Projects and Engineering • 1st prize, 2008 European Crane Job of the Year, 2008 • New cutterhead installed at the Hallandsås-project • Carlsberg tanks are moved to Fredericia JO B OF TH IZE 1. PR E YE A R 2008 • A CR NE • Cranes prevent collapse Carlsberg tanks are moved to Fredericia A lot of power was required when 12 tanks of 31 ton each were lifted from Carlsberg’s facilities in Valby and onto steel frames on the ground. A 450 ton and 200 ton crane were needed. Moving 12 tanks from Valby to Fredericia requires planning and resources. And especially resources in the form of power, as each tank has a diameter of 8 m, is nearly 17 m high and weighs more than 30 ton. When full, a tank like this contains 2.5 million bottles of beer. The first challenge was to lift the empty tanks from their original location and onto a frame structure on which they were transported to the port of Copenhagen and further on to Fredericia by barge. Two cranes solved this first part of the task superbly. In two days, the 12 tanks were lifted onto their frame structures and ready to begin their journey to East Jutland. A total of 36 tanks will be moved to Fredericia, and Krangården is in charge of the turnkey project, which includes lifting the tanks in both Valby and Fredericia, arranging transportation in both cities and also sea transport by barge. Heavy lift at “DR Byen” The most spectacular event on the construction site of the Danish Radio new media building “DR Byen”. This is how DR described the erection of the passageway “Indre Gade” linking the buildings of “DR Byen” at second floor level above a water channel. It took five cranes – including the three largest ones in Denmark – to lift the enormous steel construction for this project. Almost one and a half years of planning came to fruition when part of the 190 m long roof over “Indre Gade” was installed 30 m above ground level. The large roof construction made of steel was lifted in two sections onto supports with help from the three largest cranes in Denmark. The first section, which was 66 m long and weighed 196 ton, was lifted 30 m above ground level using two cranes. The third crane hooked to a lifting yoke in the air, after which the three cranes jointly were able to turn the roof construction into place. Another two cranes were used to counterbalance the torsion of the construction due to the chosen method of lifting when the bridge was placed onto the supporting structure. For this task we won second prize for best European Crane job of the Year in 2007. Cranes prevent collapse When parts of the roof on Siemens Arena in Ballerup collapsed one cold day in January, rapid support to prevent further collapse was crucial. As a result, we were hired to bring cranes to secure the roof while support work was carried out. There was an imminent danger of a total collapse when the roof on Siemens Arena in Ballerup suddenly started to collapse. A solution had to be found to secure the roof while scaffolds were being built beneath the roof construction. We were hired to solve the task and found the number of cranes necessary for the project to succeed. Supports was placed beneath two trusses at a time, which meant that the cranes were constantly moved in order to be ready for the next area. The cranes had to be partially disassembled in order to be moved which required time, planning, timing and precision. Therefore, AutoCAD planning became an essential tool during the process. The project succeeded and the roof was prevented from further collapse. New cutterhead ready at the Hallandsås-project Space was cramped when we lifted and placed a new 200 ton cutterhead in the rock of the Hallandsås tunnel project. However, the tunnel boring machine is again thundering along the 8.6 km stretch which is part of the new railway connection between Malmö and Gothenburg. After many kilometres of faithful service through the rocks in Hallandsås, the old cutterhead was ready to be replaced. And we were asked to solve the task of lifting the new into place. A great challenge as the new 180 ton cutterhead section had to be moved and lifted within an area underground which only allowed very few centimetres of workspace. Four hydraulic gantries operated by remote control became the solution to this task. With a total capacity of 1,000 ton, these gantries installed the cutterhead in place. Ready to take on the hard work through the rocks. JO B OF TH IZE 1. PR E YE A R A CR NE 1st prize, 2008 European Crane Job of the Year 2008 • A 193 ton pedestrian bridge greets the many people who every day drive along the street of Ågade in Copenhagen. With its beautiful design, the bridge appears as a new city gate to Copenhagen. However, the design and construction of the bridge, not to mention the logistics on one of the most congested roads in Denmark, made this lifting task unique. The closure of Ågade for traffic for two days during Easter, 400 steel plates as surface protection, four cranes and four hydraulic gantries were the primary ingredients of this cocktail with which the Ågade bridge was lifted and put in place as planned. The arch of the bridge was lifted from horizontal to vertical position, pivoted 180 degrees and then finally mounted at an angle of 45 degrees on to the foundation beneath the bridge deck. 12 hours before the deadline, the project was completed far better than the permitted tolerances called for. The land of many bridges For many years, we have been the leading contractor and partner when moving and lowering bridges above roads and railways. Holstebro Gjettrupvej 2 . DK-7500 Holstebro Tel.: +45 97 42 45 00 Fax: +45 97 41 30 05 www.krangaarden.dk We always apply the most modern hydraulic control equipment thus ensuring that the beautiful constructions are not damaged during moving, lifting and lowering tasks. The bridge decks of many bridges above existing roads are cast in excess height to allow room for formwork and we have the expertise to lower the bridge Copenhagen Sindalvej 10 . DK-2610 Roedovre Tel.: +45 70 21 45 00 Fax: +45 70 21 45 01 www.krangaarden.dk deck down to the right level. New railway bridges are often built next to the railway in order to avoid obstruction of train traffic for an extended period of time. One reason why this is possible is our specially developed method of pushing the bridge in place by lifting the bridge deck, piers and foundations. Roedekro Skaanevej 16 . DK-6230 Roedekro Tel.: +45 74 52 45 62 Fax: +45 74 52 88 38 www.krangaarden.dk
© Copyright 2024 Paperzz