9c-CIP Wastewater Projects

NO.
Project Name
Project
CAPEX
(MJD)
1
Improvement of existing Sewer Network of
Wadisseer Service Area
4.5
2
Improvement of the existing system of West
Zarqa Pumping Station Service Area: Phase 2
3
3
Improvement of Ain Ghazal existing Sewer
Network: Phase 2
14
4
Annual Expansion Program for wastewater
collection and house connections expansion for
the existing systems in Fuhais and Mahes: phase 2
7.5
Contract Name
Improvement of existing Sewer Network of
Wadisseer Service Area
Improvement of the existing system of West
Zarqa Pumping Station Service Area: Phase
2
Improvement of Ain Ghazal existing Sewer
Network: Phase 2
Construction of wastewater collection
system and house connections in Balqa
Governorate
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
4.5
Amman
2016 - 2018
3
Amman
2016 - 2018
14
Amman
2016 - 2017
Balqa
2016 - 2017
15
5
Annual Expansion Program for wastewater
collection and house connections expansion for
the existing systems in Fuhais and Mahes: phase 3
7.5
Balqa
2020 - 2021
6
Madaba System Extension (Trunk, Collection
sewer, House Connection): Phase 1
30.2
Madaba
2016 - 2019
7
Madaba Annual Expansion Program for collection
sewers and house connections: Phase 2
Madaba
2020 - 2022
8
Eastern Zarqa Pumping Station SystemReplacement of forcemain of the EZPS by
700mm diameter pipeline
9
10
11
12
13
Annual Expansion Program for wastewater
collection and house connections expansion for
the existing systems for Ajloun Qasabeh and
Kufranja Districts
Annual Expansion Program in Irbid for
wastewater collection and house connections:
Phase 1
Annual Expansion Program in Irbid for
wastewater collection and house connections:
Phase 2
Annual Expansion Program for collection sewers
and house connections in Ma'an Service System:
Phase 1
Annual Expansion Program for collection sewers
and house connections in Ma'an Service System:
Phase 2
Miscellaneous Wastewater system Projects in
Madaba
33.2
15
Construction of Transmission pipeline 900
mm from east zarqa ( hashmyeh) lifting
station to Kherbet Samra WWTP , 10 Km
length
15
Zarqa
2016 - 2017
10
Rehabilitation of Wastewater Network for
South Ajloun
10
Ajloun
2016 - 2020
Irbid
2016 - 2020
Irbid
2020 - 2021
Ma’an
2016 - 2018
Ma’an
2022 - 2025
3
2.5
Miscellaneous Wastewater system Project in
Irbid
5
2.5
12.5
Wastewater Collection System in Ma'an (
Engineering Services and Implementation)
12.5
25
NO.
Project Name
Annual Expansion Program for collection Sewers
14
and House Connections for Jafer Area
Tafila System Extension (Trunk, Collection Sewer,
House Connection)
Annual Expansion Program for collection sewers
16 and house connection in Tafila, Ies and Ruwaym
areas: Phase 1
Annual Expansion Program for collection sewers
17 and house connection in Tafila, Ies and Ruwaym
areas: Phase 2
15
18
19
Annual Expansion Program for collection sewers
and house connection expansion for Mouta'a City
Karak System (Trunk, PS, Collection sewer,
House Connection)
Annual Expansion Program for collection sewers
20 and house connection expansion for Karak City:
Phase 1
Annual Expansion Program for collection sewers
21 and house connection expansion for Karak City:
Phase 2
Expansion of Collection Networks within the
22
existing system of Aqaba City Phase 1
Expansion of Collection Networks within the
23
existing system of Aqaba City Phase 2
Improvement of Wastewater Network in
24
Hashimia District, Beren, Hiteen Camp
Construction Sewer Network and House
25 Connections in the unsewered localities of Um
Qsair and Moqabaleen
Project
CAPEX
(MJD)
0.6
20.5
Contract Name
Annual Expansion Program for collection
Sewers and House Connections for Jafer
Area
Tafila System Extension (Trunk, Collection
Sewer, House Connection)
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
0.6
Ma’an
2017 - 2018
20.5
Tafila
2016 - 2017
Tafila
2016 - 2017
Tafila
2020 - 2022
Karak
2016 - 2018
Karak
2016 - 2018
Karak
2016 - 2018
Karak
2016 - 2018
Karak
2016 - 2018
Karak
2020 - 2023
Aqaba
2016 - 2018
Aqaba
2017 - 2020
2.5
Construction of Wastewater collection
system in Tafilah
5
2.5
3
19
Annual Expansion Program for collection
sewers and house connection expansion for
3
Mouta'a City
wastewater system network in karaka Phase
4700000
one
wastewater system network in karak Phase
9500000
r\two
wastewater system network in karak Phase
4800000
three
2.5
Miscellaneous Wastewater system Project in
Karak Governorate
4.5
2
9.33
Construction of wastewater network and
replacement of the existing network
17.33
1.2
Improvement of Wastewater Network in
Hashimia District, Beren, Hiteen Camp
1.2
Zarqa
2017 - 2018
22.6
South Amman Sewer Network Project /
Phase Three
90
Amman
2016 - 2018
12
Amman
2016 - 2018
20
Amman
2016 - 2018
8
Construction of Wastewater Collection and House
26
Connection of the Unsewered Area of Abu Nseir
12
Construction of Wastewater Collection and
House Connection of the Unsewered Area
of Abu Nseir
Construction of sewer network and house
27 connections in the localities of Marka and Nasr in
West Zarqa Pumping Station Service Area
20
Construction of Miscellaneous Wastewater
Project in Amman ( East Amman, Nasir)
NO.
28
29
30
31
32
33
34
35
36
37
38
39
40
Project Name
Construction of sewer network and house
connections for the unsewered localities of Abu
Alanda & Queisma in Ain Ghazal service area:
Phase2
Annual Improvement Program of Amman
existing sewer Network: Phase 1
Annual Improvement Program of Amman
existing sewer Network: Phase 2
Construction of Sewer Network and House
Connections in the locality of Majr Al Hamam
within Wadisseer District
Construction of Wastewater Collection and House
Connection for the locality of Wadisseer in
Wadisseer District
Construction of Sewer Network and House
Connections in Khraibet Essooq, Jawa and
Yadoodeh Localities within Quaismeh District
Construction of Sewer Network and House
Connections in the locality of Binayat within
Na'oor District
Construction of Sewer Network and House
Connection for the unsewered locality of Um El
Summaq within Na'oor District
Construction of Sewer Network and House
Connection for the unsewered locality of Badr
Jadeda within Wadisseer
Construction of wastewater collection system and
house connections in Ira &Yargha area, Botna,
Shona, and Treatment Costs needed
Ma'mounieh Collection System & WWTP
Maieen Collection System & WWTP
Faisalieh Collection System & WWTP
Construction of wastewater collection system and
41 house connection in Sukhneh, and transmission
system from Sukhneh PS to EZPS
Construction of wastewater collection system and
42 house connections in unsewered areas in the East
Zarqa System
Project
CAPEX
(MJD)
6.4
18.3
18.3
Contract Name
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
South Amman Sewer Network Project /
Phase three
90
Replacement of Wastewater Transmission
Line
36.6
Amman
2016 - 2018
Amman
2016 - 2017
Amman
2020 - 2021
19
Wastewater Network System Projects in
Na'or ( 5 Phases)
55
Amman
2016 - 2018
76
Construction of Wastewater Collection and
House Connection for the locality of
Wadisseer in Wadisseer District
76
Amman
2016 - 2018
53
South Amman Sewer Network Project /
Phase three
90
Amman
2016 - 2018
6
Wastewater Network System Projects in
Na'or ( 5 Phases)
55
Amman
2016 - 2018
4.8
Wastewater Network System Projects in
Na'or ( 5 Phases)
55
Amman
2016 - 2018
8.8
Amman
2016 - 2018
30
Balqa
2017 - 2020
7.1
7.3
6.7
13.5
Madaba
Madaba
Madaba
2016 - 2017
2016 - 2017
2016 - 2017
Zarqa
2016 - 2017
2.802
Zarqa
2016 - 2017
5.29
Zarqa
2016 - 2017
8.8
30
7.1
7.3
6.7
15
14
Construction of Sewer Network and House
Connection for the unsewered locality of
Badr Jadeda within Wadisseer
Preparation of Studies and Construction of
Wastewater System in Ira,Maghareeb,Botna
and Shona
Ma'mounieh Collection System & WWTP
Maieen Collection System & WWTP
Faisalieh Collection System & WWTP
Sukhneh Wastewater Project
Construction of 400 mm transmission
pipeline from Sukhneh lifting station to
East Zarqa lifting station, 10 Km length
Wastewater Collection System Project in
Azraq / Package One/ Northern Azraq
Wastewater Collection System Project in
Azraq / Package Two/ Northern Azraq
1.5
NO.
Project Name
Zarqa System
Construction of the wastewater collection and
43 house connection and treatment for the unsewered localities of Ajloun
Construction of Wastewater Collection System
44 and House Connections for Kofor Khal & Baliela
areas in Jerash District
45
Construction of Wastewater Collection System
and House Connections for Bal'ama
Project
CAPEX
(MJD)
30
14
20
Construction of Wastewater Collection System
46 and House Connections for Badiah Shamaliyyeh
Al Gharbiyyeh
14.2
Construction of Wastewater Collection System
47 and House Connections including Pumping
Station for Manshiyyet Bani Hasan
5.2
48
Construction of wastewater collection system and
house connections for the rest of Mafraq City
Construction of Wastewater Collection System in
49 addition to WWTP for the unsewered localities in
Koorah District- Birgish Project
16.6
41.5
Contract Name
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
Wastewater Collection System Project in
Azraq / Package Three/ WWTP
5.923
Zarqa
2016 - 2017
Construction of Wastewater Collection
System Project in Junaid Area -Ajloun
30
Ajloun
2020 - 2022
4
Jarash
2016 - 2017
3.5
Jarash
2016 - 2017
3
Jarash
2016 - 2017
3.5
Jarash
2016 - 2017
20
Mafraq
2016 - 2017
14.2
Mafraq
2016 - 2017
5.2
Mafraq
2016 – 2017
16.6
Mafraq
2016 - 2017
18.5
Irbid
2017 - 2020
5.9
Irbid
2017 - 2020
4.3
Irbid
2017 - 2020
8.7
Irbid
2017 - 2020
Construction of Wastewater Collection
System Project in Jbarat , Manara ( Bab
Amman Jarash) Area /Phase one
Construction of Wastewater Collection
System Project in ( Bab Amman Jarash)/Part
of Dahr El Siro/ Phase Two
Construction of Wastewater Collection
System Project in ( Bab Amman Jarash)/Part
of Dahr El Siro & Nabi Hood Area/ Phase
Three
Construction of Wastewater Collection
System Project in ( Bab Amman
Jarash)/Sakib Area / Phase Four
Construction of Wastewater Network in
Rhaba, Bal'ama, Eiddon bani hasan /
Mafraq
Construction of Wastewater Collection
System and House Connections for Badiah
Shamaliyyeh Al Gharbiyyeh
Construction of Wastewater Collection
System and House Connections including
Pumping Station for Manshiyyet Bani Hasan
Construction of wastewater collection
system and house connections for the rest of
Mafraq City
(Birgish Sewer Network – Phase oneWWPT, Design capacity 7500 m3/day –
Reuse line for irrigation, lifting station)
(Construction of wastewater System in
Jdetah – Birgish Phase Two)
( Construction of Wastewater System in
Kufr Abel – Birgish Phase Three)
(Construction of Wastewater System in
kufor Awan – Birgish Phase Four)
NO.
50
51
52
53
54
55
56
57
58
Project Name
Construction of wastewater collection system and
house connections in the unsewered localities in
Ramtha District- Sahel Horan
Construction of Wastewater Collection and house
connections and the Treatment Cost needed in
Qasabah Irbid District
Construction of sewer network system for Jafer
Locality in addition to the wastewater treatment
cost
Mouta'a System (Trunk, Collection Sewer, House
Connection)
Construction of a new sewer network system for
Western Villages of Irbid (Kufr Yoba, Bait Yafa,
Jumha)
Studying & Construction of a new sewer network
system for Mekhaba Area
Construction of a new sewer network system for
North Salt, Ein AL Basha, and Baq’a (North &
North East)
Construction of a new sewer network system for
Salt including WWTP
Construction of a new sewer network system for
Dair Alla, Almashareh, Shona North & South
Construction of a new sewer network system for
Jarash
Construction of a new sewer network system for
60
Delal Halabat Al Khaldieh
Construction of a new sewer network system for
61
Shava Badran (Three Packages)
59
Construction of a new sewer network system for
62 Qaser District, part of Qasaba District, Alrawda,
Samakieh, Alrabah including WWTP
Construction of a new sewer network system for
63 Prince Hashim Rouda, Petra District, Eil District
Project
CAPEX
(MJD)
37
40
5.3
16.6
60
50
90
10
200
5
38
24
50
9
Contract Name
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
(Construction of Wastewater System in
Kufor Rakib and Beit Edes – Birgish- Phase
five)
4.1
Irbid
2017 - 2020
Wastewater Collection System Project in
Sahel Horan
37
Irbid
2017 - 2019
40
Irbid
2017 - 2019
5.3
Ma’an
2017 - 2020
16.6
Karak
2016 - 2018
60
Irbid
2018 - 2020
50
Irbid
2023 - 2025
90
Balqa
2018 - 2020
10
Balqa
2016 - 2017
200
Balqa
2018 - 2020
5
Jarash
2016
38
Zarqa
2023 – 2024
24
Amman
2016 - 2018
50
Karak
2023 - 2025
4
Ma’an
2016 - 2018
( Construction of Water and waste water
system within Irbid area ( Hakama, Mghaier,
Wastyeh))
Construction of sewer network system for
Jafer Locality in addition to the wastewater
treatment cost
Mouta'a System (Trunk, Collection Sewer,
House Connection)
Construction of a new sewer network system
for Western Villages of Irbid (Kufr Yoba,
Bait Yafa, Jumha)
Studying & Construction of a new sewer
network system for Mekhaba Area
Construction of a new sewer network system
for North Salt, Ein AL Basha, and Baq’a
(North & North East)
Construction of a new sewer network system
for Salt including WWTP
Construction of a new sewer network system
for Dair Alla, Almashareh, Shona North &
South
Construction of a new sewer network system
for Jarash
Construction of a new sewer network system
for Delal Halabat Al Khaldieh
Construction of a new sewer network system
for Shava Badran (Three Packages)
Construction of a new sewer network system
for Qaser District, part of Qasaba District,
Alrawda, Samakieh, Alrabah including
WWTP
Construction of Wastewater Pipeline and
house connections and lifting stations for
Prince Hashim Rouda, Petra District, Eil
District
NO.
Project Name
Project
CAPEX
(MJD)
including lifting stations
Construction of a new sewer network system for
64
Athroh, Prince Haya, and Hay Alzera’a
65 Jordan Valley Wastewater Project
Grinatha, Alaresh and German University
66
Collection System & WWTP.
5.7
42
7
Contract Name
Construction of Wastewater Network and
house connections and lifting station /
Petra District
Construction of Wastewater Network for
Athroh / Package one
Construction of Wastewater Network for
Prince Haya, and Hay Alzera’a / Package
Two
Jordan Valley Wastewater Project
Grinatha, Alaresh and German University
Collection System & WWTP.
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
5
Ma’an
2016 - 2018
3.209
Ma’an
2016 - 2017
2.516
Ma’an
2016 - 2017
42
Jordan Valley
2017 - 2019
7
Madaba
2022 - 2025
67
Construction Sewer Network and house
connections in the unsewered Areas Phase 1
20
Construction Sewer Network and house
connections in the unsewered Areas Phase 1
20
Amman
2016 - 2018
68
Construction Sewer Network and house
connections in the unsewered Areas Phase 2
14
Construction Sewer Network and house
connections in the unsewered Areas Phase 2
14
Amman
2019 - 2025
1.4
3
1
Expansion of Fuhais and Mahes WWTP
Rehabilitation of As Salt WWTP
Expansion of East Jarash WWTP
1.4
3
1
Balqa
Balqa
Jarash
2022 - 2023
2022 - 2024
2016 - 2017
10
Expansion of Madaba WWTP
10
Madaba
2016 - 2018
4.8
2.2
2.45
1.1
4
Irbid
Irbid
Irbid
Irbid
Ma’an
2017 - 20219
2022 - 2025
2022 - 2024
2019 - 2021
2022 - 2024
30.75
Aqaba
2017 - 2020
69 Expansion of Fuhais and Mahes WWTP
70 Expansion of As Salt WWTP
71 Expansion of East Jarash WWTP
Expansion of Madaba WWTP & Establishment of
72
Wastewater Network
73 Expansion of Wadi Al Arab WWTP
74 Expansion of Central Irbid WWTP
75 Expansion of Ramtha WWTP: Phase 2
76 Expansion of Wadi Hassan WWTP
77 Expansion of Wadi Mousa WWTP
4.8
2.2
2.45
1.1
4
78 Expansion of Aqaba WWTP
30.75
Disposal of the Dry Sludge in the Northern
Governorates
80 Expansion of Ramtha WWTP Phase 1
79
81
Establishment of Parallel conveyance line for the
Treated Wastewater from Ain Ghazal WWTP
82
Contribution in the Expansion of Kharbit As
Samra for Handling Extra Amount of WW
40
14.7
2
230
Expansion of Wadi Al Arab WWTP
Expansion of Central Irbid WWTP
Expansion of Ramtha WWTP: Phase 2
Expansion of Wadi Hassan WWTP
Expansion of Wadi Mousa WWTP
Expansion of Mechanical wastewater
treatment and upgrade the required system
Disposal of the Dry Sludge in the Northern
Governorates
Expansion of Ramtha WWTP Phase 1
Establishment of Parallel conveyance line for
the Treated Wastewater from Ain Ghazal
WWTP
Contribution in the Expansion of Kharbit
As Samra for Handling Extra Amount of
WW
14.7
Northern
Governorates
Ramtha
2
Balqa
2016
230
Zarqa
2020 - 2024
40
2016 - 2017
2019 - 2021
NO.
Project Name
Establishment of Parallel conveyance line for the
83 Treated Wastewater from Madaba WWTP to
South Amman WWTP
Project
CAPEX
(MJD)
20
84
Establishment of Wastewater Treatment Plant
Transported by Trunk to Ghor Safi Landfill
58
85
Establishment of conveyance reuse line for the
Treated Wastewater from Wadisseer to Kafreen
7
86 Establishment of Parallel conveyance line trunk A
2
87 Establishment of Parallel conveyance line trunk B
2
88
Construction of New Tanker station (Sewage
dumping) replacement of the existing Ain Ghazal
60
Contract Name
Establishment of Parallel conveyance line for
the Treated Wastewater from Madaba
WWTP to South Amman WWTP
Establishment of Wastewater Treatment
Plant Transported by Trunk to Ghor Safi
Landfill
Establishment of conveyance reuse line for
the Treated Wastewater from Wadisseer to
Kafreen
Establishment of Parallel conveyance line
trunk A
Establishment of Parallel conveyance line
trunk B
Construction of New Tanker station
(Sewage dumping) replacement of the
existing Ain Ghazal
Contract
Years of
CAPEX Governorate
Implementation
(MJD)
20
Amman
2016 - 2017
58
Karak
2023 - 2025
7
Amman
2017 - 2018
2
Madaba
2016 - 2017
2
Madaba
2018 - 2019
60
Amman
2016 -2018