Argyll and Bute Council 07/06/10 Page 1 of 7 Helensburgh CHORD 209275 Sea Wall Report CHORD Project Helensburgh – Sea Wall & Foreshore The aim of this report is to provide recommendations for the treatment of the sea wall and foreshore. The CHORD project represents a large investment in community facilities on the esplanade which will be dependent on the sea wall for protection. The CHORD project will also run adjacent to the foreshore and will be directly affected by its appearance. Works to the sea wall and foreshore would bring significant benefits to the CHORD proposals but were outside the client’s original brief (18th August 2009). This brief assumed that the sea walls of the esplanade were structurally sound and required only minor repair work and that the foreshore was regularly maintained by ABC. Subsequent investigation of the sea walls conducted by OCSC in March 2010 (refer to Appendix 2) revealed that although the walls are generally sound they are being undermined by wave action and further investigation is needed to give an accurate picture of the structural significance of this. The OCSC report also observed that maintenance of the wall (including grouting work) is required to maintain their structural integrity. In addition the public consultation process also highlighted the poor condition of the foreshore and so in May 2010 (refer to Appendix 3) OCSC investigated the options for improving this. The report concludes that the visual quality of the foreshore can only be maintained through a regular cleaning strategy and that even with the installation of a coastal defence system to retain more sand and reduce wave erosion this would still be the case. These surveys raise enough issues about the CHORD approach to the sea wall and foreshore for it to be prudent at this stage to review their treatment. SEA WALL Project Objectives To protect and enhance the proposed CHORD work on the esplanade To prevent damage to the existing sea wall To improve the visual appearance of the existing sea wall To improve public accessibility to the foreshore Argyll and Bute Council 07/06/10 Page 2 of 7 Helensburgh CHORD 209275 Sea Wall Report Sea Wall Option 1 - Do minimum (£60,000 allocated) Specific works Localised repairs to the existing sea wall using concrete and resins Pros A provisional sum for this work is included in the CHORD budget Cons The appearance of the existing sea wall may detract from the other CHORD enhancements Exposed wall footings and other structural issues are not addressed. Sea Wall Option 2 – Render Existing Wall (£175,000) *cost pending confirmation from specialist Specific works Option 1 plus repairs to the wall foundations followed by the application of a surface render (eg. ‘spraydeck rapid’) to unify the appearance of the wall and its footing. Pros Improved appearance in context of the CHORD enhancements Cons Durability of the surface treatment unpredictable due to the extreme conditions Sea Wall Option 3 - Structural (£70,000 - £350,000) Specific works Rebuilding existing sea wall Pros A new wall may be more attractive than the existing one Guaranteed long term protection for CHORD enhancements from the sea Opportunity to provide improved accessibility to beach front Cons Significant cost of this work Argyll and Bute Council 07/06/10 Page 3 of 7 Helensburgh CHORD 209275 Sea Wall Report FORESHORE Project Objectives To provide an improved setting for the proposed CHORD work on the esplanade To improve the visual appearance and amenity of the foreshore To reduce damage to the existing sea wall To improve public accessibility to the foreshore Foreshore Option 1 – Cleaning and recharging Regime (£60,000 - £90,000 per annum) Specific works An initial large scale clean up of beach to remove debris then recharging of the beach with new sand and the subsequent introduction of a regular maintenance regime to keep the beach in good condition. Pros Attractive appearance of the foreshore Increased use of the foreshore by visitors and public Improved perception of the town Cons On going annual financial commitment Foreshore Option 2 – Engineered Solution (£70,000 - £350,000) Specific works The use of physical barriers to allow the accumulation of sand on the foreshore e.g. artificial reef or near shore breakwater Pros Attractive appearance of the foreshore Increased use of the foreshore by visitors and public Cons Further investigation of the marine conditions required May result in a visually intrusive structure depending on solution adopted Planning permission and consent from Scottish Executive may be required Commitment to regular cleaning of foreshore will still be necessary Argyll and Bute Council 07/06/10 Page 4 of 7 Helensburgh CHORD 209275 Sea Wall Report Recommendations Sea Walls OCSC have carried out a preliminary review of the current condition of the sea wall and the proposed CHORD works will help to improve the wall’s short term structural integrity. However, this work is not sufficient to fully investigate the wall’s long term integrity and will have limited impact on its present appearance. Option 2 is the most cost effective way of addressing the appearance of the wall but its outcome is uncertain and the natural stone wall (with localised enhancements and remedial repairs) may actually have more character than would be achieved by a homogenous render that may weather poorly over time. The only option that guarantees an improved appearance to the wall and its long term structural integrity is Option 3 which requires a significant financial commitment. Foreshore OCSC have carried out a high level review of the current condition of the beach and its maintenance regime and have provided outline proposals for improving it's quality including beach nourishment/recharging, near shore breakwaters and artificial reefs. Further detailed studies need to be carried out before a decision can be made on which solution best suits the requirements of the West Bay. However, it is clear that any solution will require an ongoing cleaning and maintenance regime and a financial commitment to Foreshore Option 1 which will bring significant benefits to the CHORD project. In summary, unless there are sufficient funds available to rebuild the sea wall it seems the CHORD approach of localised repairs is the best short term option. The OCSC preliminary report describes the condition of the wall ‘as generally sound’. However, the poor condition of the foreshore is a concern. The success of the CHORD project could be compromised by the condition of the adjacent foreshore. In addition to improving the appearance and useability of the beach, Foreshore Option 1 would also improve the appearance of the sea walls and combat undermining from wave action. Argyll and Bute Council 07/06/10 Page 5 of 7 Helensburgh CHORD 209275 Sea Wall Report Appendix 1 –OCSC initial sketch diagrams of sea wall options Argyll and Bute Council 07/06/10 Page 6 of 7 Helensburgh CHORD Sea Wall Report Appendix 2 – OCSC Visual Inspection report 209275 VISUAL STRUCTURAL INSPECTION REPORT RIVER WALL ALONG THE WEST BAY ESPLANADE, HELENSBURGH PROJECT NO. A242S 15th MARCH 2010 15th March 2010 PROJECT NO. A242S VISUAL STRUCTURAL INSPECTION REPORT RIVER WALL ALONG THE WEST BAY ESPLANADE, HELENSBURGH INDEX PAGE 1.0 INTRODUCTION 1 2.0 BRIEF 1 3.0 SCOPE 1 4.0 DESCRIPTION OF STRUCTURE 1 5.0 OBSERVATIONS 2 6.0 RECOMMENDATIONS 3 APPENDED: Layout Drawing Photographs Appendix A Appendix B 15th March 2010 PROJECT NO. A242S VISUAL STRUCTURAL INSPECTION REPORT RIVER WALL ALONG THE WEST BAY ESPLANADE, HELENSBURGH 1.0 INTRODUCTION This report has been prepared at the request of Argyll & Bute Council as part of the Redevelopment of the West Bay Esplanade project The report is based on a visual structural inspection only carried out on the 14th March 2010 by Martin McCrossan, Regional Manager (Scotland) with O’Connor Sutton Cronin Consulting Engineers. Weather conditions during the inspection were generally sunny following a period of heavy rain. 2.0 BRIEF A visual structural inspection report was requested by Argyll & Bute Council to assess if the sea wall along the West Bay Esplanade from William Street to Colquhoun Street is structurally sound as had been originally reported in the ‘Helensburgh – Redeveloping the West Bay Esplanade’ project initiation document. 3.0 SCOPE This is a report on the general condition of the sea wall based on a non-invasive inspection. All dimensions noted within the report are approximate and a dimensional survey was not carried out as part of the inspection. Details of the design and construction of the sea wall are unknown and this report does not comment on the overall structural capacity or stability of the wall. No material testing has been carried out as part of the report and any comments made on materials within the report are based solely on a visual grading of materials. No monitoring of the sea wall has been carried out and therefore this report does not comment on any ongoing movement or issues which may be present, 4.0 DESCRIPTION OF STRUCTURE The sea wall is approximately 340m in length from and varies in height from approximately 0.9m above ground level at the Eastern end adjacent to Colquhoun Street to approximately 2.2m high to the Western end adjacent to William Street with a sloped face at between approximately 24 and 35 degrees. The construction of the wall varies along its length although it is typically a natural stone / mortar composite. The construction of the wall between Colquhoun Street and James Street consists of large natural stones tightly packed at the bottom of the wall and closely packed long and thin stones to the top. To the West of the monument adjacent to James Street a section of the sea wall appears to have had remedial work carried out in the past, with fewer natural stones visible and larger sections of mortar / concrete patching. Refer to section 4.0 of Appendix B. Moving West from James Street the construction of the wall changes to that of long narrow vertical stones on a fairly regular spacing. Approximately 20m West of the monument the construction changes to a horizontal pattern of long narrow natural stones in a mortar bed for approximately 7m before reverting to the previous vertical pattern. The wall then continues on a combination of long narrow vertical natural stone and larger natural stone sets in a mortar / concrete bed. Along its length the sea wall is interrupted by 3 sets of inset steps, a drainage outflow pipe and a large culvert. Refer to Appendix A for locations. Approximately half way between James and John Street the foundation of the wall is exposed above the seabed level and remains exposed for approximately 85m to the West before it steps down below seabed level. The foundation is formed in concrete and where exposed is between 300-450mm deep and projects between 1100-1300mm from the face of the sea wall. Weep holes are visible at mid-depth of the foundation at between 3 and 4m centres. Significant portions of the foundation show signs of overspill concrete also exposed above seabed level. 5.0 OBSERVATIONS The general condition of the wall is relatively good with few significant structural defects and no visible sign of structural instability. There is however a number of issues which occur fairly consistently along the length of the wall as discussed in the following sections. 5.1 Grout Loss Along the length of the wall there are constant signs of grout loss between the natural stones however it is particularly noticeable at the base of the sections of wall constructed using the long narrow sections of natural stone. Refer to section 5.1 of Appendix B. 5.2 Undermining of Foundation The foundation is exposed above ground for approximately 85m with the full depth of the toe being exposed for approximately 70m. There is a large section of overspill concrete also exposed above sea bed level however there is a 10m section where the sea bed has been washed away and the toe of the foundation has been undermined slightly. Refer to section 5.2 of Appendix B. 5.3 Foundation Damage There are 3 locations along the exposed section of the foundation which show signs of cracking or where a section of the foundation toe has broken away. These locations may relate to construction joints during the construction. On one of the broken sections a 6mm reinforcement bar can be seen protruding. Refer to section 5.3 of Appendix B. 5.4 Debond of Sea Wall Base from Foundation Toe There is a 5-10m long section where the base of the sea wall and the foundation have become debonded and a joint has opened up between the two. This occurs to the West of John Street. Refer to section 5.4 of Appendix B. 5.5 Drainage Outfall To the West of John Street the sea wall is penetrated by a drainage outfall pipe. One of the hinges on the non-return flap valve has corroded and the flap valve is hanging from the second hinge. Refer to section 5.5 of Appendix B. 5.6 Steps There are three sets of in-set steps providing access from the esplanade to the beach. The steps have been constructed in concrete and are showing signs of considerable wear however they would appear to be structurally sound. The steps between Colquhoun Street and James Street have cracks across the side aprons. Refer to section 5.6 of Appendix B. 6.0 RECOMMENDATIONS In general the condition of the sea wall is relatively good however as noted in Section 5.0 there are a number of areas that require some attention. 6.1 Grout Loss The presence of small pockets of grout loss is not considered of major structural significance at this time however if left in it’s current state the problem will gradually get worse as the result of both wave action creating pressure pockets within the body of the wall and freeze-thaw action causing the mortar to be fractured further. It is recommended that a maintenance regime is put in place to locate the worst affected areas, which should be cleaned out to remove all surface laitance and grouted with a high strength non-shrink grout suitable for marine environments such as ‘Expocrete UA’ by Fosroc. 6.2 Undermining of Foundation From the visual inspection it is unclear how much undermining of the foundation has occurred and what / if any impact that has had on the overall stability and function of the sea wall. Further investigation is recommended in co-ordination with Argyll & Bute Council to determine the exact extent. 6.3 Foundation Damage Although there are signs of damage to the foundation they would appear to have had limited impact on the overall stability or function of the sea wall. There were no signs of differential movement between adjacent sections of foundation or wall. It is recommended that that the foundation is broken back locally to provide a minimum section of 450mm and the section is then re-cast with dowel bars drilled into both sides. 6.4 Debond of Sea Wall Base from Foundation Toe The occurrence of a joint between the base of the wall and the foundation was limited to one section of between 5 and 10m length. There would appear to be no sign of slippage between the wall and foundation and it is likely this has been caused by the ingress of water at the base of the wall being subject to freezethaw action. It is recommended that the sections of mortar between the stones in this area are broken out, cleaned and re-grouted with ‘Expocrete UA’ by Fosroc. 6.5 Drainage Outfall The hinges of the flap valve should be removed and new hinges welded to the existing outfall pipe and a new flap valve installed. 6.6 Steps The steps between Colquhoun Street and James Street have cracks across the side aprons and these cracks should be injected with a resin which is suitable for marine environments to prevent the ingress of water which over time will potentially lead to the steps themselves cracking. This is a report for the use by Argyll & Bute Council only. MARTIN McCROSSAN For O’Connor Sutton Cronin APPENDIX A LAYOUT DRAWING APPENDIX B PHOTOGRAPHS 4.0 - Concrete Patching at Monument 5.1 – Grout Loss West of Colquhoun Street 5.1 – Grout Loss East of Monument 5.1 – Grout Loss West of Monument 5.1 – Grout Loss West of Monument 5.1 – Grout Loss 15m East of Culvert 5.2 – Exposed Foundation 5.2 – Exposed Foundation 5.2 – Exposed Foundation 5.2 – Exposed Foundation 5.2 – Exposed Foundation 5.2 – Exposed Foundation Undermining 5.2 – Exposed Foundation Undermining 5.3 – Exposed Foundation Damage 5.3 – Exposed Foundation Damage 5.3 – Exposed Foundation Damage 5.3 – Exposed Foundation Damage 5.3 – Exposed Foundation Damage 5.3 – Exposed Foundation Damage 5.4 – Debonding at Base of Sea Wall 5.5 – Drainage Outfall 5.6 – Steps between Colquhoun Street and James Street 5.6 – Steps between Colquhoun Street and James Street 5.6 – Steps between Colquhoun Street and James Street 5.6 – Steps between James Street and John Street 5.6 – Steps between James Street and John Street DUBLIN OFFICE 9 Prussia Street Dublin 7 GALWAY OFFICE The Grainstore Lower Abbeygate St. Galway CORK OFFICE Unit C, Building 6800, Ave 6000 Cork Airport Business Park Cork BELFAST OFFICE 4C Weavers Court Linfield Road Belfast BT12 5GH Tel. 00353 (1) 8682000 FAX 00353 (1) 8682100 Tel. 00353 (91) 560310 FAX 00353 (91) 532547 email: [email protected] Tel. 00353 (21) 5004900 FAX 00353 (21) 4299177 email: [email protected] Tel. 0044 (0) 2890244444 FAX 0044 (0) 2890244442 email: [email protected] SCOTLAND OFFICE Suite 4/4, 53 Bothwell Street, Glasgow, G2 6TS ROMANIAN OFFICE OCSC si Asociatii Str. Ion Campineanu, no. 1, sc. A, II-2 (second floor, unit 2), Sector 1., Bucharest Postal code: 010031 Romania Tel. +040 (31) 4256384 WARSAW OFFICE OCSC Sp. z.o.o. Ul. Targowa 43 03-728 Warszawa, Poland FAX +040 (31) 4256387 email: [email protected] email: [email protected] email: [email protected] LONDON OFFICE 40 Bowling Green Lane London EC1R 0NE Tel. 0044 (0) 2074157120 FAX 0044 (0) 2074157012 email: [email protected] ABU DHABI OFFICE (Also serving Qatar) P.O. box 35899 #203 Golden Falcon Tower Hamdan St. Abu Dhabi UAE Tel. +97150 8626273 email: [email protected] Tel. +44 (0)141 404 2785 FAX +44 (0)28 9024 4442 email: [email protected] RUSSIAN OFFICE OOO “O’CONNOR SUTTON CRONIN” Building 26, Novocheryemushkinskaya, Moscow, 117218, Russia Mobile (RUS) +7 916 065 4390 Mobile (INT’L) +353 86 172 4018 email: [email protected] LIBYAN OFFICE O'Connor Sutton Cronin - Libya AL-Ankabout Engineering & Technical Consulting Office Ain-Zara, In-front of AL-Fateh UniversitySection B Tripoli-Libya PO.BOX 4811 Ain-Zara Tel / FAX 00218-214623279 email: [email protected] O’CONNOR SUTTON CRONIN International Multi-disciplinary Engineers Tel. 0048 (22) 7410020 FAX 0048 (22) 6183013 COSTA RICAN OFFICE Apdo 86-1Z00 Pavas San Jose Costa Rica Tel. +353 86 8198459 email: [email protected] Argyll and Bute Council 07/06/10 Page 7 of 7 Helensburgh CHORD 209275 Sea Wall Report Appendix 3 – OCSC Beach maintenance report O’CONNOR SUTTON CRONIN Consulting Engineers Suite 4/4, Mercantile Chambers 53 Bothwell Street, Glasgow, G2 6TS Ph. 0141 404 2785 Fax 028 9024 4442 Job Ref: A242S Title: Helensburgh CHORD Client: Argyll & Bute Council Date: May 2010 BEACH MAINTENANCE Introduction The current condition of the beach adjacent to the pier and West Bay Esplanade has been raised as a key concern during the public consultation phase of the CHORD projects in Helensburgh. As a result O’Connor Sutton Cronin have been requested to carry out a high level review of the current condition of the beach and provide outline proposals for improving the quality of the beach. The beach as referred to within this paper is the section from the Western face of the pier and running along the West Bay for approximately 175m. It should be noted that there have been no coastal or marine studies carried out as part of this exercise and all options suggested would require detailed investigation and design to determine their success. Current Situation At present the beach is noted as containing a large amount of coastal/marine litter especially around the slipway adjacent to the pier. The four main sources of coastal/marine litter are typically: public littering, the fishing industry, the shipping industry and the sewage network. Although a full litter survey has not been carried out, based on a number of visual inspections the main sources of litter would appear to be timber, plastic, metal (cans etc) and paper however it is likely that under closer inspection there will also be sewage related debris. It is believed that the current maintenance regime for the beach includes a quarterly clean up by means of tractor and rake and that a more regular maintenance regime had been in place previously. It is also understood that Argyll & Bute Council have in the past employed seasonal workers for the sole purpose of beach cleaning over a period of 20 weeks throughout the summer period. Beach Maintenance Although the beach is outside the boundary of the CHORD project it is seen as a key asset to Helensburgh and the success of the environmental improvements to the West Bay Esplanade is likely to be undermined if the beach itself is not improved and maintained. In terms of improving the visual appearance of the beach as it currently stands the options would be: Carry out large scale clean up of the beach to remove all litter/debris including all litter trapped in the Pierhead gabion walls. Beach Nourishment/recharging. The initial outlay is likely to be between £10,000-50,000 dependant upon the source of the recharging material. Provide additional resources in the form of two council employees to manually remove litter and debris from the beach on a weekly or bi-weekly 1 O’CONNOR SUTTON CRONIN Consulting Engineers Suite 4/4, Mercantile Chambers 53 Bothwell Street, Glasgow, G2 6TS Ph. 0141 404 2785 Fax 028 9024 4442 Job Ref: A242S Title: Helensburgh CHORD Client: Argyll & Bute Council Date: May 2010 BEACH MAINTENANCE basis as deemed necessary Invest in a pedestrian operated beach cleaner reducing the manpower to one person per week An alternative to this relatively low tech approach would be to incorporate the beach improvements into an engineered solution that would also act as a form of coastal protection such as: Nearshore breakwaters: Normally built of rock at the high water mark they do not prevent some wave energy to reach further up the beach. They are visually obtrusive and in storm conditions may allow debris to accumulate on the upper shore. Costs are in the range of £20,000-£60,000 per 100m (RLF to provide costs based on drawing A242S/CSK10). Nearshore Breakwater on the upper foreshore in the Dornoch Firth Artificial Reefs: Similar to the nearshore breakwater however they are located further from the shoreline and will be submerged for at least part of the tidal cycle. When submerged they may cause navigation problems for anybody looking for access to the slipway. Costs are in the range of £40,000-100,000 per 100m (RLF to provide costs based on drawing A242S/CSK10). With both schemes we would require planning consent and also it will be likely that consent will be required from the Scottish Executive Rural Affairs Department under the Food and Environment Protection Act 1985 and also possibly the Scottish Executive Development Department (Transport Division) if they are deemed to endanger navigation. Conclusions Essentially the visual quality of the beach can only be maintained through a regular cleaning strategy and it is recommended that the council’s beach cleaning budget is reviewed in line with the aspirations of the CHORD projects and the overall benefits that are to be gained to Helensburgh as a whole. If it is decided that a form of coastal 2 O’CONNOR SUTTON CRONIN Consulting Engineers Suite 4/4, Mercantile Chambers 53 Bothwell Street, Glasgow, G2 6TS Ph. 0141 404 2785 Fax 028 9024 4442 Job Ref: A242S Title: Helensburgh CHORD Client: Argyll & Bute Council Date: May 2010 BEACH MAINTENANCE defence system should be incorporated this will not remove the requirement for ongoing maintenance and cleaning of the beach but it will help to reduce the resources required to do so. Further studies will be required and a marine engineering consultant will need to be appointed to further develop the options. 3
© Copyright 2026 Paperzz