TECHNO TECHNO From late May to mid-July, a large-scale scraping operation was conducted on a section of our Transitgas pipeline in Switzerland. This operation in a mountainous area required the use of an ultrasound pig: a major technical challenge! air pressure adjustment vent ultrasound pig expanding stoppers Ruswil high-pressure pumps Wallbach THE RHINE Ultrasound scraping OGE ON THE MOVE In order to ensure that the infrastructure is in good condition and does not exhibit any traces of wear or corrosion, Transitgas decided to inspect the interior of the pipeline this year over a distance of 70 kilometres between Wallbach, at the Swiss/German border, and the Ruswil compressor station. This scraping was carried out using an ultrasound pig propelled through the pipeline by means of water pressure. This operation is practically unheard of in Europe, which is why Transitgas enlisted Open Grid Europe, the operator of the German grid. Up until now, only the OGE’s teams had any prior experience with this technology, in a section of the TENP pipeline in Germany. While the inspected section of the TENP was longer, the differences in altitude, for their part, were less: Transitgas is nestled in a particularly mountainous and difficult-to-access area of Switzerland. The operation involved 10 OGE collaborators in total as well as some forty 10 other persons from different contractor companies. PIG AND EXPANDING STOPPERS In order for the ultrasound pig to properly record all data to assess the condition of the pipe, its travel speed must remain between 0.7 and 1.8 km/h. Further, in order to compensate for the water pressure pushing it along inside the pipeline, air was used to exert a back pressure. This water pressure and air back pressure were adjusted to keep the speed within the proper range at all times. Throughout the operation, the ultrasound pig was preceded by three expanding stoppers whose job was to block free space to prevent any contact between the air and water. An additional challenge had to be tackled: considerable differences in altitude, at times as much as 500 metres. Therefore, it was necessary to prevent the pig from getting stuck underway at all costs. This is the reason why a long preparation phase was necessary before the operation: during the preparations, the operation teams analysed the whole route, down to the smallest details, to determine the precise water pressure and air back pressure that needed to be applied at each point in the run in order to keep the pig at the proper speed at all times. SUPPLY TO THE CUSTOMERS Because the pipeline was going to be filled with water for the scraping, it had to be taken out of service for a period of 11 weeks. Although the operation was planned for May to July, a period when consumption is at its lowest, a solution had to be found for the customers receiving natural gas via this pipeline. Fortunately, the Transitgas infrastructure is made up of two parallel pipelines at this location; customers were temporarily connected to the twin pipe throughout the operation. THE OPERATION ITSELF The gas present in the relevant section of the pipeline was first evacuated through the downstream network. Then a cleaning pig was introduced into the pipe to eliminate any impurities which might interfere with the proper functioning of the ultrasound pig. Once the cleaning was complete, compressors installed in Wallbach injected air into the pipe section at a pressure of 26 bar: this is the air used to counterbalance the water pressure (see point 2). Finally, water was drawn from the Rhine with a pumping system and transported over a distance of 1.5 km to Wallbach to be injected into the pipe and push the expanding stoppers and ultrasound pig along. In total, 46,000 m3 of water were needed to propel the three stoppers and the pig another 70 km up to the Ruswil compressor station. This operation took almost 85 hours, i.e. 3 and a half days. Once the scraping was complete, the pipeline was cleared of its water: an activated carbon filtration device had been installed at Wallbach to purify the water before dumping it into the Rhine. Then, the entire section had to be dried using foam pigs and hot air to prevent humidity inside the pipeline which could lead to corrosion problems. DATA ANALYSIS AND RESTORATION As soon as the ultrasound pig had been liberated from the pipeline at Ruswil, the data recorded were scanned to make sure the entire section had been properly inspected and that no major anomalies were detected. As this analysis did not indicate anything abnormal, the operation team was able to get down to remove the temporary connections to the parallel pipeline and to reconnect customers to the original pipeline. Written in French by Fluxys and translated into English and German by Transitgas; All rights reserved. 11
© Copyright 2026 Paperzz