PRELIMINARY ENTERGY NEW ORLEANS, INC. CITY OF NEW ORLEANS DOCKET NO. UD-08-02 2015 IRP Technical Conference #1 IRP Overview including Plans for DSM Potential Study & DSM Avoided Cost Inputs JUNE 27, 2014 Note: All IRP materials presented here are marked “preliminary”. This is because the material is subject to change prior to ENO’s filing of its final IRP report scheduled for October 2015. 1 PRELIMINARY ORGANIZATION OF MATERIALS* I. II. III. IV. Overview of IRP Process Impact From Joining MISO DSM Potential Study DSM Avoided Cost Inputs • IRP Objectives & Framework • Energy Market • Load Forecast • Portfolio Design Analytics • Load Modifying Resources • Demand Side Management Potential Study Process • Benefits of ICF • Next steps • Capacity Market • Avoided Energy • Avoided Capacity *All material presented is informational and subject to change based on additional analysis, new information or stakeholder feedback. 2 PRELIMINARY OVERVIEW OF IRP PROCESS IRP PLANNING OBJECTIVES The process will seek to balance three objectives . . . • Consider the effects of environmental compliance regulation on customer costs. Reliability Cost While considering utilization of natural resources and effects on the environment . . . • Assess risk to reliability and cost associated with environmental concerns. Risk Mitigation • Assess the implications of proposed portfolios (which include both supply-side and demand-side resources) on the use of natural resources and the effect on the environment by measuring key parameters such as: – CO emissions, and These objectives will be measured from a customer perspective. That is, the IRP process seeks to design a portfolio of resources that meets customer power needs at the lowest reasonable cost while considering risk. – Natural gas use 3 PRELIMINARY OVERVIEW OF IRP PROCESS CONCEPTUAL REQUIREMENTS OF AN IRP The IRP considers the range of alternatives available to meet customer needs in order to develop a preferred resource portfolio. Requirements Reliability Reliability Peaks Cost Stewardship Peaks Cost Stewardship Shape Risk Compliance Shape Risk Compliance Planning Objectives Load Environmental Projected Load Assess Current Resource Position Existing DSM Planning Objectives Environmental Identify Future Resource Needs & Alternatives Existing Existing Generation Transmission (including purchased power) New DSM Alternatives *MISO Transmission Expansion Plan New MISO MTEP* Changes/ Generation Deactivations to Existing Units Assess Cost & Risk IRP Two Key outputs: 1) “Preferred Resource Portfolio” that is intended to guide planning and procurement activities. 2) “Action Pan” which creates a link between ENO’s preferred portfolio and the specific implementation actions that need to be performed during the first five years of the planning period. Note – The IRP guides future planning and procurement activities. However specific resource decisions are not made during the planning process. 4 PRELIMINARY OVERVIEW OF PROCESS PREFERRED PORTFOLIO DESIGN ANALYTICS The Goal of the IRP is develop Preferred Portfolio that meets the IRP objective to maintain reliability at the lowest reasonable cost recognizing the need to mitigate future risk events which are beyond the control of ENO or its customers. Gather Inputs; Develop Scenario & Sensitivity Cases Run Capacity Expansion in AURORA1 Footprint Run Sensitivity Analysis Select Preferred Portfolio Detailed MISO South Modeling with DSM Optimization Develop ENO Portfolio Plan For Each Scenario Validate Preferred Portfolio The IRP is dynamic process for long-range planning that provides for flexible approach to resource selection. The Preferred Portfolio resulting from the IRP planning process provides guidance regarding long-term resource additions, but is not intended as static plan or pre-determined schedule for resource additions. Actual portfolio decisions are made at the time of execution. 1AURORAxmp is the name of an electric market simulation model which among other uses forecasts the economic commitment and dispatch of supply side and demand side resources on an hourly basis over many years. AURORA is product of EPIS (www.epis.com). SPO under the guidance of EPIS has customized AUROA to better simulate ENO’s participation in MISO. 5 OVERVIEW OF PROCESS PRELIMINARY IRP OUTPUT METRICS Portfolios will be designed to provide reliable power . . . All portfolios must include sufficient capacity to meet peak load plus contingencies. Metric • Planning Reserve Margin While Considering Risks . . . Portfolio design will consider risks relating to total supply cost and reliability. Risks include exposure to power price volatility and fuel cost uncertainty. Metrics • Variability in Total Supply Cost across scenarios • Change in portfolio rankings Objective function is to minimize customer cost . . . Analysis measures total supply costs, which include variable production cost and fixed supply costs. In other words, all supply costs that ultimately affect customer bills. Metric • Present Value of Total Supply Cost Other Considerations & Metrics Analysis will produce a variety of other metrics. Metrics • Emissions • Natural Gas Consumption 6 PRELIMINARY ORGANIZATION OF MATERIALS* I. II. III. IV. Overview of IRP Process Impact From Joining MISO DSM Potential Study DSM Avoided Cost Inputs • IRP Objectives & Framework • Energy Market • Load Forecast • Portfolio Design Analytics • Load Modifying Resources • Demand Side Management Potential Study Process • Benefits of ICF • Next steps • Capacity Market • Avoided Energy • Avoided Capacity *All material presented is informational and subject to change based on additional analysis, new information or stakeholder feedback. 7 IMPACT FROM JOINING MISO PRELIMINARY SUMMARY OF MISO ENERGY MARKET ENO pays MISO to serve its load and is paid to supply energy. A locational marginal price (“LMP”) mechanism is used which considers three components: energy, congestion and line losses. The LMP price differs at each generation and load point along the MISO network. The concept behind LMP is that the market price of electricity should be the cost of supplying the next unit when supply and demand are in balance. The energy cost includes the cost of supplying operating reserves. The diagram below is a simplified version of how the LMP methodology works. The cost to serve load in the West is $30/MWh and $40/MWh in the East. If there was no congestion the cost to serve load across both the West and the East would be $30/MW. Note, in this simplified example line losses are assumed to be zero. Source: Illustrative training materials 8 IMPACT FROM JOINING MISO PRELIMINARY SUMMARY OF MISO ENERGY MARKET (CONTINUED) MISO Operates what is commonly known as a Day Two Market: Day ahead market (hourly energy prices for a 24 hour period) Real Time Market (energy prices change every five minutes) Both load and energy generated clear at locational marginal prices (“LMPs”): generally about 95% or more in day ahead market, about 5% or less in real time market. Although the MISO market and SPO’s generation offers determine operation of ENO’s resources, physical control remains with SPO which provides the service to ENO and the other Entergy operating companies. 9 PRELIMINARY IMPACT FROM JOINING MISO MISO RULES CREATE A MARKET FOR CAPACITY • MISO is a “two-part” market in which capacity and energy transact and are valued separately. • The existence of an annual capacity market coupled with Resource Adequacy rules requiring load serving entities (“LSE”) to meet prescribed levels of capacity creates a value (or opportunity cost) for capacity. • The objective of meeting customers power needs at the lowest reasonable cost requires that the Capacity Value be considered in the System’s resource planning and investment decisions. • Capacity Prices are determined by supply / demand conditions in MISO overall as well as in each of the MISO Local Resource Zone (“LRZ”). ENO is in LRZ 9. Prices are the same throughout each LRZ and can be the same or different across LRZs. MISO North LRZs MISO South LRZs 8 9 10 PRELIMINARY IMPACT FROM JOINING MISO SUMMARY OF MISO CAPACITY MARKET MISO conducts an annual auction each year and each load serving entity must provide physical capacity or capacity credits to meet its projected peak load plus reserves referred to as a planning reserve margin requirement in MISO. MISO South is currently oversupplied. SPO estimates the 2013 reserve margin was 39% based on an SPO assessment of installed capacity and load. Consequently, capacity prices have been low and are expected to be low in the near-term reflecting the excess capacity in MISO South. As measured by MISO for the planning year started June 1, 2014, ENO had 140 MW of extra generating capacity meaning it did not have to purchase capacity in the MISO annual capacity auction. The clearing price for capacity in the auction was 16.44/MW-day (can be expressed as $6.00 per KW year). Overtime, however, capacity prices are expected to increase as the market tightens due to load growth, unit deactivation, etc. When valuing DSM the current and projected cost of capacity credits or the lowest cost of physical capacity (whichever is lower) represents the avoided cost of generating capacity which is the primary basis for the DSM avoided capacity cost benefit. 11 PRELIMINARY IMPACT FROM JOINING MISO LOAD MODIFYING RESOURCES • MISO values load modifying resources (“LMR”) on equal footing with generation resources (supply side resources). LMR resources are any resource that can reduce demand at the time of peak or at other times when MISO needs to reduce demand. • LMRs reduce a load serving entities peak load and the associated requirement to carry reserves. For long-term planning purposes ENO assumes reserves need to equal 12% of peak load. • LMRs recognized by MISO include: • • • Traditional interruptible tariffs registered with MISO. Demand respond resources under the control of the local balancing authority (“LBA”). Entergy operates the LBA for zone 9 which includes ENO. LMRs lower the amount of generating capacity credits needed in MISO’s annual capacity auction. 12 IMPACT FROM JOINING MISO Preliminary MISO MARKET CONSTRUCT SUMMARY ENO used to operate in a bilateral market, now it operates in an organized market ENO serves customer load through energy purchased from MISO. ENO MISO “Generators” sells output to MISO. $ MWh Load Serving Entity $ MWh ENO receives payments from MISO for its generation both owned and contracted which revenues are used to offset the cost of energy purchased to serve ENO load. Generation (Owned & Contracts) MISO market participation does not change the objective that ENO is trying to minimize customer revenue requirements. Customer Cost Load Settlement Cost Base Rate Components of generation costs (“NonFuel”) Generation Variable Production Cost (“Fuel & Emissions”) Generation Revenues Total Supply Cost Legend Effects (cost or benefit) of transaction flow to customer Denotes transaction between Utility (“LSE”) and MISO 13 PRELIMINARY ORGANIZATION OF MATERIALS* I. II. III. Overview of IRP Process Impact From Joining MISO DSM Potential Study DSM Avoided Cost Inputs • IRP Objectives & Framework • Energy Market • Load Forecast • Portfolio Design Analytics • Load Modifying Resources • Demand Side Management Potential Study Process • Benefits of ICF • Next steps • Capacity Market IV. • Avoided Energy • Avoided Capacity *All material presented is informational and subject to change based on additional analysis, new information or stakeholder feedback. 14 PRELIMINARY DSM PROCESS DSM RESOURCES There are two basic types of utility-sponsored DSM. Demand Response, which lowers capacity requirements, and Energy Efficiency, which lowers both capacity and energy requirements. Demand Response Energy Efficiency Load management program that have the intended goal of reducing or shifting load from hours with high electricity cost and/or reliability problems. Permanent changes to electricity use through replacement of end-use devices with more efficient equipment or more effective operation of existing devices, and any program or resource defined as an Energy Efficiency resource in any Energy Efficiency rule(s) issued by the New Orleans City Council. Demand Response programs may include direct load control (such as air conditioners and water heaters), and interruptible rates which include incentive payments designed to induce lower electricity use at times of high wholesale market prices or when system reliability is jeopardized. Generally, this type of resource results in reduced energy consumption across all hours rather than just event-driven targeted load reductions in specific hours. ICF International will produce a detailed DSM Potential Study For ENO and this will be reviewed with parties to this docket and the public at the 2nd Technical Conference scheduled for October 2014 15 PRELIMINARY DSM PROCESS TYPES OF DSM POTENTIAL Technically Achievable The estimated level of energy and capacity savings that could be achieved without consideration of cost, customer behavior or other barriers. Assumes customers adopt 100% of what is feasible. X Economically Achievable Cost effective sub-set of Technically Achievable potential. Ignores customer financial constraints, behavioral issues or other market barriers. X Achievable Potential Sub-set of Economically Achievable potential. In other words, what is likely to be achieved given customer profile and local market conditions. ICF Potential Study will solve for this level of DSM. Appropriate For IRP X Not Appropriate For IRP 16 PRELIMINARY DSM PROCESS 2014 DSM POTENTIAL STUDY PROCESS MAP 4 Standard Tests Total Resource Cost Program Administrator Ratepayer Impact Participant Test DSM Programs that achieve a TRC Test of 1.0 or higher are candidates for more detailed Optimization Modeling. Bundle Similar Programs If Needed for IRP Modeling Which Compares Supply-Side and Demand-Side Resource Options to Meet Customers’ Needs at the Lowest Reasonable Cost 17 PRELIMINARY DSM Process ICF CHOSEN TO CONDUCT DSM POTENTIAL STUDY • ENO will use ICF International to conduct the DSM Potential study for the ENO service territory (i.e. City of New Orleans excluding Algiers*) • ICF’s experience producing DSM Potential Studies for ENO, the other Entergy Operating Companies and other utilities across the U.S. will provide an independent, unbiased expert point of view: • ICF conducted an ENO DSM Potential in 2009 and 2012 for ENO as well as the other Entergy utility Operating companies. • ICF is currently conducting a DSM Potential Study for Entergy Louisiana (including Algiers), Entergy Gulf States and Entergy Mississippi. The cost of the current ENO study is modestly lower due to economies of scale. • In addition to its expertise pertaining to DSM, ICF can draw upon its deep knowledge across the energy spectrum, with particular expertise in environmental issues and environmental compliance modeling in the power sector. • ICF is a major contractor for the U.S. Environmental Protection Agency. * Algiers we be part of a larger study conducted encompassing all of Entergy Louisiana’s service territory 18 PRELIMINARY ORGANIZATION OF MATERIALS* I. II. III. IV. Overview of IRP Process Impact From Joining MISO DSM Potential Study DSM Avoided Cost Inputs • IRP Objectives & Framework • Energy Market • Load Forecast • Portfolio Design Analytics • Load Modifying Resources • Demand Side Management Potential Study Process • Benefits of ICF • Next steps • Capacity Market • Avoided Energy • Avoided Capacity *All material presented is informational and subject to change based on additional analysis, new information or stakeholder feedback. 19 PRELIMINARY DSM AVOIDED COST INPUTS ENO LOAD FORECAST FOR DSM POTENTIAL STUDY 1.5 7,000 5,000 1.0 4,000 3,000 0.5 2,000 Net Energy For Load (TWh) Total Peak Demand (GW) 6,000 1,000 0 WN Peak 10 Year CAGR 20142024 20242034 Peak: 0.9% 1.3% Energy: 0.95% 1.0% Total Peak Forecast 2030 2028 2026 2024 2022 2020 2018 2016 2014 2012 2010 2008 2006 0.0 Total Eenrgy Forecast WN Peak = Actual peak demand at the generator adjusted to normal weather. Note: For 2013 it’s the actual peak (has not been weather normalized). Forecast assumes no DSM spending beyond 2014 Forecast 2014 2015 2020 2025 2030 Peak (MW) 1,014 1,043 1,080 1,117 1,158 Energy (GWh) 5,250 5,461 5,763 6,046 6,359 20 PRELIMINARY DSM Avoided Cost Inputs AVOIDED ENERGY COST IN DSM POTENTIAL STUDY The use of avoided energy cost in the DSM Potential Study allows the examination of hundreds of DSM measures without having to run hundreds of detailed hourly Market Model simulations to assess which DSM programs are worthy of further study. The cost of avoided energy for ENO will be calculated as follows using the AURORA Market Model Nodal construct: The AURORA model assumes Reference Case fuel price forecasts, SO2 and NOx allowance prices and no carbon prices as of January 2014. AURORA forecasts the Locational Marginal Price (“LMP”) of power to serve load each hour over the twenty year IRP period for each ENO pricing node. MISO establishes each pricing node and there are 22 pricing nodes for ENO. The AURORA Market Model Nodal Construct has the same 22 pricing nodes. The ENO LMPs are load weighted to come up with a load weighted hourly LMP for ENO. The hourly LMPs are averaged into nine time buckets each year for use in the DSM Potential Study. The buckets are: Summer Weekday 5X16, Weekend 2X16, and Night 7X8 Winter Weekday 5X16, Weekend 2X16, and Night 7X8 Shoulder Weekend 5X16, Weekend 2X16, Night 7X8 21 PRELIMINARY DSM Avoided Cost Inputs AVOIDED ENERGY COST FOR DSM POTENTIAL STUDY ENO Load Zone LMPs $160 $140 $120 $/MWh $100 $80 $60 $40 $20 $0 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Summer Weekday 5X16 Winter Weekday 5X16 Shoulder Weekday 5X16 Summer Weekend 2X16 Winter Weekdend 2X16 Shoulder Weekend 2X16 Summer Night 7X8 Winter Night 7X8 Shoulder Night 7X8 22 PRELIMINARY DSM Avoided Cost Inputs AVOIDED CAPACITY COST IN DSM POTENTIAL STUDY The cost of avoided capacity will be calculated as follows: The forecast of the clearing price of the MISO annual capacity auction calculated on a $/kW Year basis. This price is expected to rise over time as reserve margins tighten. The result is multiplied by (1+ the average distribution line loss percent for each retail customer class. The loss %’s are: 4.29% (Residential) 4.17% (Commercial) 3.48% (Government) 1.45% (Industrial) The result is multiplied by (1+ the average transmission line loss percent) for the resource zone that ENO is in. This value is set by MISO for the next planning year and is used for calculating ENO’s planning reserve margin requirement. The value is 2.4% for the planning year beginning June 2014. For planning purposes the 2.4% is kept constant each year. The result is multiplied by (1 + a planning reserve margin). ENO uses a 12% planning reserve margin for long-term planning. An avoided transmission and distribution cost that comes from investing in utility sponsored DSM is added to the result above. The avoided transmission and distribution (“T&D”) cost is grown each year based on a forecast provided by IHS Global Insight of cost increases for T&D spending. In 2014 avoided T&D cost is estimated to equal $24.87/kW Year. *See MISO Business Practices Manual 011 (Resource Adequacy) Appendix L for more information 23 PRELIMINARY DSM Avoided Cost inputs ILLUSTRATIVE AVOIDED CAPACITY COST The avoided capacity cost from DSM for ENO varies by year. However, to provide an order of magnitude the levelized cost of capacity over the period 2015-2034 is displayed below. The discount rate used is ENO’s electric weighted average cost of capital which, as of 12/31/2013, is 6.93%. Value of Avoided Capacity Cost (Nominal $) Capacity at The Meter Residential Commercial Government Industrial $/KW Year $/KW Year $/KW Year $/KW Year $62.44 $62.44 $62.44 $62.44 Transmission Line Losses 1.50 1.50 1.50 1.50 Distribution Line Losses 2.68 2.61 2.17 0.90 Planning Reserves 7.99 7.99 7.93 7.78 T&D Cost 28.62 28.62 28.62 28.62 $103.23 $103.15 $102.66 $101.24 Total 24 PRELIMINARY Next Steps NEXT STEPS ICF continues to prepare the New Orleans DSM Potential Study. ENO continues to prepare IRP inputs: Define scenarios and sensitivities to be performed. Prepare IRP input forecasts (e.g. load, fuel prices, emissions prices and macro economic factors). Prepares a supply-side resource Technology Assessment (comparing the cost and performance of various supply-side options) Conventional technologies Utility-scale renewable resources Next milestone in IRP process to review DSM Potential Study results and IRP inputs: Technical Conference to be schedule for October 2014. 25
© Copyright 2025 Paperzz