Barnard Construction Winter 2016 OnSite P e o p le b u ild in g f o r P e o p le . PG&E L-402 Program Makes History At V-214 in Cottonwood, California, the L-402 crew installed a valve automation and in-line inspection tool launcher barrel. The L-402 Program was completed as the largest liquefied natural gas/compressed natural gas (LNG/CNG) project in PG&E history. T o keep 44,000 Redding, California-area residential and commercial customers in service during natural gas line strength tests, Barnard Pipeline, Inc.’s (Barnard’s) L-402 Program Team supported Pacific Gas and Electric Company (PG&E) in completing the largest LNG/CNG project attempted in PG&E history. This effort required the injection of 1,351,853 gallons of LNG over 19 days, all of which was transported by trucks, each on a 30-hour round trip. At peak, Barnard employed over 200 craft employees with an additional 50 subcontracted employees. PG&E and the Barnard Team estimate that this complex project required over 1.5 million man-hours from design, construction, inspection, gas control, management, and vendors and suppliers. The Program finished with zero at fault dig-ins or line strikes, and zero OSHA recordable incidents. The team also received numerous customer appreciation notices. Since 2013, Barnard has participated in PG&E’s natural gas pipeline modernization program dedicated to strengthening and improving the integrity and safety of its natural gas transmission system in Northern California. A project within this program, L-402 included 12 contracts comprised of five valve automations, one in-line inspection site, and two hydrotest sections, all spread across 38 miles of single-feed lateral transmission pipeline. To complete this work, Barnard conducted 24 strength tests, automated 8 valves, and safely completed over 100 challenging excavations involving wet and “in the street” conditions. The Project began in early March 2016 and reached substantial completion in mid-October 2016. Barnard would like to thank valued subcontractors Rader Excavating, Inc., Machado and Sons, Inc., Material Testing, Inc., Lonestar West Hydrovac, and Badger Daylighting Corporation. Inside page 2 page 3 page 4 • • • • • • • • • Stabilizing Wilson Lock C-44 Reservoir Project Notables Dawn Dobson Joins Barnard Meet Our New Employees Tie-in Activities at Lake Mead Barren Ridge Energized Wedding Bells Barnard’s “Next Generation” Stabilizing Wilson Lock notables Barnard ranked among the nation’s top contractors in a number of disciplines this year, according to Engineering NewsRecord’s 2016 Top 400 Sourcebook released in early October. These rankings include: #1 in Hydroplants; #5 in Water Transmission Lines; #6 in Dams and Reservoirs; #6 in Petroleum Pipelines; and #9 in Power Transmission and Distribution. The Boone Dam Exploratory Drilling and Grouting Team reached a milestone by completing their Low Mobility Grout (LMG) operation this fall. The Team will now install High Mobility Grout while Tennessee Valley Authority (TVA) tests the effectiveness of the LMG. A labama’s abnormally dry fall has been hard on agriculture but good for concrete placement at Barnard’s Wilson Lock Modifications Project for the Tennessee Valley Authority in Florence, Alabama. Following a design by Hatch, we are stabilizing and upgrading the 1950’s-era lock on the Tennessee River. The lock is operated by the U.S. Army Corps of Engineers. In recent months, the Team completed Phases 1 and 2 concrete, placing nearly 10,000 CY without a single quality concern. The concrete is being supplied by Ready Mix USA. Barnard’s team also installed a cofferdam and dewatering system to allow for excavation in preparation for Phase 3 concrete. Phase 3 requires 21 lifts that climb 108 feet. As of publication, the team had completed up The Wilson Lock Team works on Phase 3 concrete placement. to lift five on Phase 3. Early in 2017, subcontractor Nicholson will mobilize to begin work on the installation and tensioning of 22 horizontal anchors and 4 vertical anchors. Barnard crews are installing sleeves for the horizontal anchors in the concrete placement currently underway. Safety has been a big focus at Wilson. We are proud to say that we have worked over 44,000 man-hours without a recordable or lost time accident. Foundation Excavation Begins at C-44 Reservoir A t the C-44 Reservoir Project near Indiantown, Florida, our Team is wrapping up deconstructive testing as a final step in test section development for construction of the 30-foot-high earthen embankment that will encircle a new 3,500-acre reservoir for the U.S. Army Corps of Engineers. Deconstructive testing included excavating previously installed drain pipe and manholes to verify alignment, identifying any settlement, and The 150-foot radial stacker offloads and stockpiles 80,000 verifying compaction. Subcontractor H2R of the 620,000 tons of drain sand slated for construction of now begins geological borings to identify the toe trench, blanket and chimney drain, and perimeter the material and depths for a permanent canal lining. toe trench. A dry November also allowed subcontractor McDonald Construction Corp. to begin excavating the foundation and existing ditches and canals onsite. To date, almost 1,000 feet of foundation has been excavated to the required elevation. Barnard crews are also moving and updating access roads to accommodate the new work activities on this four-year, multi-package project designed by HDR. 2 Barnard ins ide Bar n a r d Dawn Dobson Joins our Business Development Team B arnard is pleased to introduce our new Underground Construction Business Development Manager, Dawn Dobson. Throughout her 24-year career in tunneling and underground mining, Dawn has held supervisory and engineering roles on large, complex transportation and water/wastewater projects. She earned a B.S. in Mining Engineering from Montana Tech of the University of Montana in 1992 and then began her career with Consolidation Coal Company (now CONSOL Energy) near Pittsburgh, where she worked as a Miner, Safety Inspector and crew Foreman. Most recently, she was Project Manager during the completion of Kiewit’s $272 million Devil’s Slide Tunnel Project in California. As Barnard’s Underground Business Development Manager, Dawn will conduct client outreach regarding future projects, coordinate with joint venture partners, and prepare qualification and proposal packages. Dawn can be reached at dawn.dobson@ barnard-inc.com or (406) 586-1995. Dawn Dobson Meet Our New Employees Adam Beck, Project Engineer B.S., Construction Engineering Technology Montana State University Adam joins our Estimating Team at the Home Office. Brittany McNamee, Marketing Coordinator B.S., Marketing with minors in Int’l. Business and Entrepreneurship Montana State University Brittany joins the Marketing Team at the Home Office in Bozeman. Michael Dishong, Project Engineer B.S., Civil Engineering Technology University of Pittsburgh at Johnstown Michael joins our Muskrat Falls Team in Labrador, Canada. Erin Morrison, Administrative Assistant B.S., Marketing and Management Minot State University Erin joins our Safety and Equipment Teams at the Home Office. L3PS Team Prepares for Tie-in Outages W ork at the Discharge Aqueducts Project within the Lake Mead Low Lake Level Pumping Station (L3PS) Project has reached tie-in-focused activities for the 120-inch pipe, both inside the concrete valve vaults and in the excavation ditch. Pipe installation will be followed by backfilling with CLSM, in-place mortar lining, installation of the valves, and testing, all in advance of the tie-ins, which are critical activities in that they will require three outages of the Southern Nevada Water Authority’s (SNWA’s) pumping stations and water treatment plants. Elsewhere on the L3PS site, the Access Shaft drill and blast and concrete lining are now complete to a 490-foot depth. The shaft will be 525 feet deep at completion; the remaining 35 feet, however, will be excavated at a later scheduled date when crews develop the tunnels and forebay. Our L3PS Team now shifts focus to accessing an existing 450-foot-deep Surge Shaft, constructed under a previous contract A crew installs pipe at the Lake Mead Project site. as part of SNWA’s new Intake No. 3 system. Following access and set up, Barnard crews will begin pre-excavation grouting and excavation of the Connector Tunnel and Riser Shaft. Construction of the 34 drilled well shafts by our key subcontractor North American Drillers is now more than 50 percent complete. OnSite 3 701 Gold Avenue OnSite Bozeman, MT 59715 Barnard’s official newsletter. 406-586-1995 406-586-3530 (fax) barnard-inc.com An Equal Opportunity Employer Season’s Greetings! Barren Ridge Project Energized At the Barren Ridge Renewable Transmission Project, we’re wrapping up site restoration and hydroseeding activities beneath the new 230kV double- and triple-circuit transmission lines that have now been energized for more than two months. The 62 miles of new conductor, running from the Mojave Desert and through Southern California’s Angeles National Forest, now bring renewable energy to the Los Angeles Department of Water and Power’s more than 1.4 million customers in LA. Black & Veatch designed the project under Barnard’s Engineer Procure Construct contract. Wedding Bells Barnard’s “Next Generation” Charlie Slattery and Mallory Crandall were married on September 24, 2016, in Roseland, Virginia. Baby girl born to Tyler and Katelin Ross. Adelyn Rose Ross was born on July 24, 2016, weighing 6 lbs. 14 oz.
© Copyright 2026 Paperzz