WORK AT HEIGHTS HSE DIRECTIVE 3 WORKING AT HEIGHTS Directive owner per 01.01.2016 Bjarte Skulstad Please consult the asset’s HSE instructions for potential installation specific requirements 1 GENERAL Purpose The purpose of this directive is to ensure that • all work at heights is carried out safely • there are no accidents due to dropped objects • all use of ladders takes place in a safe manner • all scaffolding is erected, taken down and used safely • work above the sea is carried out safely Domain This directive applies to all BP-operated installations and contracted installations on the Norwegian continental shelf • Contracted mobile installations which have a system that satisfies the requirements in this directive, may use their own system provided this has been clarified upon implementation By following this directive, all requirements in the ”Working at Heights” section in the ”BP 8 Golden Rules of Safety” are complied with • Onshore facilities or projects where BP Norge have a particular responsibility and which are assessed being part of the petroleum activities References • Regulations relating to scaffolding, ladders and work on roofs, etc • Regulation relating to use of work equipment • The Norwegian Labour Inspection Authority’s regulations • OMS Procedure 4.5 Control of Work • OMS Risk 3.2 Personal Safety • BP Guide 100426 Ladder Safety • Norwegian Oil and Gas Association guideline 088 Common model for work permits • NS-EN 795 Protection against fall from heights. Anchoring methodes • HSE Directive no. 1 – Work permits • HSE Directive no. 11 Safe job analysis • Use of Work Basket - ref. HSE Directive 4 Lifting Operations • Norwegian Oil and Gas Association guideline 113 - Securing and rescue when working in heights (only in Norwegian) • Norwegian Oil and Gas Guidelines 105 Scaffolding (including competence requirements) • Norsk Standard NS 9600-1, 2, 3, 4 Definitions and abbreviations • Working at heights means all work carried out standing with one’s feet two metres or more above deck level where there is no fixed platform or approved scaffolding • Work permit is a written permit to carry out a defined work task at a given place onboard an installation under given conditions and in a safe manner 99 • Safe Job Analysis (SJA) is a systematic and step-by-step review of all elements of risk carried out prior to a specific task or operation so that measures can be taken to remove or control any elements of risk identified during the preparation for or performance of the said task or operation • First line MOB (Man overboard) preparedness includes oo the platform’s MOB crew standing by in case of an emergency or oo a standby vessel ready by the installation 2 WORKING AT HEIGHTS Competence for using fall arrest equipment • Complete BP fall arrest course offshore (4 hour in house training for fall protection) or onshore basic fall protection safety courses • For both courses the BP requirement is 5 yearly verification/ repetition Use of safety devices • All work carried out standing with one’s feet 2 metres or more above the deck requires: oo fixed platform with handrail, or oo scaffolding with green scafftag, or oo use of approved safety harness secured in a suitable anchor point which limits free fall to 2 metres from the footing, normally by use of a fall block, and oo filled in and signed ”Checklist for Work At Heights/Use of Harness” • When moving at height outside a fixed platform, scaffolding or ladder an approved safety harness with fallblock (or, alternatively, a Y-line) shall be used. When relocating the fallblock, the person involved must be secured with a fall arrest line • When using fall arrest equipment oo at least one person shall be present in the area nearby at all times in order to alert and start basic rescue work in case of a fall oo if needed prepare a written Rescue Plan oo the rescue plan shall take the time for a safe rescue into consideration in order to be able to rescue a person within sufficient time (i.e. prevent blood circulation injuries) • There shall be a site specific instruction on how required competent personnel are organized (for instance a rescue team) Securing underlaying area • Tools and equipment shall, as far as practical, b e secured with suitable means to prevent them from being dropped • If there is a potential for dropped objects the underlaying area shall be secured either with a guard person or roped off in co-ooperation with the area technician 100 • If dropped objects can damage pressurised equipment, the area shall be physically protected or de-pressurised in cooperation with the area techncian • Upon completion of work the area shall be checked to secure that no potential dropped objects are left Inspection of fall arrest harness • The user shall always visually check his/her safety harness, - system and anchor point and also have it checked by a coworker. If there is any doubt contact the scaffolding foreman or inspection re. anchor points • Defective harnesses or harnesses that lack the control tag (yearly control) for approved lifting device shall not be used and handed in for repair Use of fall lifeline • The anchorage point for the lifeline shall bear a load of 1000kg and the anchorage point should be above the user • The lifeline shall be connected to the anchorage point at the approved fall Harness. The rear anchorage point should be used but depending on the work the front anchorage can be used • Normally a self retracting lifeline shall be used • Restraint lanyard shall not be used as lifeline • Composition of the fall arrest system shall be based on identified risks like: potential pendulum movement, horizontal movement 3 USE OF LADDERS Use • Ladders may only be used for access or work of short duration, like installing temporary chain hoists, control and cleaning of F & G detectors Which ladders can be used • Ladders shall be in accordance with Chapter VI in the Regulations relating to scaffolding, ladders, work on roofs, etc • Ladders must have rubber knots at both ends and have no visual deformation • Only single ladders may be used • Stepladders up to 3.5m, may be used on firm and even foundations when there is no potential for fall to a lower level/ sea. Maximum climb height in the ladder is 2m. The 2m shall be clearly marked on the ladder • In electrical switchrooms, ladders shall be of non-conducting material Inspection • The user is responsible for checking the ladder before use • Defective ladders must be discarded 101 for: « • Check oo Twisted, bent or dented rails oo Cracked, worn, bent or loose steps oo Cracked or damaged welded joints, loose rivets or damaged stays oo Broken, bent or damaged locking mechanism (Stepladder) Safety measures • Ladders must be secured to prevent them from sliding or tipping over when used, by a person securing at the bottom until it is secured at the top • During movement on a ladder nothing must be carried in the hands • During work on a ladder three-point contact must be maintained (e.g. 2 feet and one hand) • When working, standing above 2 meters fall arrest harness shall be used 4 SCAFFOLDING with work plaform 2m and above shall have work « • Scaffolding permit level 2 for construction/demolition Approval of work • Construction/demolition scaffolding with work platform lower than 2m requires a general platform/area Work Permit level 2 • Construction/demolition scaffolding over sea requires approval according to section 6 of this directive Erecting/dismantling scaffolding • Scaffolding shall be erected/moved and dismantled by authorised scaffolders only • Scaffolding shall be in accordance with Chapter III of the Regulations relating to scaffolding, ladders, work on roofs, etc • A work platform (including access platforms) shall be secured with handrails and kick plates and other required covering/securing to prevent dropped objects. If this is not possible, the green scafftag shall be marked with necessary safety precautions, such as use of harness and closing of underlaying area Erecting/dismantling scaffolding over sea When scaffolding is erected/dismantled over sea: • the rules for Work over sea shall apply • a Toolbox Talk or Job Safety Analysis shall be performed • there will always be 2 scaffolders Scaffolding approval • Approval of scaffolding for use shall only be performed by authorised approval personnel. Ref. competency requirements, section 1 • Approved scaffolding is shown with a green scafftag with 102 date and signature. The scafftag must be at the scaffolding entrance • The scaffolding foreman must ensure scaffolds are inspected/ approved at least once every 7 days, as well as before and after spells of strong wind or other conditions that may damage the scaffolding Approval of the scaffolding equipment used for temporary securing • Approval of scaffolding equipment used for temporary securing shall be performed by authorized personnel. Ref competency requirements section 1 • Approved scaffolding is shown with a scafftag with date and signature. The scafftag must be wissible and attachen to the scaffolding equipment used • The scaffolding foreman must ensure the scaffolding equipment used are inspected/approved at least once every 14 days, as well as before and after spells of strong wind or other conditions that may damage the scaffolding equipment Use of scaffolding • Only scaffolding having a green scafftag is approved for use • Scaffolding must be used in accordance with limitations given on the green scafftag Storing the scaffolds • All scaffoding equpmet shall be stored at predefind/approved areas 5 ROPE ACCESS (RA) Standard, training, procedures and methods NS 9600 part 1, 2, 3 and 4 shall be used for rope access work • NS 9600-4 Requirements to and certification of suppliers of services sets the standard to the skills requirements, roles, responsibilities, methods and the execution of work Approval RA work requires approved work permit level 1 • Work shall be planned and executed according to NS 9600 • Rescue plan shall be attached to the Work Permit form 6 WORK OVER OPEN SEA Introduction • Work over sea means work taking place outside permanent railing where there is a risk of a person/persons falling into the sea • Work using stepladders, ladders or work platform where there is a risk of a person/persons falling into the sea • Work creating or working close to created openings where « 103 « there is a risk of a person/persons falling into the sea. (ref. SiKAP 1.70.153 for details) • Use of Rope Assess (RA) is not defined as work over sea when it is performed in compliance with RA requirements in section 5 • Work in hydraulic basket in ”moon pool” and on approved scaffolding is not defined as work over sea when extra barriers are in use such as oo fall arrest equipment oo man-riding belt oo net oo scaffolding build as a class 3 and to be certified and used as a class 2 scaffolding with extra heighten hand rail (railing). The scaffolding shall be certified every week and inspected after external influence e.g. strong wind Note: use of fall arrest equipment, man-riding belt or net requires independent securing (not attached to the scaffolding). Approval • Work over sea requires an approved work permit level 1 Restrictions Work over sea is permitted provided: • The wind speed is < 30 knots, measured at a 10 m level • The wave height is < 5 m (corresponds to 3 m significant wave height) • Standby vessel is in near-standby mode or MOB in extra preparedness mode • The MOB boat onboard or on the standby vessel is operative and can be launched/retrieved in case a person falls into the sea • The light and view is good enough to perform the work and rescue any person that may fall into the sea • Consent has been obtained from the diving supervisor if there is diving activity near the work site Safety precautions • When working over sea, a safety guard must be present and monitor the personnel located over sea at all times. The safety guard shall be familiar with and carry out tasks stated in the Safety guard’s duties in connection with work over sea • A life buoy with line and light shall be easily available • The performing personnel shall be familiar with all procedures, preconditions, risks and safety precautions relating to the work • Everyone working over open sea shall wear a life vest • When working below the cellar deck, consider whether to secure spills, overflow, etc. from e.g. fire water • Consider the need for implementing measures to avoid objects falling to lower levels or down on vessels 104 HSE DIRECTIVE 3 WORKING AT HEIGHTS ATTACHMENTS Attachment 1: Duties for the safety guard during work over sea Attachment 2: Safety Critical Work Procedure BP Attachment 1: Work Permit Form Level 1 Attachment 2: Work Permit Form Level 2 Attachment 3: Guidelines For Completing And Using Work Permit Form Attachment 4: Fire Guard´s Duties Attachment 5: Safety Measures For Working With Hydrocarbon Carrying Systems Attachment 6: Safety Measures For Working With Hazardous Chemicals Attachment 7: Safety Measures For Jet Water Washing Over 250 Bar Attachment 8: Safety Measures For Pressure Testing Attachment 9: Form For Approval Of Hot Work Class A In Classified Areas Attachment 10: Advance Approval Of Hot Work Class A In Classified Areas Attachment 11: Form For Logging Heating Value ATTACHMENT 1: DUTIES FOR THE SAFETY GUARD DURING WORK OVER SEA « The Safety Guard shall be clearly marked with “sikkerhetsvakt” Before commencing the work The Safety Guard shall: • participate in the work planning, including SJA/pre-job talks • locate the nearest fire call point/telephone • ensure that the agreed MOB function (Standby boat or the installation’s MOB) is informed and operational • establish and check radio communication with the work place, CCR or Standby boat • ensure escape routes are known by involved personnel • be familiar with the weather limitations for work over sea • perform “comradeship check” upon fall arrester equipment and life vest During work The Safety Guard shall: • keep track and overview of the number of people involved in the work and notify/report cases of personnel falling into the sea • be located at a permanent deck of the installation and have an unhindered view of the personnel working over sea • not take part in work that may interfere with his/her duty as safety guard • monitor changes in weather conditions/visibility and light and stop the work if the preconditions and limitations for the work are exceeded • monitor the work and surroundings and stop work should a situation arise that calls for such action Interruptions/completion of work The Safety Guard shall: • inform CCR or Standby boat • secure equipment/workplace If ”man over board” The Safety Guard shall: • notify colleagues, CCR or Standby boat • activate alarm • throw out a life buoy • maintain visual contact with person in sea • secure equipment/workplace Alarm situations The Safety Guard shall: • notify personnel over sea and stop work • secure that all personnel return to a permanent deck of the installation • secure equipment/workplace 106 ATTACHMENT 2: SAFETY CRITICAL WORK PROCEDURE BP Safety Critical Work Procedure BP USE OF FALL ARREST HARNESS / WORKING IN HEIGHT SiKAP No.: 1.70.076 Field: BPN Offshore Verified by: OTL-V Mech/Utility Date: 01.01.2011 Discipline: ALL TAG no.: N/A Validated by: B.Skulstad, S.G.Hellevik, A.Hide, G.Lied Date: 03.11.2011 Approved by; Owner HSSE Directive no 3 Working in Height Date: 24.09.2015 Rev. No.: 03 Expire: 12/2016 1 Consequence Task / Title: 2 3 4 5 D C B A Probability The objective for the work procedure (ref. classification sheet no,): K 1.70.076 Prevent personnel injury from working in height using fall arrest harness and associated equipment. Identified dangers (ref. classification sheet no,): K 1.70.076 1. Lack of competence in inspection, control and use of fall arrest harness and lines. 2. Uses anchor points of less strength than 1000kg load bearing capacity. 3. Incorrect limitation in use of equipment in relation to fall distance to protruding equipment or swinging can result in collision and hurt oneself. 4. If hanging for a long time in fall protection harness one can get circulation failure if one does not get to use relief (leg) strap. (Hang trauma) References: (Refers to relevant laws, regulations and BP’s directives, manuals, HMS-instructions, vendor’s documents, datasheet for chemicals and other dangerous substances,) Governing documents: 8 Golden Safety Rules – Permit to Work, Working at Hights; HSE directive 1 Work Permits, HSE directive 3 – Working at Hights. Vendor documents: Users Guide Drawings: Users Guide HSE data sheet, N/A (LogiChem): Planning / Preparation: WP Level 1 when working over sea, otherwise Level 2 Class ”A” Class ”B” Class ”B” Level 1 Level 2 Work Permit (WP) no.: Direct involved roles Performing technician, one person/safety guard (number): 2+ Gassfree /Access / Ref WP Scaffolding: Requirement for service by N/A vendor: Tools / Equipment / Chemicals: (Refers to special personal protective equipment, tools listings, special equipment and Equipment/system state: Ref WP Special personal protective Fall arrest harness and associated line(s) equipment: Special tools & equipment: N/A Special lifting equipment: N/A Special position of valves: N/A Step Description of the activity: (step number Comments: (especially critical steps and warning gives the sequence of actions; bullets indicates about adjacent activities are marked with underlined no.: that the actions can be performed in any chosen order) BOLD letters and eventual risk reducing measures are noted, ref to Tr@ction no. and SJA as relevant.) Plan for working at hights: - Consider the need for WP level 1 or 2 - Follow check list and tick off each step - Step 7, see identified danger no. 4 - The need for written rescue plan shall always be considered NOTE! It is vital to initiate rescue immediately after a fall. To be hanging in the harness without being able to use the relief strap may indulge hang trauma to the person and stop the blood from circulating. ARKIVERT: Eustvs2/BPN Info Vol//Templates/BP Norge Templates Evt.kvitter expected state of equipment / systems, in excess of WP, in advance to allow start of work) 1 av 2 107 Safety Critical Work Procedure BP USE OF FALL ARREST HARNESS / WORKING IN HEIGHT SiKAP No.: 1.70.076 Field: BPN Offshore Verified by: OTL-V Mech/Utility Discipline: ALL Approved by; Owner HSSE Directive no 3 Working in Height Date: 24.09.2015 Date: 01.01.2011 Check list for use of fall arrest harness / working in height 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. TAG no.: N/A Validated by: B.Skulstad, S.G.Hellevik, A.Hide, G.Lied Date: 03.11.2011 Rev. No.: 03 1 Consequence Task / Title: Expire: 12/2016 Check points Are you using a full body harness with double latch self-locking snap hooks and equipment with relief strap / foot strap? Has a proper anchor point for the safety line been located? Is fall arrest equipment in use that will limit the free fall to 2 meters or less? Has the fall arrest equipment been visually checked for: - damage/wear or defects? - control tag with the latest control date? If a ladder is used, is the ladder free of visual damage and secured? During securing of the ladder one person shall secure the ladder at the bottom until the ladder is secured at the top Has the fall arrest equipment, system and anchor point been checked by a colleague? Is there a person in the work area that can initiate basic rescue, if a fall should occur? Are equipment / tools used at height controlled and adequately secured against dropping? And not left behind finishing the work? Are underlying areas closed off and pressurized/sensitive equipment protected against dropped objects? Are lighting, noise and weather conditions satisfactory for the task? Are there any other risks and have they been evaluated and found acceptable? Use the 4 – Point Risk assessment Have the involved persons completed a course in fall arrest methods? Have all items on the checklist been answered YES without comments? If NO, the work shall not be started. Contact the line manager to find alternative methods to perform the work. N/A 2 3 4 5 D C B A Probability YES NO Comments ADDITIONAL COMMENTS : Note! Work over open sea also require the use of “Duties for the safety guard during work over sea” (attachment1) Date: Area technician (Work w/o WP): Performing technician(s): Closure of work 14. Are all loose tools/equipment removed from the workplace? Performing technician (s): END ARKIVERT: Eustvs2/BPN Info Vol//Templates/BP Norge Templates 108 END 2 av 2
© Copyright 2025 Paperzz