construction update march 2016

CONSTRUCTION UPDATE MARCH 2016
QUEENSLAND
SCHOOLS PROJECT
NEW SCHOOL AT
CABOOLTURE
NORTH EAST
VIEW LOOKING SOUTH TOWARDS THE OVAL AREA
WORK AT NEW SCHOOL IN FULL SWING
FAST FACTS
Location:
Builder:
Site size:
Stage 1
Completed:
Stage 2
Complete:
Pumicestone
Road,
Caboolture
Work is now well underway on the new primary
school being delivered in Caboolture North East as
part of the Queensland Schools Project.
After work commenced on site at the beginning of
the New Year, construction has progressed well.
Watpac
Construction
Activities currently underway include:
6.3 hectares
- Digging and pouring of footings,
- Bulk earthworks which are due to be completed
by the end of March,
- Installing underground electrical infrastructure;
and
January 2017
- Installing under slab drainage.
All works are progressing well and are on track for
completion of Stage 1 A in early November 2016.
January 2019
The following activities will be progressing over the
coming months:
- Sewer trunk installation,
- Stormwater installation,
- Pouring building slabs,
- Laying blockwork,
- Steel frame installation; and
- Install roofing.
The management of safety on site continues to be
a priority for the construction team, with no injuries
or incidents reported to date.
Work will continue to be undertaken on site from
Monday to Saturday; always within council
regulated hours.
FOR MORE INFORMATION
PLEASE CONTACT:
Design of the required upgrade to the surrounding
external infrastructure is currently being
undertaken by the local authority and the
Department of Education and Training.
Our design consultants have been liaising with the
designers of the external works to ensure the
integration with the new school site is designed and
constructed appropriately.
Where impacts to the surrounding community are
unavoidable, Watpac will proactively notify
affected residents and seek to alleviate any
relevant concerns, where practical and feasible.
CONSTRUCTION OVERVIEW
- Stage 1A works set for handover in early
November 2016,
- Stage 1B works set for handover in early January
2017 ahead of the academic year
commencement; and
- Stage 2 works to re-commence in 2018 for
commencement of 2019 academic year.
It is expected by November 2016 the school will be
partially open to take enrolments.
ABOUT THE PROJECT
The Queensland Schools Project is being delivered
as a public private partnership between Plenary
Schools and the Queensland Government’s
Department of Education. The Plenary Schools
consortium will design, construct, commission,
partially finance, maintain and provide facilities
management services for the project’s 10 schools
over 30 years.
In January 2016, Plenary Schools successfully
opened new schools at Bellmere, Deebing Heights,
Griffin and Pallara which followed the successful
openings at Burpengary and Pimpama in January
2015.
Plenary Schools Site Office
Pumicestone Road
Caboolture QLD 4510
T: 0401 274 909
E: [email protected]
For more information on the
Queensland Schools Project visit
www.deta.qld.gov.au
VIEW LOOKING WEST TOWARDS THE MAIN SCHOOL CARPARK AREA
STAGE 1 BUILDING PLATFORMS BEING ESTABLISHED FOR SERVICES
RETICULATION