spaces
Significant numbers of residents living in the surrounding area had strong concerns on the effect that
development may have on local schools and services, levels of traffic and parking, safety and antisocial
No loss of affordable homes
behaviour
A new replacement community facility
The results of the consultation were discussed in detail with local Kilburn ward councillors, and based
on the responses received from the consultation, Camden instructed the consultant team to develop
Additional affordable family housing for rent must be included
more detailed proposals based on Option B(1), so that any revised design responds to the consultation
comments shown on the diagram above
Existing residents in Emminster and Hinstock to be offered first choice of a new home
A local lettings policy must be agreed with existing Abbey Co-op residents before any decisions are
made to demolish existing homes
Proposals to provide extra school places and health services to be explored and agreed as part of the
planning process
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
Camden
The revised proposals for the Abbey Co-op
Ab
Connect the new public space
around the junction to the
existing open green space
behind the towers
be
yR
oa
d
5
Create new play areas and
enhance the existing open space
which will be used by existing and
new residents on the estate
Play area
Slow the traffic down through
the junction to make it
suitable to use the outdoor
space around the junction for
seating and make it safer for
pedestrians
oad
eR
z
i
s
l
e
B
Mark all the approach to the
junction with new street trees
on either side of the road
Create private
courtyards behind
the new housing
blocks
Create a vibrant new
character for road junction
to mark its importance as
a local centre surrounding
on all sides by shops and
community facilities to serve
the local area
Create secure
play areas within
the courtyards
Improve / widen the
pavements across the railway
bridge to help improve links
to both the Abbey Estate and
the Alexandra & Ainsworth
Estates to the south
ey
a
Ro
d
Mark all the approach to the
junction with new street trees
on either side of the road
b
Ab
Existing car park
building redeveloped
to provide new homes
and shops
Plant a green
barrier to shelter
the
housing
courtyards from
the
railway
noise
ad
Locate new flats away
from the railway where
possible
o
eR
lsiz
Be
ilw
Ra
ne
li
ay
Concept plan of Abbey Co-op Estate following proposed redevelopment
The proposed buildings are currently being tested and any final proposals will be designed to ensure that
an overshadowing of existing properties will be strictly within recommended limits. The sunlight study
illustrated below shows the effect on 21st April of the current proposals on the surrounding area and the
new outdoor spaces formed around the junction.
Key issues:
9.00
11.00
13.00
15.00
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
The existing 74 existing homes in Hinstock and Emminster
would be demolished
These would be replaced with 265 new homes, of which up to
114 would be for affordable rent
In addition to this some of the new homes would be shared
ownership
All existing bedsits would be replaced with 1 bed flats
Up to 40 of the new homes would be new 3 or 4 bedroom
homes for families
At least 27 of these would be suitable for wheelchair users
All new homes would be built to lifetime homes standards,
and would also have better sound insulation, better thermal
insulated and be more efficiently heated than your existing
homes, and so would need less energy to heat them
All new homes would either have a balcony, a private garden
or a roof terrace. This would match or be larger than typical
existing balconies in Emminster and Hinstock
All new homes would be built to the latest environmental
standards (Code for Sustainable Homes Level 4)
The new buildings would be built to a high standard of
construction, with both affordable and private sale homes built
to the same external quality: this is called tenure blind
A design code would form part of any planning application.
This would contain information on the minimum design
standards for key elements of the design such as: the size
of the new homes; the number of homes sharing common
areas such as lifts and courtyards (e.g.. keeping this low so
that people feel a greater sense of ownership over where they
live); the quality of external materials etc; to ensure that the
overall quality of the scheme is maintained throughout the
development
Camden
The revised proposals for the Abbey Co-op
6
Use the existing towers as a
landmark for a new community
hub building built around the
base of the towers
Abb
ey R
oad
New building at base of towers
(no more than 2-storeys high)
help enclose the space around
the junction to give it a more
defined character. Green roofs
could be added to provide visual
amenity from the towers
iz
ls
Be
ad
o
eR
Existing green space would be
upgraded, including a strong new
edge treatment along Belsize
Road
Create a high quality landmark
building on the corner of the Car
Park Site to mark the entrance to
the road junction and new public
space. This corner will be visible
from a long distance along Abbey
Road from the South
Buildings stepped down in
height where they meet the
existing buildings to reduce
over shadowing
d
e
z
i
ls
a
Ro
Gaps formed in new buildings along
Belsize Road to let light in, views
out and increase sunlight reaching
the private courtyards behind the
new blocks to the north
Be
New buildings on this corner
to be lower than the existing
buildings to let more light
into the public space in the
afternoon
Ab
be
yR
oa
d
Artists impression of aerial view of Abbey Co-op Estate following redevelopment
A high quality landmark building is proposed on the corner of the Car Park site. This would be the tallest of
the proposed new buildings and would be prominent in views looking north along Abbey Road. Studies
12 ST TOWER?
for a 10 storey building and a 12 storey building (both with the same number of flats in) are illustrated
below to show different ways how this might be achieved.
10 storey option
1 storey
Ab
be
Be
lsiz
yR
oa
d
eR
oad
This option is shorter, but is
2 storeys
4 storeys
significantly wider on the side
5 storeys
facing Abbey Road. This would
6 storeys
7 storeys
cast a shorter midday shadow,
10 storeys
but a wider shadow over the
Abbey
11 storeys
12 storeys
junction and the buildings to the
Road
east along Belsize Road in the
oad
R
bey
Ab
afternoon.
20 storeys
Proposed building heights diagram
Key issues:
12 storey option
Ab
Be
lsiz
be
yR
eR
oa
d
oad
This option is taller but much
narrower on the side facing
Abbey Road, giving it a thinner
appearance. This would cast a
longer shadow at midday, but a
Abbey
Road
oad
R
bey
Ab
much narrower shadow over the
junction and the buildings to the
east along Belsize Road in the
afternoon.
The existing community centre, health centre and rows of shop
units would be demolished
A new community centre would be built as part of any
redevelopment to re-provide the existing centre
Any proposals would also show a location for a new health
centre. A decision on whether the new heath centre would
be relocated on the estate or elsewhere in the area will not be
made until later due to recent changes in the health service
New retail and commercial spaces would be built as part of the
development which would replace the existing shop units and
provide additional retail space to serve the extra homes being
built
New outdoor seating / display spaces would also be created to
encourage small café’s, restaurants, florists etc to move to the
area
All new buildings would be designed to the latest police advice
to make access into and around the buildings safer. Extra
shops, busier public spaces, and the wider range of housing
tenures would also help to improve safety in the area
Aerial view looking north west along Abbey Road Aerial view looking south towards the Abbey Estate
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
Camden
Housing
7
Artists impression of view looking east along Belsize Road, with the Car Park site on the right of the image
All new homes built by the railway
would have whole house mechanical
ventilation and extra sound insulation,
and glazed in balconies to help keep the
noise of the train out and avoid the need
to open windows to let fresh air in
Buildings designed so that
approximately 90% of all new
homes will be dual aspect and
so will naturally stay cool in the
summer and warm in the winter
2 bed
3 bed
4 bed
Indicative typical upper floor showing new housing
New 3 and 4 bed homes generally
located at ground level with
private rear gardens within the
courtyards
A green barrier would
also help protect
outdoor spaces from
train noise
1 bed
1 bed
2 bed
3 bed
Illustration of how the new homes could be built by the railway
What the new homes could look like
Key Issues: Emminster and Hinstock residents
Key Issues: Decent Homes
Residents who wish to stay on the estate would be offered
a range of housing options. These shall include the option to
live in a new home built either on the Car Park site or on the
current Emminster and Hinstock site
Residents would also be given the option to move off the
estate if they prefer and would be given additional points in
order to bid for new properties through the Choice-based
lettings programme
The number of bedrooms in your new home would be based
on your housing needs, not the size of your current flat
The size of all new homes would either match or be larger than
the size of your existing home
A local lettings policy would be agreed with existing residents
prior to the start of building any new homes
Leaseholders would get compensation in line with Camden’s
standard terms of compensation for redevelopment of council
land and would be offered the option of buying a new home in
the new development
Outstanding Decent Homes works for Snowman and
Casterbridge would be funded from proceeds from private
sales.
Upgrade works to the common areas in Snowman and
Casterbridge would also be carried out when new building
works are carried out between the towers.
Decent homes works to other properties in the wider Abbey
area could also be funded through the development, but this
would be dependent on the level of new affordable a and
private sale homes that would be built, which the Council would
not decide until 2011 at the earliest.
4 bed
Indicative ground upper floor showing new housing
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
Camden
Retail and Commercial Spaces
8
Artists impression of view looking south along Abbey Road towards new shops and the new public space
UPDATE?
larger shops and/or showrooms
smaller shops possibly including
cafes but not fast food
small shops and/or offices or
start up studio’s
local cafe / small restaurant
Artists impression of view looking west along Belsize Road toward new shops and the new public space
Proposed ground floor showing retail and commercial spaces
Key Issues: Retail and Commercial Spaces
New commercial spaces would be created around the road
junction
These would mostly be small spaces for local shops or offices.
New outdoor seating / display spaces would be created to
encourage small café’s, restaurants, florists etc to move to the
area
The amount of additional commercial space would be limited
to serve just the extra new homes in the development, so that
they would not affect existing shops in the surrounding areas
Existing shopkeepers would be given the opportunity to rent
new units in the area if they wish.
Commercial leaseholders who would prefer to relocate
elsewhere would be compensated.
New delivery bays would be created to avoid delivery lorries
affecting traffic
The new shop unit on the corner of the Car Park Site would be
large enough for a small supermarket or other large store, with
a dedicated service yard to the rear for deliveries
Belisze Road / Abbey Road junction today
Examples around the area of how the shops could look like
At Home in the Abbey Area
Examples of how new shops could use the new public spaces
Abbey Co-op Estate Regeneration Exhibition
Camden
Community Facilities
9
Artists impression of view of the new community buildings and new public spaces around the base of the towers
Tower Concierge: Option 1
Medical Centre could
be located at first floor
to maintain privacy for
visitors
Community Centre
Health Centre
Communal Entrance Foyer
Proposed first floor showing community spaces
Single storey building with a community
centre and a small new cafe
Separate new entrances to existing towers
formed
24hr concierge located to either tower with
remote cameras / access control for other
tower (subject to cost)
New pedestrian entrance to the open space
behind the towers formed to the side of
Casterbridge on Belsize Road. This would
be gated at night.
Tower Concierge: Option 2
2-storey building with a community centre, a
health centre, a small café and a pharmacy
Entrances to both towers, the community
centre and the health centre all accessed
from a communal glazed foyer space
24hr concierge located in foyer space
serving all 3 uses (subject to cost)
New entrance to the open space as option
1, with access to the open space also
possible through the glazed foyer during the
day
Tower Concierge: Option 3
Separate 2-storey buildings
Community centre / café in one building
with a health centre / pharmacy in the other
2 separate entrances formed to the tower
blocks as Option 1, but entrances located
opposite each other so that a concierge on
one side overlooks an entrance on the other
New canopy added over the gap between
the new buildings to form a gateway linking
the square to the open space. This would
be gated at night
Key Issues: Community Facilities
Community Centre could be located
at ground floor with private outdoor
spaces to the rear for a crèche and/
or nursery. Both community buildings
could be accessed via a shared central
glazed foyer which also opens out
onto the green space
Community Centre:
The existing community centre would be replaced by a new
centre built on the estate. This would be designed to provide at
least the same quality of services as the existing buildings, and
potentially could be larger to provide additional services
The preferred location for the new centre would be at the base
of the towers, subject to further consultation with residents
Health Centre:
The existing health centre could be re-provided in the area, but
any decision as to what type of facility this might be, or whether
this would be located on the estate or elsewhere in the area
would not be made until 2011 at the earliest.
School provision
The new homes would house up to 80 additional children . This
equates to an average of 5 additional children per year group
(e.g. 80 ÷ 16 = 5)
A financial contribution would be made to cover the costs of
providing additional school places for this number of children.
The Council is currently in the process of formulating plans to
assess how best this could be spent on schools in the area
Community Centre
Health Centre
Communal Entrance Foyer
Proposed ground floor showing community spaces
At Home in the Abbey Area
Examples of new community buildings and common foyer areas
Abbey Co-op Estate Regeneration Exhibition
Camden
Public Spaces
10
Artists impression of view looking across the new public space towards the new community buildings with the new entrance to the green space visible behind
Ab
be
New public spaces could be created either side
of Abbey Road. New traffic calming would reduce
traffic noise and street trees would provide both
shade and help screen noise from seating areas
reaching existing flats in the towers above. The
activity in these spaces would also help to make
the entrance areas to the towers safer.
yR
oa
d
New outdoor space by
shops would be partially
shaded but designed for
short term activities with
trees and benches, but
could be large enough for
temporary cafe seating
d
e
Proposed section looking north along Abbey Road through the new public space showing new outdoor areas
Existing towers force
wind down towards the
ground making it difficult
to enter towers or use
the street level space
between them
Creating either new
buildings or horizontal
canopies above ground
level deflects the wind
making it easier to enter
the towers and allowing
the areas at ground level
for cafe seating etc.
Examples of how busy roads can be made much safer for
pedestrians by introducing new crossing areas / central strips
At Home in the Abbey Area
New outdoor space
in front of community
buildings would catch the
sun all day, and would be
large enough to allow spill
out seating for a local cafe
/ restaurant
iz
s
l
e
a
Ro
B
Proposed new public spaces created around the road junction
Key Issues: Public Spaces
New traffic calming measures would be added around the
road junction to slow traffic speeds which would increase
traffic safety, and also make it easier and safer for pedestrians
to cross between the new shops and community facilities
These would include introducing pedestrian only strips in the
centre of the roads allowing pedestrians to cross more safely
in 2 stages when traffic is moving slowly
The existing bus stops would be retained but repositioned
to make them easier to use with more room to wait without
obstructing pavements
New buildings around the base of the towers and the new
street trees planted around the road junction would help
cut down wind speed, noise and pollution making the new
pedestrian areas suitable for outdoor seating
Existing trees would be retained wherever possible with new
street trees planted to provide shade and screen noise from
the new public space to residents living in flats above
Diagrams showing how building new buildings around the base
of the towers will help reduce wind speeds at ground level
Abbey Co-op Estate Regeneration Exhibition
Camden
Open Space & Play Facilities
Ab
be
yR
Possible jogging track
running around the
periphery of the open space
oa
11
Play spaces and active
open spaces
d
d
oa
R
ze
Quieter seating
areas for older
people
si
Bel
Private communal courtyards
to individual residential blocks
access only by the residents
who look onto them
– possible play areas and
spaces
– quieter seating areas
– routes for walking and
strolling along pleasant
planter beds
a
ilw
Ra
If the car park was moved this
area could be landscaped as a
prominent new sunny part of the
open space or even a new play
area
y
be
Ro
e
a
Ro
Ab
New main entrance into the open
space. This could be between both
the towers or to the side of Casterbridge. All entrances to the open
space would be gated at night for
security
d
iz
els
ne
i
l
y
New gated pedestrian
entrance into the open
space off Belsize Road
ad
B
St
ab airs
ov to
e
fla
r
uffe
ed b
lant
ly p
hick
Quiet seating
area
en t
Raised planter bed to
define courtyard space
and separate space and
separate vehicular access route to housing on
western edge
Timber deck
u
hic
Ve
R
s
nit
u
ail
et
lar
s
es
c
ac
Active open area
Public space along Abbey
Road
Raised planter bed to define courtyard space
Gre
Bac
k
Terr garde
ace
ns t
o
Prio
ry
Play area
ts
Proposed landscape plan of Abbey Co-op Estate following redevelopment
D
e
iz
els
A
RO
B
Shops screened off
from courtyard. No
access to shops
New Infant Play Area
New Formal Play Area
Upgraded of Existing Informal
Play Areas
Proposed plan showing new play spaces on the Abbey Co-op estate
Possible layout of a new private courtyard
Key Issues: Open Space and Play Facilities
There would be an overall increase in open space in the area
following redevelopment through the provision of new private
courtyards behind the new buildings
These would also have new play areas in them to provide for
younger children in the new buildings
The existing public open space area behind Snowman and
Casterbridge would be retained and improved with new play
facilities and the existing car parking area opened up as part
of the green space
The open space would primarily be designed for use by both
the existing and the new residents on the estate. It would
remain a public area as the existing space is, and so would
also be open to the general public
This could include the relocation of the existing car parking
area behind Snowman house which would improve the open
space, but would mean the car park would be accessed off a
busy road.
Any parking area would still provide the same number of
parking spaces as existing
Examples of high quality private residential courtyards like those
proposed behind the new buildings for use just by residents
At Home in the Abbey Area
Examples of different types of play spaces. Some of these would be in
the private courtyards, with others in open space behind the towers
Abbey Co-op Estate Regeneration Exhibition
Camden
Parking & Deliveries
A planting buffer could be added
along the boundary for security to
adjacent houses, with trees helping to visually screen cars from the
flats above
Ab
be
yR
12
Alternative location for parking area to the
north side of Snowman House. This would
mean access to the car park would be off
a busier road, but would make the open
space more visible from the road, and allow
residents to make better use of the sunnier
part of the open space where the existing
car park is located.
oa
d
P
Bus stops all located
outside of new public
space to keep this
uncluttered
d
P
oa
R
ze
si
Bel
Out of hours servicing lane
for retail units e.g.. early AM
or late PM deliveries only
ne
li
ay
ilw
Ra
Existing car park location could be
retained, but car park currently blocks
views and access to the open space
from Belsize Road and occupies an
area which could be made into a
sunny new open space.
Communal green
courtyards at ground level
only for amenity space.
No parking provision
within courtyards
Bus
P
Bus Stop
On-Street Pay & Display
Parking
On Street Resident Permit
Parking
Bike Parking Stand
y
be
P
Estate residents only car park
P
Estate residents only car park
(underground)
ad
Ro
New covered service yard
formed at ground level to
serve retail units on corner
of block, with landscaped
courtyard for flats built above
Ab
New underground parking
Ro
area created by re-using
e
z
i
ls
basement of existing
e
B
buildings. This would be the
only new car parking for all the
new buildings
Proposed parking plan for the Abbey Co-op Estate following redevelopment
ad
Proposed section through new buildings on Car Park Site showing covered service yard and entrance to underground resident car park
Key Issues: Parking & Deliveries
All existing on-street parking spaces, drop off-bays, and
parking spaces to Snowman and Casterbridge and the
Community Centre would retained and/or relocated
Up to 70 parking spaces for the new homes would be
provided in an new underground car park on the car park site,
including new wheelchair parking spaces
These 70 new spaces would replace approximately 250 car
parking spaces currently in the car park building, meaning
there would be much less traffic using the estate overall if it
was redeveloped
New residents would not be eligible for street parking permits
in the area
All new homes would also be provided with a secure place to
park a bicycle
Existing car park cuts off access to open space from road and
could create a new sunny part of the open space if relocated.
New underground car park could be naturally lit from above / or
from the side making it feel lighter and safer
At Home in the Abbey Area
View of possible new location
for car park behind towers
Abbey Co-op Estate Regeneration Exhibition
Examples of upgraded street
parking combined with tree planting
Camden
Local Lettings Policies
Council tenants who need to move because of the
regeneration:
Will get priority for any new homes that are built. It is anticipated
that the majority of tenants will only have to move once. Where a
temporary move is necessary tenants will be able to return to a new
property on the Abbey Co-op Estate.
If they wish to move away from Abbey Co-op, tenants will get extra
priority when bidding for homes on the Choice Based Lettings
Scheme.
Will be entitled for moves both within and outside the Abbey Area
to be offered a home of the size needed as measured by Camden’s
bedroom standard. This means that those currently living in bedsits,
will be entitled to move into a one-bed home.
Homeloss payment- tenants who need to move because of the
regeneration programme will be entitled to receive a statutory Home
Loss Payment £4700.
We hope to avoid the need for any temporary moves but in cases
where tenants are required to move temporarily prior to taking up a
new permanent home, disturbance payments will be paid for each
move and covers:
– The cost of removals.
– The cost of disconnection/re-connection of washing machines,
telephone lines, satellite or terrestrial television aerials (but only in
cases where authority to erect the aerial / dish was obtained from
the Council.
– Any costs for redirection of mail and the cost of informing service
providers of change of address (doctors, dentists, banks etc)
– Legal costs.
– Transport costs relating to schools where a tenant moves
temporarily.
13
Leaseholders who need to move because of
regeneration:
Will receive priority to purchase new homes that are built, either on
an outright or shared ownership basis.
Will be offered full market value for the purchase of their property.
Compensation for home-loss at 10% of the value of the property to
a maximum of £75,000.
Disturbance payments to cover removal costs, legal and surveyors
fees, and stamp duty on a new property where this is purchased
within one year of the repurchase.
Leaseholders in financial hardship may be able to benefit from a
discretionary scheme allowing leaseholders to convert to a secure
Council tenancy – in these circumstances the Council would only
offer around 37% of the market value of the leaseholder’s current
property.
Where the leaseholder has not been in occupation for minimum of one
year prior to the resolution to purchase on the following terms:
Full market value for the property.
Compensation for basic loss at 7.5% of the value of the property to
a maximum of £75,000.
Legal and surveyors fees.
We will work with individual leaseholders to give them opportunities to
buy properties, either outright or on a shared ownership basis, in any
new development.
Tenants not directly affected, but in housing need:
Future lettings:
Many residents living at Abbey Co-op will not be directly affected by
the building of new homes (i.e. they won’t need to move home). However we know that there are residents who need to move, or would
like to move because their current home is either too small or too large
for their needs.
In these circumstances residents may be able to apply to receive
extra points that will enable them to bid for new properties that are
built in the area. In this way residents living on the estate will be able
to share directly in the benefit of new homes being built.
The Council has a sustainable estates policy, which means that
households with drug, alcohol or mental health problems are not considered for bed-sit and 1 bedroom properties on some estates. If this
was considered relevant, this policy could potentially apply to any new
homes for rent to be managed by Abbey Co-op.
A new set of local lettings criteria could also be implemented that
would cover the existing homes and the new homes.
Practical help:
Please note:
All tenants and leaseholders who are directly affected will be visited
at home at least 12 months before moving to discuss housing
needs and preferences, and to discuss removal and compensation
arrangements.
The Council will arrange help with packing for vulnerable, elderly and
disabled tenants, where needed, and will provide help during the
removal process and settling-in period for those vulnerable tenants
who need it.
Care packages for tenants currently receiving health and/or Social
Services support will be co-ordinated by the Council so that they
continue after residents move into their new home.
The Council will assist those not directly affected to apply and bid
for new homes being built on the estate.
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
This is the same wording that has been previously circulated to Abbey
Co-op residents.
The above policy is still under discussion with the Council’s Allocations team- initial discussions about some element of ring-fencing of
new stock for those in housing need current living on the estate could
be possible – how would this work in practice is still under consideration, and this will also require further discussion with the Abbey Co-op
Management Committee.
Camden
Questions raised during the consultation
14
Why does this need to happen?
We want to provide a sustainable community for all. Currently there is a shortage of housing and funding for decent homes work. The development of the car park, and
potentially other areas, could produce funding for decent homes improvements. It will also provide a high quality building which contributes to the community and creates a
vibrant neighbourhood, which suits the needs of local people.
How will the new buildings be paid for?
The scheme does not rely on separate government funding to build the new affordable housing or improvements to the public spaces, which would be paid for through the
sale of some of the new homes. The current proposals have also been tested by independent consultants and Council officers to check its viability.
Why do the new buildings need to be so high?
The proposed heights of the buildings are largely set by the amount of new affordable housing the Council wish to provide and the need to generate funds for Decent
Homes improvements to the homes retained on the estate. The buildings could only be made lower if either these are reduced, or the quality of the new homes is reduced
(by creating more single aspect homes (e.g.. without natural ventilation))
Will the new buildings overshadow my windows or garden?
The new buildings are likely to have some overshadowing affect on surrounding buildings, but any planning application would have to clearly demonstrate that this affect is
within national guideline limits. The height of the proposed buildings currently reduces near the existing buildings on Belsize Road and Priory Terrace to reduce any impact on
these properties.
What will happen to the existing link bridges?
These would be removed under the current proposals, including the bridge over the railway.
Could the new courtyards on the Car Park Site face the road instead of the railway?
This option would mean that more of the new homes would be nearer the railway and any communal outdoor space, including play areas for younger children would have to
face the road and so would have much less privacy.
How many of the new homes will be for private sale?
In the current proposals 151 of the 265 proposed new homes would be for private sale
Will there be a lift to my new home?
Massing options explored during development of Option B(1) since
the last public exhibition
The current proposals assume a lift will be provided to all new homes above ground level.
Will my new home have more bedrooms?
All existing residents affected by demolition will be offered a new home within the new development which would be allocated on your existing housing needs, not the size of
your existing home.
Who will manage the new homes?
This has not been decided yet, but the Council is currently in discussion with the Abbey Co-op to see if they would like to manage the new affordable homes, and potentially
other areas of the new development.
What are the options for the location of the Community Centre?
The location of the new community centre has not yet been agreed. The location shown is the existing centre’s preferred location but other locations could be looked at.
What facilities will the community centre provide?
As a minimum the new community centre building would provide a similar range of facilities as the existing centre, but this could be expanded if there was interest in
providing a wider range of services (subject to funding being available), such as somewhere to hire for children’s birthday parties etc.
What happens to the proposed new community building if the health centre moves off the
estate?
Any planning application will include options for the community building both with, and without a health centre on the site. This will generally mean a smaller and/or lower
building near the towers without a health centre.
I like the way the existing towers look. Can any new buildings near Snowman and
Casterbridge be separate from the towers?
If the new buildings were separated from the towers this would not stop the existing problem of high wind speeds at the base of the towers making the area around them
Public Space studies during development of Option B(1) since
the last public exhibition
difficult to use, and is likely to make this problem worse by creating smaller gaps between the buildings. This would restrict the way any new buildings could use the outdoor
space around them, such as providing outdoor crèche areas for a community building or outdoor seating for a new cafe.
Will the shops and community buildings create noise problems for the flats living above
them?
The new shops and community buildings will be designed to minimize noise affecting those living nearby. This could be achieved by recessing the shop fronts and/or adding
horizontal canopies to the shop fronts so that the new homes above overhang the shops to deflect any noise; and by planting a canopy of street trees to filter any noise from
any outdoor seating areas created in front of the new buildings
Will the new homes increase the existing parking problems in the area?
Competition for existing on street parking spaces would not be affected by the redevelopment as new residents would not be able to apply for resident parking permits for
on-street parking bay. Parking for new residents would be provided in an underground level on the Car Park site instead.
Will the new traffic calming increase congestion?
The new traffic calming measures would only slow traffic around the junction, and so would have a minimal impact on overall congestion, but would make it safer and easier
for pedestrians to cross between the new shops and community facilities
What impact will the development have on schools in the area?
The current proposals would mean approximately 5 extra children per year group attending schools in the local area. A financial contribution would be made as part of any
development which would be used to fund improvements to local schools, but no decision has been made yet as to how or where this would be spent
How can you be sure the quality of the development will be high enough?
If a planning application is made for the scheme, it will include a ‘Design Code’ which will define the quality of key areas of the scheme. What this will cover has not been
decided yet, but it could include the quality of materials used; minimum flat size; minimum standards of sound proofing, daylighting, and natural ventilation (e.g.. dual
aspect) for new homes; maximum number of homes sharing a lift on each floor etc.
Will the redevelopment provide benefits for the other estates in the area?
Benefits to the other estates in the area will largely be determined by the size of the new buildings and the number of new affordable homes built. Final decisions on these
have not been made by the Council, but benefits provided by the current proposals are largely to the Abbey Co-op Estate
When would construction start and how long would this last?
No decision on when to start construction has been made. The existing car park building would form the first phase of any redevelopment. Construction would not start on
this site until mid 2012 at the earliest, with new homes potentially becoming available in 2014.
At Home in the Abbey Area
Abbey Co-op Estate Regeneration Exhibition
Consultation model / plans using during development of Option B(1)
Camden
What is happening next?
Project team develop
design of Council’s
preferred option
15
Series of consultation events
focusing mostly on the residents/
stakeholders most affected
Public exhibition
preferred option
Council review
exhibition feedback
Project team
finalise designs based
on council comments
Council submits
outline planning
application
Planning process designs open for
public comment
Planning committee
make decision on
planning application
What is happening next
The information on these boards will form part of a public
exhibition for the project which will be on display in the Abbey
Hive between 22-27th November
Following this exhibition, Camden will review all comments
made on the current proposals to date, and these comments
will be discussed with your local Kilburn Ward councillors
who will make a recommendation as to what to do next to
Camden Council’s Cabinet Committee in December 2010
The Council’s Cabinet Committee will then make a decision
on whether to proceed or not with the scheme
If the Cabinet decide to proceed further with the scheme,
the proposals are then likely to be developed further and an
outline planning application submitted for the scheme
The planning application would be made public, so that
anyone can have their say on the application
The earliest an application could be made would be in late
January 2010, and it would take approximately 4 months for
the council to make a decision on the planning application
At Home in the Abbey Area
Outline Planning Applications
An Outline Planning Application covers limited details for a
new development, to allow further details to be decided at a
later date
If an Outline Planning Application is submitted for the scheme,
it is likely that it would only cover the overall size and shape of
the new buildings; the number of new homes and amount of
new commercial and community space; and the location of
parking and delivery areas for the new buildings. It is unlikely
to cover what they would be made of, what they would look
like, or the landscape design of the spaces around them
Camden would also submit a ‘Design Code’ as part of any
outline application. This would contain information on other
issues which are felt to be important for the success of the
scheme but are not covered in the application drawings, such
as design quality; design features for new homes (such as
flexible layouts); landscape design features etc.
Camden would like to hear your views on what should be
included in the ‘Design Code’ as part of this consultation.
Please include any comments you may have on the feedback
forms provided
Abbey Co-op Estate Regeneration Exhibition
How the Council makes its decision
Any decision to proceed with a planning application will be
made by the Council’s Cabinet Committee
The Cabinet is made up of the Leader of the Council and nine
other councillors (called Cabinet Members) chosen by the Full
Council. The Cabinet meets eight times a year.
All Cabinet decisions must be taken in public apart from
exceptions for things like personnel matters, commercially
sensitive information or confidential legal advice. Even where
a decision is taken by an individual Cabinet councillor this is
done at a public meeting with publicly available agendas and
reports.
Officers are not able to put decisions into practice until the
seven-day ‘call-in’ period has elapsed (except for decisions
taken under emergency procedures).
The Cabinet is allowed by law to meet in private, but cannot
take decisions in private or discuss in private session a matter
on which a decision is to be taken in the next 28 days.
Camden