DNV-RP-A204: Quality Survey Plan (QSP) for Offshore Class New

RECOMMENDED PRACTICE
DNV-RP-A204
Quality Survey Plan (QSP)
for
Offshore Class New-building Surveys
SEPTEMBER 2011
The electronic pdf version of this document found through http://www.dnv.com is the officially binding version
DET NORSKE VERITAS AS
FOREWORD
DET NORSKE VERITAS (DNV) is an autonomous and independent foundation with the objectives of safeguarding life,
property and the environment, at sea and onshore. DNV undertakes classification, certification, and other verification and
consultancy services relating to quality of ships, offshore units and installations, and onshore industries worldwide, and
carries out research in relation to these functions.
DNV service documents consist of amongst other the following types of documents:
— Service Specifications. Procedual requirements.
— Standards. Technical requirements.
— Recommended Practices. Guidance.
The Standards and Recommended Practices are offered within the following areas:
A) Qualification, Quality and Safety Methodology
B) Materials Technology
C) Structures
D) Systems
E) Special Facilities
F) Pipelines and Risers
G) Asset Operation
H) Marine Operations
J) Cleaner Energy
O) Subsea Systems
© Det Norske Veritas AS September 2011
Any comments may be sent by e-mail to [email protected]
For subscription orders or information about subscription terms, please use [email protected]
Computer Typesetting (Adobe Frame Maker) by Det Norske Veritas
This service document has been prepared based on available knowledge, technology and/or information at the time of issuance of this document, and is believed to reflect the best of
contemporary technology. The use of this document by others than DNV is at the user's sole risk. DNV does not accept any liability or responsibility for loss or damages resulting from
any use of this document.
Recommended Practice DNV-RP-A204, September 2011
Contents – Page 3
CONTENTS
1.
GENERAL ............................................................................................................................. 4
1.1
1.2
1.3
Preamble ...............................................................................................................................................4
Objective ...............................................................................................................................................4
Scope ......................................................................................................................................................4
2.
DEFINITIONS....................................................................................................................... 4
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
Customer ...............................................................................................................................................4
Owner.....................................................................................................................................................4
Builder....................................................................................................................................................4
Society ....................................................................................................................................................4
IACS .......................................................................................................................................................4
Flag state ................................................................................................................................................4
Surveyor.................................................................................................................................................4
Hull Structure .......................................................................................................................................4
Documents .............................................................................................................................................5
Survey Methods.....................................................................................................................................5
3.
APPLICATIONS ................................................................................................................... 5
3.1
3.2
Certification of Equipment and Materials .........................................................................................5
Locations of Construction ...................................................................................................................6
4.
REVIEW OF THE CONSTRUCTION FACILITY .......................................................... 6
5.
NEW BUILDING SURVEY PLANNING........................................................................... 6
5.1
5.2
5.3
Kick-off Meeting ..................................................................................................................................6
Quality Standards .................................................................................................................................6
Survey Extent .......................................................................................................................................6
APP. A CATEGORIZATION OF SYSTEMS FOR TESTING AND COMMISSIONING ... 23
DET NORSKE VERITAS AS
Recommended Practice DNV-RP-A204, September 2011
1. General – Page 4
1. General
1.1 Preamble
This is a guide only for a typical drillship and should be used no more than as an example to prepare a project
specific Quality Survey Plan (QSP) that addresses all the requirements related to a specific project. A project
specific Quality Survey Plan with agreed extent of participation from DNV shall be submitted by the Builder/
Owner (as applicable) for approval by DNV prior to commencement of activities.
This guide contains requirements obtained from IACS unified requirements, Z23 “Hull Survey for New
Constructions”. For the convenience of users, various cross references to relevant rules and guidelines are
provided in addition to IACS documents.
IACS unified requirements; Z23 “Hull Survey for New Constructions” is available from www.IACS.co.uk.
This Guide also incorporates relevant requirements of IACS UI SC234, UI LL76 and UI MPC96 regarding
initial statutory surveys at new construction. Updates to IACS Z23 are also incorporated.
1.2 Objective
The objectives of this Guide is to ascertain various activities that are necessary for the Classification of a unit,
to identify Customer’s, DNV’s and various standards and procedures that are applicable to those activities, and
to define the extent of involvement by the Customer and DNV.
1.3 Scope
The scope is defined in the contract between the Customer and DNV but typically covers the requirements of
applicable rules related to main Class, Statutory and additional class notation. The scope of the typical Quality
Survey Plan should include all the activities of the new building project as much as possible, but the contents
of QSP shall not be considered as covering the detailed scope to the as specified in the contract.
Description of principles and procedures for DNV’s services related to new-building projects are described in
the various Rules for Classification e.g., DNV Rules for Classification of Offshore Drilling and Support Units
DNV-OSS-101, Rules for Classification of Floating Production and Storage Units DNV-OSS-102, etc.
2. Definitions
2.1 Customer
Customer is the party who has requested the Society's service and may mean the Owner or the Builder of the
Unit.
2.2 Owner
The registered owner of the vessel or any other organization or person who has assumed the responsibility for
operation of the vessel and who on assuming such responsibility has agreed to take over all the duties and
responsibilities.
2.3 Builder
Builder is the party contracted to build a vessel in compliance with the Society's rules.
2.4 Society
Det Norske Veritas AS.
2.5 IACS
The International Association of Classification Societies’ IACS unified rules, interpretations, guidelines and
recommendations may be found on www.iacs.org.uk.
2.6 Flag state
State under whose laws the vessel is registered or licensed.
2.7 Surveyor
Surveyor to Det Norske Veritas, authorized to carry out surveys and to conclude whether or not compliance
has been achieved.
2.8 Hull Structure
The hull structure is defined as follows:
i) Hull envelope including all internal and external structures
ii) Superstructures, deckhouses and casings
iii) Welded foundations (e.g., main engine seating)
DET NORSKE VERITAS AS
Recommended Practice DNV-RP-A204, September 2011
Page 5 – 3. Applications
iv) Hatch coamings, bulwarks
v) All penetrations fitted and welded into bulkheads, decks and shell
vi) The fittings of all connections to decks, bulkheads and shell, such as air pipes and ship side valves
– all ILLC 1966, as amended
vii) Welded attachments to shell, decks and primary members (e.g., crane pedestals, bitts and bollards), but only
as regards their interaction on the hull structure.
2.9 Documents
Reference to documents also includes electronic transmission or storage.
2.10 Survey Methods
Definition of survey methods which the Surveyor is directly involved in:
Survey: Signifies a systematic and independent examination of a unit, materials, components or systems in
order to verify compliance with rules and/or statutory requirements. Surveys will be carried out at the prefabrication sites, onboard the unit, as well as at sub-suppliers and other locations at the discretion of DNV,
which also decides the extent and method of control.
Unscheduled surveys (U): are planned activities undertaken by DNV to verify that applicable fabrication,
installation, and testing during mechanical completion phase, testing and commissioning activities related to
systems are carried out in accordance with applicable procedures in order to comply with the project
requirements.
Review (R): A systematic examination of drawings, design documents and/or records in order to evaluate their
ability to meet requirements, to identify any problems and to propose necessary actions.
Witness (W): Attending tests or measurements where the surveyor verifies compliance with agreed test or
measurement procedures.
Verification (V): Confirmation through the provision of objective evidence (analysis, observation, measurement,
test, records or other evidence) that specified requirements has been met.
MPQA: Manufacturer Product Quality Assessment (MPQA) is a tool to assess a Customer’s ability to control
product quality by using rating methodology. Where DNV has no recent experience with offshore activities at
the fabrication facility and/or when significant new infrastructure has been added, DNV may initiate an MPQA
and conclude the Customer’s QAQC-performance and set the initial survey scope on basis of the rating
methodology.
Survey Category I (Structure): is related to survey of “special areas” as defined and outlined in DNV-OS-C101
Design of Offshore Steel Structures. General (LRFD method) Section 4 C202 and C300.
Survey Category II (Structure): is related to survey of “primary areas” as defined in DNV-OS-C101 Design of
Offshore Steel Structures. General (LRFD method) Section 4 C202 and C300.
Survey Category III (Structure): is related to survey of “secondary areas” as defined in DNV-OS-C101 Design
of Offshore Steel Structures. General (LRFD method) Section C202 and C300.
Survey Category I (Systems): Systems which needs to be in continuous operation for maintaining the unit’s
manoeuvrability and position keeping. The definition is extended for systems associated with drilling and
production plants to cover systems which are needed to be available on demand to prevent development of, or
to mitigate the effects of an undesirable event, and to safeguard the personnel, environment and the installation.
Survey Category II (Systems): Generally defined as systems in continuous operation for maintaining the unit’s
manoeuvrability and station keeping, but which are necessary to maintain the unit’s main functions. The
definition is extended for systems associated with drilling and production plants to cover systems, which
ensures reliable operation and which maintains plant operation within given operational limitation.
Survey Category III (Systems): Defined as a system, which are neither Category I nor Category II.
3. Applications
Using this as a model document, a project specific Quality Survey Plan (QSP) that clearly identifies the agreed
level of participation by the Society shall be prepared by the Customer and accepted by the Society for use in
all new building classification projects.
3.1 Certification of Equipment and Materials
This document does not cover the certification of equipment and materials.
Evidence of acceptance for such items shall be provided by the Client by way of accompanying documentation
from a Class Surveyor at manufacturer’s or other applicable location and verified at the Customer’s location.
DET NORSKE VERITAS AS
Recommended Practice DNV-RP-A204, September 2011
4. Review of the Construction Facility – Page 6
3.2 Locations of Construction
This document applies to the offshore construction activities at any of the following:
i) Customer’s construction facilities
ii) Subcontractors at the Customer’s construction facilities
iii) Subcontractors at their own facilities or at other remote locations.
4. Review of the Construction Facility
DNV is to familiarize itself with the Customer’s production facilities, management processes, and safety
procedures for consideration in determining the contents and application of Table 5-1. This familiarization
shall take place prior to starting any fabrication or construction. Such familiarization will take place under the
following circumstances:
i) Where DNV has no recent experience at the construction facility (typically after a lapse of one year) or
when a significant new infrastructure to the facility has been added
ii) Where there has been a significant management or personnel restructuring, having an impact on the ship or
offshore construction processes or,
iii) Where the builder contracts to construct a vessel of a different type or substantially different in design.
In order to assess compliance with specified Rules, Standards and Regulations, the Society may require
additional documentation and carry out an assessment of yard’s processes, systems, and personnel related to
the classification projects. The results of the assessment should be used as a basis to decide on the extent of the
involvement of surveyors of the Society. The extent of the Classifications Society’s involvement for the site
survey activities shall be clearly reflected in Table 5-1 in this document.
Where DNV has no recent experience with new building activities at the builder’s construction facility or its
subcontractors and/or when significant new infrastructure has been added, DNV may initiate an MPQA and
evaluate the Customer’s QA/QC-performance and set the initial survey scope on basis of the MPQA rating
methodology.
5. New building Survey Planning
5.1 Kick-off Meeting
Prior to commencement of any new building project, the Customer and DNV are to discuss at a kick-off
meeting the survey activity items listed in Table 5-1. The purpose is to agree how the list of specific activities
shown in the Table is sufficiently comprehensive, to be adjusted, if necessary and to be addressed.
A record of the meeting is to be made, based upon the contents of the Table, (the table can be used as the record
with comments made inserted in the appropriate column). The Customer may be asked to agree to undertake
ad hoc investigations during construction where areas of concern arise. DNV is to be kept informed of the
progress of any investigation. Whenever an investigation is undertaken and, if warranted by the severity of the
problem, the Customer should suspend relevant construction activities until counteractive measures are
satisfactorily implemented, reviewed and accepted by the Society.
5.2 Quality Standards
Construction quality standards for the hull structure, piping, electrical, HVAC and other disciplines during new
building project are to be properly listed in this document, reviewed and agreed during the kick-off meeting.
5.3 Survey Extent
It shall be underscored that the QSP table is not exhaustive, and in cases where the QSP is incomplete and/or
not necessarily covering all survey aspects, it shall be the prerogative of DNV to require such activities/items
added.
The QSP only covers survey activities and does not cover the technical interpretations of the statutory
requirements or approval of plans, designs and manuals required by the Regulations.
DET NORSKE VERITAS AS
Sl. No.
Activity
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
Typical Activities
A. Hull Structure And Hull Outfitting
1.1
1.2
2.1
DET NORSKE VERITAS AS
2.2
2.3
2.4
3.0
3.0
Material Receipt Control
DNV-OS-C401
Material traceability during
production
DNV-OS-C401
Welding
Consumables
DNV-OS-C401
Welder Performance
Qualification
Welding Procedure
Specification (WPS)
DNV-OS-C401
DNV-OS-C401
Post weld heat treatment
(PWHT)
DNV-OS-C401
Welding
Environment
DNV-OS-C401
WPT
Welding Production Test
DNV-OS-C401
Traceability records
Nesting plans, traceability
records
V
R
V
R
V
U
V
R
V
W/R
V
R
V
U
W
W
Procedure for handling of
consumables
Welders’ records
WPS
Heat treatment records
QC report checklist
QC report checklist
— Review files, review of material certificates and
records, Verify that plates and profiles are marked
according to procedure
— Random verification in shop of material
traceability against nesting plan.
— Review of traceability
— Review type approval status,
— Review that storage, handling and treatment are in
accordance with procedure and manufacturers
requirements.
— Verify consumables against type approval
— Verify compliance with procedures in temporary
and permanent storage facilities
— Verify compliance with handling in shops and
outdoor conditions.
— Review of welder certification records
— Verify welder qualifications according to agreed
recognized standards
— Verify welders approval for weld positions
— Verify validity of certificates and required training
— Verify that only WPS approved according to DNV
standard are used for the project.
— Verify that wide gap welding procedures are
qualified on gaps specified by IACS 47
— Verify that reference is given to preheating, incl.
repairs
— Review records for heating, temperature
differences, soaking and cooling in accordance
with approved procedures.
— Verify that fabrication facilities are protected from
adverse weather, e.g. wind, rain, snow, draughts
and kept dry.
— Verify that outdoor areas applying welding with
shielding gases and flux arc are protected
— Verify that fabrication facilities are protected from
adverse weather, e.g. wind, rain, snow, draughts
and kept dry.
— Verify that outdoor areas applying welding with
shielding gases and flux arc are protected
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 7 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
3.1
4.0
4.1
4.2
4.4
Welding and Fabrication
Supervision, production
Edge preparation
(pre-assembly)
(pre-erection)
Fit-up and alignment,
General
(pre-assembly)
(pre-erection)
Reference to Rules
Procedures
(Yard/DNV)
DNV-OS-C401
Quality Records generated
DNV-OS-C401
QC report checklist
DNV-OS-C401
Fabrication records
Extent of
Attendance
Yard
DNV
V
U
W
U/R
W
Cut outs in structural
member s etc
U/R
Fabrication records
Fit-up and alignment,
Special areas
(Survey Category I)
DNV-OS-C401
NDT
DNV-OS-C401
W
U/R
W
U/R
W
U/R
Fabrication records
NDT records
Repair records
Typical Activities
Comments
— Verify that sufficient number of skilled inspectors
are kept during fabrication
— Verify that welding equipment is in good order and
calibrated as per procedure
— Verify that edge preparation is kept within the
agreed standard
— Verify that procedures are in place to compensate
for wide gaps and alignment
— Deviations and that remedial actions have been
taken to counteract with reported nonconformances
— Update as built and get it approved prior to start of
the work
— Verify that the fabrication has been carried out
properly and inspected
— Review that alignment and fit-up have been
checked against Class requirements for special
areas.
— Verify that alignment and fit-up conform with
fabrication records
— Review that NDT extent has been carried out
according to NDT plans and that all repairs have
been tested.
— Review that defect rates are within acceptable
limit.
— Verify that NDT is documented such that the
performed examination is properly duplicated.
— Verify that repaired areas are satisfactorily carried
out and not more that twice unless procedure
available
Cut outs in hull, frames,
girders, columns, braces to
approved prior to any work
being carried out
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 8
DET NORSKE VERITAS AS
4.3
Activity
Sl. No.
4.5
DET NORSKE VERITAS AS
4.6
5.0
Activity
Final block inspection
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
DNV-OS-C401
Fabrication
history records and status
Records design changes and
status
Unscheduled inspection nonconformity records and status
NDT records and status
QCH final records and status
Block erection welding
DNV-OS-C401
(Survey Category II and III) IACS 47
Tightness testing, including
leak and hose testing, hydro
pneumatic testing
DNV-OS-C401
Fabrication
history records and status
Records design changes and
status
Unscheduled inspection nonconformity records and status
NDT records and status
QCH final records and status
Inspection records and test
results
Extent of
Attendance
Yard
DNV
W
U/R
W
U/R
W
W/U
Typical Activities
— Review that blocks are controlled and completed
by production and finally checked by QCH
according to approved drawings agreed fabrication
procedures and standard for workmanship.
— Review tolerance records
— Review that NDT has been completed according to
NDT plans.
— Verify that the general welding and workmanship
standard are maintained
— Verify that scantlings and details are carried out
according to approved drawings.
— Verify that weld surface preparation is kept
according to standard and that specified weld
surface preparation for enhanced fatigue life is
satisfactorily carried out.
— Verify that DNV’s unscheduled records are dealt
with.
— Review that blocks are controlled and completed
by production and finally checked by QCH
according to approved drawings agreed fabrication
procedures and standard for workmanship.
— Review that NDT has been completed according to
NDT plans.
— Prior to inspection review that the Customer has
performed own inspection.
— Review that any specified leak testing in subassembly shops have been witnessed and accepted.
— Review that tightness testing of penetration has
been carried out.
— Review that hose testing has been carried out by
the Customer,
— Verify that all boundaries and interfaces between
blocks subject to tightness testing are covered by
the inspection
— Verify that all subject boundaries and penetrations
are in absent of leaks
— Verify that all boundaries and connections subject
to hose testing are not leaking.
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 9 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
5.1
6.1
6.2
Structural testing
Corrosion Protection
Systems (e.g., coatings,
cathodic protection,
impressed current)
Application of antifouling
systems
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
DNV-OS-C401
Inspection records and test
results
DNV-OSS-101
DNV-OS-C101
DNV-OS-C401
DNV-OS-E101
Coating included in the
SOLAS Reg. II
PSPC: Application of
Protective Coatings for
Dedicated Seawater Ballast
Tanks in all Types of Ships
and the International
Convention for the Control
and Management of Ships’
Ballast Water and Sediments
is applicable to offshore
units (semi submersibles,
floating platforms, FSUs and
FPSOs) as defined in
Articles 1-12 and 3 of the
Convention
Dimensional Measurement
Extent of
Attendance
Yard
DNV
W
W
W
R
W
R
W
U/R
Installation records
Builder's and manufacturer's
records and manufacturer’s
declaration
QC records and
manufacturer’s data sheets,
Approved CTF
QC records
Typical Activities
— Prior to inspection review that the Customer has
performed own inspection.
— Review that correct testing pressures have been
used
— In case the structural test shall be combined with
tightness testing, review that no protective coating
has been applied
— Verify that the structural integrity is maintained
and all boundaries and interfaces between blocks
subject to tightness testing are free from protective
coating and covered by the inspection
— Verify that all subject boundaries and penetrations
are free from leaks
— Review that coating standard has been confirmed
in order by manufacturer and Customer.
— Verify that anodes are provided with appropriate
documentation, and that number and locations as
per approved drawings.
— Verify that impressed current system is installed
and tested
— B600 Corrosion protection systems
— B601 Application of coating, steel surface
preparation with respect to application of coating
and fabrication and installation of sacrificial
anodes and impressed current cathodic protection
systems are not included in DNV’s scope of work
unless upon special agreement.
— Kick off meeting with customer and owner.
— Review and monitoring the implementation of the
coating Verify that applied coatings are approved
Comments
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 10
DET NORSKE VERITAS AS
6.0
Activity
Sl. No.
7.0
8.0
9.0
10.0
11.0
DET NORSKE VERITAS AS
11.1
Activity
Freeboard Mark Inspection
Load Line and Draft Mark
Inspection
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
DNV-OS-C301
QC records
ILLC 1966
In- Water Survey Mark
(BIS)
Bottom Survey Before
Launching
Ship Rules
Inclining Experiment and
Deadweight Measurement
DNV-OS-C301
Watertight integrity of
internal and external
openings
Weather tight integrity
DNV-OS-C301
QC records
QC records
DNV-OS-C301
Extent of
Attendance
Yard
DNV
W
W
W
W
W
W
W
W
W
W
W
W/U
Inclining test report
Installation and testing and
records
Approved drawings
Installation and testing
records
Approved freeboard plan
Typical Activities
— Verify freeboard marks in accordance with load
line assignment
— Verify draft marks in accordance with the agreed
tolerances
— Water tight integrity to be verified, including
openings, attachments etc
— DNV stability surveyor to verify that the inclining
experiment has been carried out according to
approved procedure.
— Verify that watertight integrity is maintained
— Verify that weather tight integrity is maintained
B. Quality Survey Plan Piping Systems
1.0
1.1
Piping fabrication facilities
Welding Procedure
Specification
(WPS)
DNV-OS-D101
DNV-OS-D101
Pipe fabrication records
NDT and testing records
Welders’ record
W
U/R
V
W/R
Procedural coverage records
— Review that pipe fabrication is carried out and
documented according to agreed procedures and
job instructions.
— Review of traceability system and records
— Review records qualification
— Review of testing facilities. Verify by qualified
survey that the pipe fabrication facilities are
generally in good order that piping fabrication is
carried out to good workmanship standard
— Verify receipt control and traceability of materials
during fabrication.
— Review that qualification of personnel is according
to procedure and that welding machines and nondestructive testing facilities are calibrated
— Review that all weld joint types, weld positions
and weld processes, including repairs, are covered
by approved welding procedures according to
agreed qualification method
— Verify that only WPS's approved according to
DNV standard DNV-OS-D101 are used for the
project.(ASTM American Society for Testing
Materials ASME B31.3 ASME Code for Pressure
Piping)
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 11 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
2.0
Activity
Marine Class I Piping
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
DNV-OS-D101
Fabrication Records
Shop pressure testing records
2.2
DNV-OS-D101
Class I Drilling and
Production piping
DNV-OS-E101
and E201
Class II Drilling and
Production piping
2.4
Installation Inspection
2.5
Post Weld Heat Treatment
(PWHT)
Nondestructive Examination
Cleaning & Flushing
(WaterAir Etc.)
2.6
2.7
2.8
Hydro-test (Class I)
2.9
Hydro-test (Class II and III)
DNV-OS-D101
PWHT Procedure
NDE Procedure
Cleaning,
Flushing &
Preservation
Procedure
Hydro Test
Procedure
Hydro Test
Procedure
— Review of fabrication records include NDT
— Review that PWHT if required is carried out and
documented as per procedure. Verify by visual
examination that the fabrication standard is
acceptable.
— Review of fabrication records include NDT
— Review that PWHT is carried out documented as
per procedure
— Review of fabrication records include NDT
— Review that PWHT if required is carried out and
documented as per procedure
— Verify by visual examination that the fabrication
standard is acceptable.
— NB More extensive documentation required for
HP Drill to be furnished by builder
— Review of fabrication records include NDT
— Review that PWHT if required is carried out and
documented as per procedure
— Verify by visual examination that the fabrication
standard is acceptable.
— P & ID walkthrough
U/R
W
U/R
W
U/R
W
U/R
Piping Installation
Check Sheet
PWHT Record
W
U/R
W
R
NDE Report
W
R
W
R
W
W/U/R
— Review Chart Recorder Calibration and Hydro
Test Chart (Record)
W
U/R
— Review Chart Recorder Calibration and Hydro
Test Chart (Record)
Fabrication Records
NDT and PWHT records
Fabrication Records
Shop pressure testing records
NDT and PWHT records
Fabrication Records
Shop pressure testing records
NDT and PWHT records
Piping Installation
Check Sheet
Test Record
Piping Installation
Check Sheet
Test Record
Comments
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 12
DET NORSKE VERITAS AS
2.3
Marine Class Piping
Class II and III
Typical Activities
W
NDT and PWHT records
2.1
Extent of
Attendance
Yard
DNV
Sl. No.
Activity
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
Typical Activities
C. Electrical and Instrumentation Installations
1.0
1.1
DET NORSKE VERITAS AS
1.2
Cable tray and installation
Cable type
Cable Segregation
DNV-OS-D201
DNV-OS-D201
MC check sheet
V
R
V
R
V
U
W
U
W
U
TA certificate
Cable list
Ship Rules Pt.6
Layout drawing
DNV-OS-D201
Layout drawing
— Verify that Cable ladders and trays with their
fixing devices are made of corrosion resistant
steel.(Hot galvanizing or stainless)
— Verify that TA certificate are available. Cables for
services, required to be operable under fire
conditions shall be of fire resistant type complying
with the requirements of IEC 60331-, where they
pass through high fire risk areas.
— Special requirement,
— i.e. Norwegian flag require Halogen free cables in
living quarters.
— Verify cable segregation on an ongoing basis.
1.2 Cable Installation
1.2.1
Generator cables
1.2.2
Emergency generator cables DNV-OS-D201
Layout drawing
1.2.3
Steering gear cables
Layout drawing
DNV-OS-D201
1.2.4
Emergency fire pp cables
SOLAS CH II-2
Layout drawing
1.2.5
Heating cable installation
DNV-OS-D201
1.2.6
Segregation of low and high DNV-OS-D201
voltage cables
Layout drawing
Maker’s instruction
Layout drawing
1.2.7
Segregation of power cables DNV-OS-D201
and cables for control
circuits
Layout drawing
W
U
W
U
W
U
W
U
W
U
— Verify that generator cables shall be divided
between two or more cable runs.(Both for power
and control cables)
— Verify that generator cables are not going through
cofferdams.
— Verify that Power cable inside steering gear room
shall running as wide as possible
— Power cable from ESBD shall not pass through ER
— Control cable from local to bridge shall running
separately.
— Verify that the power cable from ESBD is not
passing through E or other high fire risk area.
— Verify that earth fault circuit breaker is provided.
— Verify that at least 300 mm from each other unless
mechanically separated by earthed metal partitions
or pipes.
— Verify that they are not running in the same bunch
or pipe.
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 13 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
1.2.8
Activity
Single core cables
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
DNV-OS-D201
Layout drawing
Cable Penetrations
DNV-OS-D201
1.2.10
Mechanical protection of
cables
DNV-OS-D201
1.2.11
Cable bends and fixing
DNV-OS-D201
Maker’s instruction
1.2.12
Cable expansion
DNV-OS-D201
Layout drawing
1.2.13
Termination of cables
(High voltage cable)
DNV-OS-D201
Maker’s instruction
1.2.14
Cable entrance
Maker’s instruction
TA certificate
W
U
W
U
W
U
W
U
W
U
W
U
W
U
V
R
V
R
V
R
V
U
W
W
DNV-OS-D201
Typical Activities
— Verify that the phases preferably in a triangular
formation.
— Verify that all phases belonging to the same circuit
are running together in a common bulkhead
penetration (MCT)
— A sampling shall be witnessed under maker’s
instruction.
— Focus on below the floor in engine and cargo hold
area.
— Verify that cable bending is properly considered
during cable ladder installation.
— Installation of expansion shall be agreed with yard
at early stage.
— Termination kits approved or recommended from
the cable manufacturer and made by qualified
people.
— It is recommended that Hi-pot test will be down for
the first cable after termination, if successful then
do others.
— Verify that the size of glands shall match with
cable size.
— Verify that the integrity of the enclosure is not
impaired.
2.0 Main Power supply
2.1
DNV-OS-D201
Test procedure
2.2
System voltages and
frequency
Voltage drop
DNV-OS-D201
Approved calculation
2.3
2.5
Harmonic distortion
Switchboard arrangement
DNV-OS-D201
DNV-OS-D201
Approved calculation
Layout drawing
— Focus on long loops, i.e. lighting loops in offshore
unit.
— Normally caused by powerful frequency converter
— Make sure that No pipes installed above, no dead
end corridors if more than 7m.
— Passage ways for switchboards, and insulation mat
in front of and behind of switch boards.
3.0 Emergency Power supply
3.1
Emergency Generator
protection
— Short circuit protection (Trip ACB)
— Over current protection, only alarm, NOT trip
ACB.
Comments
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 14
DET NORSKE VERITAS AS
1.2.9
Extent of
Attendance
Yard
DNV
Sl. No.
Activity
3.2
Emergency generator used as
harbour generator
Starting arrangements for
emergency generating sets
3.3
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
W
W
W
R/V
Typical Activities
— Same as main generator
D. Fire Detection Systems
1.1
DET NORSKE VERITAS AS
1.2
1.3
1.4
Smoke Detection
SOLAS/ FSS
Code 2001
Test Records
Spare Components Onboard FSS Code 2001
Address Identification
FSS Code 2001
Main and emergency power
supplies and battery charging
failure fault signal
Inventory List
Test Records
Test Records
Test indication of
disconnected loop and fault
signal for earth fault, short
circuit and wire break in
detection loops. Perform
lamp test if applicable
Fire and Smoke Detection
above ceilings in corridors
and stairways
FSS Code 2001
Test Records
1.7
Manual call point Test
function
FSS Code 2001
Test Records
1.8
Audible Alarms
FSS Code 2001
Test Records
1.5
1.6
1.9
Test activation of alarm
W
W
W
W
W
W
W
W
W
W
FSS Code 2001
FSS Code 2001
W
W
W
W
W
W
W
W
Test Records
— Smoke detection is required in all locations where
fire detection is required, except in galleys, saunas
and cold rooms with temperature below 5 °C,
where heat detection is required. Pay special
attention to installations in hazardous areas
— E.g. fire detectors of all types used in the system.
— Switch off main power supply. Observe visual and
audible fault signals and automatic change-over to
emergency source
— Simulate indication of disconnected look and wire
break by disconnection of inputs for selected
loops. Simulate earth fault and short circuit on
input circuits for selected loops.
— Applicable where ceilings and suspension contain
combustible materials, which is allowed for pre
SOLAS 1974 vessels.
— Fire detector Test function of smoke detectors
above ceilings in corridors and stairways
— Test at least one per loop. Verify visual and audible
fire signal in the fire central
— Verify that audible alarm can be heard throughout
the crew accommodation and service spaces,
control stations and machinery spaces of category
A
— If the fire signal at the fire central has not received
attention within two minutes, the fire alarm shall
be activated
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 15 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
Activity
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
Typical Activities
Comments
2.0 Hydrocarbon gas detection system, fixed
2.1
2.2
Gas detector Test function
Examine and test function
SOLAS 2000
Ch.II-2
DNV-OS-D301
Test Records
SOLAS 2000
Ch.IIMODU-code
Test Records
— Test one detector in each loop or area. Use span gas
and verify alarm at a defined percentage of the
lower explosion level (LEL). Oil carriers with keel
laid on or after 2002-07-01 10%, oil carriers with
keel laid before 2002-07-01 30%, gas carriers
30%, offshore units 25% - 60%, other vessels 30%.
— Applicable for all fixed systems on board. Test
audible and visual alarm at a continuously manned
position.
W
W
W
W
W
W
W
W
SOLAS 2000
Ch.II-2 2 and
Ch.VI MODU
Code-
W
W
SOLAS 2000
Ch.II-
W
W
— Verify quantity on board. Normally minimum two
units
W
W
— Verify that the foam concentrate has a valid
certificate or test report
W
W
— Examine all hoses, nozzles and applicators that
hose boxes contain correct coupling spanners for
hydrants and nozzles. Hoses shall be of a nonperishable type. Nozzles shall be of an approved
dual-purpose (spray jet) type incorporating a shut
off
W
W
3.0 Hydrocarbon gas detection system, fixed
3.1
3.3
Quantity
Test Records
— Refer to the manufacturer's instructions
— Verify that calibration and maintenance has been
carried out in accordance with the manufacturer's
recommendations.
— Normally minimum two units
4.0 Oxygen detection, portable unit
4.1
Quantity
5.0 Fire fighting – On board documentation
5.1
Fixed firefighting system
service report
Fixed firefighting system
service report
6.0 Fire water system
6.1
Fire hoses & Fire hose
SOLAS 2000
stations including equipment Ch.II-
7.0 Fire water supply system, main
7.1
Fire water pumping units,
— Perform examination while in running condition
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 16
DET NORSKE VERITAS AS
3.2
Test function as far as
practicable
Calibration
Sl. No.
Activity
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
SOLAS Ch.II-2
Test Records
7.2
Fire water pumping units,
main
7.3
One of the fire pumps is
SOLAS Ch.II-1
supplied from the emergency
source of electric power
Extent of
Attendance
Yard
DNV
Typical Activities
— Verify Operation Test
W
W
W
W
— Verify that one of the fire pumps is supplied from
the emergency source of electric power
ICLL and MODU Test Records
Code- 2001
W
W
— Test operations of valves, check valve position
indicators and check for water on deck
— Verify remote operation of sea suction valve
SOLAS 2000
Ch.II-2
Test Records
W
W
Operation with supply from
the emergency source of
electric power
SOLAS 1996
Ch.II-1
Test Records
W
W
International Shore
Connection
SOLAS 2000
Ch.II-2, MODU
Code
W
W
W
W
Test Records
8.0 Fire water supply system, emergency
8.1
Fire water supply piping,
emergency
9.0 Fire pumping units, emergency
9.1
DET NORSKE VERITAS AS
9.2
9.3
Operation test
— Test primary and secondary starting arrangements.
Verify that pumps installed above the lightest
water line are of self priming type
— Applicable for electrically driven pumps. Verify
that the emergency generator is able to deliver to
the emergency fire pumps simultaneously with
other consumers
— At least one international shore connection shall be
provided, enabling use on both sides of the vessel.
Gasket, 4 bolts, 4 nuts and 8 washers shall be
available
10.0 Fire water distribution system
10.1
Fire hydrants operation test
Test Records
10.2
Fire main pressure test
Test Records
10.3
Fire main - Main nozzle
pressure under main pump
operation
SOLAS 2000
Ch.II-and MODU
Code-
W
W
W
W
Test Records
— Spot check by opening and closing of valves.
— Not applicable for vessels with pressurized
systems. Verify that all hydrants outlets are closed
and that all isolation valves are open. Examine the
fire main whilst under pressure from two pumps
running simultaneously and verify no leakage.
Test function of safety valves, if fitted.
— Verify nozzle pressure at the highest hydrant, with
two hoses connected to the highest hydrants and
two pumps running. Minimum pressures for
vessels with gross tonnage >= 6000 GT 0.27
Nmm2, other vessels 0.25 Nmm2.
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 17 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
Activity
10.4
Fire main - Hose throw under
emergency pump operation
10.5
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Fire main Verify no
MODU Code
connections other than those
necessary for fire-fighting
purposes
Extent of
Attendance
Yard
DNV
W
W
W
W
Typical Activities
Comments
— Perform test with two hoses connected to the
highest hydrants. Verify that both hoses throw 12
m simultaneously.
— Perform test with two hoses connected to the
highest hydrants. Verify that both hoses throw 12
m simultaneously.
11.0 Fire water supply control and monitoring system
11.1
Test Records
Verify local start of main fire SOLAS 2000
pump
Ch.II-2 and
MODU Code-
Test Records
W
W
W
W
— Applicable in case of periodically unattended
machinery space, when only one person is required
on watch, or if dangerous goods is carried, unless a
system permanently pressurized by one of the
main fire pumps is installed.
— Start pumps locally and verify function and
pressure
W
W
— Including pilot bottles, piping, pull pistons, wire
pull etc.
W
W
— Examine connection to the manifold. Bottle rooms
shall contain no storage
W
W
W
W
W
W
W
W
W
W
12.0 Machinery space fixed gas fire fighting system
12.1
Examination Of Release
Mechanism
12.2
Examination of Gas
reservoir condition
12.3
Function Test of Release
Alarm
Function Test
12.4
SOLAS 2000
Ch.II-2 MODU
Code
SOLAS 2000
Ch.II-2 and
MODU CodeFSS Code 2001
SOLAS 2000
Ch.II-2 and
MODU Code-
Test Records
Test Records
— For internal systems, use outlet to deck
13.0 Machinery space fixed local application water spraying fire extinguishing system
13.1
Examination of Type Of
Nozzles
13.2
Pumping unit – Operation
under main power supply
13.3
Test system according to
requirements in type
approval certificate
SOLAS Ch.II-2
Test Records
— The bulb shall be in accordance with approved
plans. Examine for dirt, clogging and mechanical
damage
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 18
DET NORSKE VERITAS AS
11.2
Test remote start of main fire SOLAS 2000
pump
Ch.IIMODU Code
Sl. No.
Activity
13.4
Function Test – as far as
possible
13.5
Sufficient number of spare
sprinkler heads
Reference to Rules
Procedures
Quality Records generated
(Yard/DNV)
SOLAS 2000
Test Records
Ch.II-2
MODU CodeFSS Code 2001
Extent of
Attendance
Yard
DNV
Typical Activities
W
W
— Test manual release, from local and remote
location of operation controls
W
W
— Total no. < 300, 6 spares. Total no. 300 - 1000, 12
spares. Total no. > 1000, 24 spares
W
W
— Test automatic start of pump at pressure drop in
system
W
W
— Visual and audible alarm shall be activated
whenever any sprinkler comes into operation. Test
flow alarm in each section by simulating alarm
condition. Alarm panel shall also include fault
alarm
W
W
W
W
W
W
W
W
— Total no. < 300, 6 spares. Total no. 300 - 1000, 12
spares. Total no. > 1000, 24 spares
W
W
— Use water if possible; if not blow through with air.
Verify that all nozzles are open
W
— Storage tank fuel pumps shall be provided with
means which permit shutdown from a safe remote
location in the event of a fire. Where a gravity-fed
fuelling system is installed, equivalent closing
arrangements shall be provided.
14.0 Accommodation fixed water spraying fire extinguishing system
14.1
Testing automatic start of
pump
FSS Code 2001
Test Records
14.2
Testing flow alarm at control FSS Code 2001
station or bridge
Test Records
DET NORSKE VERITAS AS
14.3
Operation under main and
emergency power supply
14.4
Piping - pressure gauges are FSS Code 2001
fitted
14.5
14.6
FSS Code 2001
System Test in accordance
SOLAS 2000
with TA/manufacturer’s test Ch.II-2
procedure
MODU Code
Sufficient number of spare
sprinkler heads
Test Records
FSS Code 2001
— At each section stop-valve and at a central station.
Glass gauges are not required on pressure tanks for
water mist system
— Test operation of valves. A test valve shall be
provided for each section valve. Test automatic
alarms for each section of sprinklers.
15.0 Drilling area water spraying fire fighting system
15.1
Piping system – Blow
Through Test
FSS Code 2001.
Test Records
16.0 Helicopter deck foam fire extinguishing system
16.1
Helicopter fuel remote
control stop valve Test
function
SOLAS 2000
Ch.II- MODU
Code
Test Records
W
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 19 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
Activity
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
Typical Activities
Comments
17.0 Helicopter fuel storage and distribution arrangement
17.1
Helicopter fuel remote
control stop valve Test
function
SOLAS 2000
Ch.II-2 MODU
code
Test Records
W
W
W
W
— Storage tank fuel pumps shall be provided with
means which permit shutdown from a safe remote
location in the event of a fire. Where a gravity-fed
fuelling system is installed, equivalent closing
arrangements shall be provided.
18.0 Fire extinguishing equipment, mobile
18.1
18.2
18.4
SOLAS 2004
Ch.II-
Fire extinguisher, portable
Verify quantity of spare
charges
SOLAS 2000
Ch.II-2
Fire extinguisher, portable
Verify type, number and
location at helicopter deck
SOLAS 2000
Ch.II-MODU
Code
— As shown on the 'Fire control plan'
— According to the fire control plan, including semi
portable fire extinguishers; 135 l foam in each
boiler room, and 45 l foam in each machinery
space containing combustion engines.
— Spare capacity 100% for the first 10 required
extinguishers and 50% for the remaining. Not
more than 60 spare charges are required. For
extinguishers that cannot be recharged on board,
spare extinguishers shall be provided.
Extinguishers installed in excess of the
requirements can be counted as spares
— At least two dry powder extinguishers having a
total capacity of not less than 45 kg. Carbon
dioxide extinguishers of a total capacity of not less
than 18 kg or equivalent.
W
W
W
W
W
W
SOLAS 2000
Ch.II-2
W
W
SOLAS 2000
Ch.II-2
W
W
— Refer to the 'Fire control plan'. If not shown on the
plan, the plan shall be amended and verified at next
survey
W
W
— Examine cleanliness of filters and quality of air
supply. Start and verify operation.
SOLAS 2000
Ch.II-2
19.0 Emergency escape breathing arrangements
19.1
19.2
Emergency escape breathing
device (EEBD), Verify
number of devices installed
in the accommodation spaces
Emergency escape breathing
device (EEBD), Verify
number of devices installed
in the machinery spaces
— At least two devices plus one spare
20.0 Breathing air supply
20.1
Breathing air compressor
unit Examine condition and
test function
SOLAS 2000
Ch.II
Test Records
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 20
DET NORSKE VERITAS AS
18.3
Fire extinguisher, nonportable wheeled Verify
number and location,
Fire extinguisher, portable
Verify type, number and
location
Sl. No.
Activity
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
Typical Activities
21.0 Fire-fighter's outfit
21.1
21.2
Verification of lifeline
Examine stowage
— One lifeline shall be provided for each required
breathing apparatus. The lifelines shall be
fireproof.
— The outfits shall be stored in widely separated
positions.
SOLAS 2000
Ch.II-2
W
W
SOLAS 2000
Ch.II-2
W
W
W
W
W
W
— Required for Halon and CO2 systems. May also be
arranged for other gas fire extinguishing systems.
W
W
— If arranged. Shut down may be initiated by fire or
gas detection.
W
W
— Fans shall be of certified safe type.
W
W
— Exhaust fans shall be of certified safe type. SS Jan.
2004 Pt.4 Ch.8 Sec.2 I400
22.0 Ventilation systems for machinery spaces
22.1
Verify arrangement
SOLAS 2000
Ch.II-
— Arrangements shall be fitted to permit the release
of smoke in the event of fire. Inlets and outlets
shall be located at least 4.5 m above freeboard deck
23.0 Ventilation control and monitoring system
DET NORSKE VERITAS AS
23.1
Test automatic shutdown of
ventilation in spaces
protected by gas fire
extinguishing systems
SOLAS 1981
Ch.II-2
Test Records
24.0 Ventilation systems for accommodation spaces
24.1
Ventilation systems for
accommodation spaces, fan
units Test automatic
shutdown
MODU code
Test Records
25.0 Ventilation systems for hazardous stores
25.1
Condition examination
MODU Code
26.0 Ventilation systems for battery rooms
26.1
Condition examination
MODU Code
27.0 Ventilation systems for drilling areas
27.1
27.2
27.3
Ventilation systems for
drilling areas, ducting Test
function of fire dampers
MODU code
Ventilation systems for
drilling areas, fan units Test
remote stop
MODU Code-
Test function
MODU Code
Test Records
Test Records
W
W
W
W
W
W
— Perform spot checks. Test local operation and
remote operation if arranged. Test automatic
operation if arranged. Verify open and closed
position indication locally at dampers and
remotely if arranged
— Power ventilation shall be capable of being
stopped from an easily accessible position outside
the space being served.
— Test start and stop
Comments
Recommended Practice DNV-RP-A204, September 2011
Page 21 – 5. New building Survey Planning
Table 5-1 QSP - Survey Activity Items (Continued)
Table 5-1 QSP - Survey Activity Items (Continued)
Sl. No.
Activity
Reference to Rules
Procedures
(Yard/DNV)
Quality Records generated
Extent of
Attendance
Yard
DNV
Typical Activities
Comments
28.0 Emergency shut down safety system
28.1
Test selective shut down of
ventilation and ignition
sources
MODU and
DNV-OS-A101
28.2
Verify Ex-protection of live
equipment after shut down
MODU Code and
DNV-OS-A101
28.3
Verify operability of
emergency systems after
emergency shut down
Vessel operation
manual, MODU
Ch.6.5 and
DNV-OS-A101
Test Records
W
W
W
W
W
W
Test Records
E. HVAC and Other Similar Systems Should be added using the examples above
1.0 Testing and Commissioning
1.0
Survey Category I Systems
DNV-OS-D101 & Testing and Commissioning
DS-OS-E101
Records
W
W
1.2
Survey Category II Systems DNV-OS-D101 & Testing and Commissioning
DS-OS-E101
Records
W
U/R
1.3
Survey Category III Systems DNV-OS-D101 & Testing and Commissioning
DS-OS-E101
Records
W
U/R
— Verify that all class and statutory related testing
and commissioning is carried out satisfactorily
— Verify that all class and statutory related testing
and commissioning is carried out satisfactorily
— Verify that all class and statutory related testing
and commissioning is carried out satisfactorily
Recommended Practice DNV-RP-A204, September 2011
5. New building Survey Planning – Page 22
DET NORSKE VERITAS AS
— Shut down shall be possible from at least two
strategic locations outside hazardous areas.
Selectivity shall at least cover: 1. Ventilation,
except combustion air. 2. Main electric power. 3.
Emergency electric power.
— Equipment located outside enclosed spaces shall
be suitable for zone 2
— At least emergency lighting required for escape
and disembarkation, blow-out preventer control
system, general alarm system, public address
system and battery-supplied radio communication
installations
Recommended Practice DNV-RP-A204, September 2011
Page 23 – APPENDIX A Categorization of Systems for Testing and Commissioning
APPENDIX A
CATEGORIZATION OF SYSTEMS FOR
TESTING AND COMMISSIONING
Table A-1
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Category 1 Systems for Commissioning (for Integration)
Name of the System
Fire Main System
Inergen System
Fire Water Deluge System
Main Diesel Generator
Sea Water Cooling System
Thruster S.W. Cooling System
Thruster
11Kv Switchboard
690V HPU MCC
690V Drilling VFD Switchboard
690V Thruster VFD Switchboard
230V AC UPS
230V AC UPS Battery
230V AC UPS Main Distribution Board
230 AC UPS DB
ICMS, Fire And Gas, ESD & DP
With Sensor And Reference System
Telecom System
Column And Pontoon Machinery Rooms Ventilation Systems
Electrical And Auxiliary Machinery Rooms Ventilation Systems
Engine Rooms Ventilation Systems
Port/Stbd/Aft Machinery Rooms Ventilation Systems
LQ HVAC
Power Management System
Dynamic Positioning System Test (DPS)
Machinery Unmanned Test
Table A-2
No.
1
2
3
4
Category II Systems for Commissioning (for Integration)
Name of the System
Ballast System
Aux. Cooling F.W. System
460V LV Switchboard
230V LV Switchboard
Table A-3
No.
1
2
3
4
5
6
7
8
9
10
11
Category I Systems for Commissioning (as independent systems)
Name of the System
Lifeboat & Launch System
Mob Boat Launch Device System
Column Room Lift
emergency bilge system
Emergency Shut Off System (Quick closing valves)
Drill Floor Elevator
Escape Chute
230V AC UPS
230V AC UPS Battery
230V AC UPS Main Distribution Board
230 AC UPS DB
DET NORSKE VERITAS AS
Integrated with
F&G/Deluge/control
F&G/HVAC/PA
F&G
PMS&S/T&DP
Consumer Capacity Test
S/T
S/T
PMS
SIT
SIT
DP/PMS
ESD
ESD
ESD
ESD
ESD/HVAC
ESD
ESD
ESD
ESD
ESD
ESD
DRILL/DP
CONTROL
E0
Integrated with
Semi Recovery Test
S/T & SIT
S/T
S/T
Recommended Practice DNV-RP-A204, September 2011
APPENDIX A Categorization of Systems for Testing and Commissioning – Page 24
Table A-3
No.
12
13
14
15
Category I Systems for Commissioning (as independent systems) (Continued)
Name of the System
Water Tight Door
Helideck Fire-Fighting System
Inclining Experiment & Light Weight Measurement Procedure
Dynamic Positioning System Test (DPS)
Table A-4
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
Category II Systems for Commissioning (as independent systems)
Name of the System
Misc.Lifesaving Equipment
Helicopter Refueling System
Ballast System
Dirty Drain System
Fire Main System
Inergen System
Fire Water Deluge System
Main Diesel Generator
Steam Generating System
Sea Water Cooling System
Starting Air System For Main Engine
Thruster S.W. Cooling System
Sewage & Gray Water Discharge System
Anchor Winches
Thruster
Bilge System
Diesel Gen. F.W Cooling System
11Kv Switchboard
690V HPU MCC
690V Drilling VFD Switchboard
690V Thruster VFD Switchboard
Nav. And Signal Light
U-Light And Foghorn
Obstruction Light
Remote Sounding System
ICMS, Fire And Gas, ESD & DP With Sensor And Reference System
Telecom System
HPU For V/V Operation
Ram Rig Travelling Yokes Main/Aux.
Tong Lift System
LIR / HVAC Room, HVAC
DDM-1000-HY-RR/DDM-650-HY-RR
Rotary Table Main/Aux.(Including Power Slips)
DAT System
Guideline Winch & Tensioner System
LP/HP Nitrogen System
Mud Bucket
Bulk Powder Handling System
Mud Storage And Transfer System
Mud Mixing And Additive System
Mud Supply System
Mud Return And Treatment System
Pontoon Mud, Brine, Oil Storage & Transfer System System
BOP Package
Diverter Package
Tubular and Riser Feeding Machine/Shuttle, Main Rig
DET NORSKE VERITAS AS
Recommended Practice DNV-RP-A204, September 2011
Page 25 – APPENDIX A Categorization of Systems for Testing and Commissioning
Table A-4
No.
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
Category II Systems for Commissioning (as independent systems) (Continued)
Name of the System
Lower Guiding Arm including Heads and Rail, Main/Aux
Trolley For Riser Guiding
Riser Chute
DP/DC, Casing & Riser Fingerboard
Direct Lift Bridge Crane DP/DC/CSG, Main Rig/Aux. Rig
Hydraulic Roughneck MH 1899
Multi Scope Arm (Casing Modem)
Hydraulic Cathead, Brake Out, including Wire
Tail in Arm
Multi Manipulator Arm (DFMA)
Piperack Gantry Crane
Riser Handling Crane (w/ Rail)
BOP Skid/X-Mas/ LMRP Transportation/Handling
Miscellaneous Guides
Access Basket
BOP Overhead Crane/X-mas Tree Overhead Crane
Underhull Guiding Main/Aux.
Overhull Guiding
Utility Winch & Manrider Winch
Burner Boom
Ringline HPU And Distribution System
Ramrig HPU And Distribution System
Dual Derrick Simultaneous Operation
Integrated BOP & Riser Handling System
Integrated Drill String Test (Simulated Spud-in Mode)
LQ HVAC
Power Management System
Navigation Equipment
Machinery Unmanned Test
Anchor Test
PA Coverage Measurement
Table A-5
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Category III Systems for Commissioning (as independent system)
Name of the System
Monorail System
Air Winches & Towing Equipment
Drill Water System
Deck Bilge System
Service Air System
Steam & Drain System
Seawater Service System
Aux. Cooling F.W. System
Diesel Oil Transfer & Drain System
Lub. Oil Storage, Transfer & Drain System
Distilled & Make-Up Water System
Potable & Sanitary Supply System
Cold Starter Generator
MGPS (Marine Growth)
Heat Trace System
460V LV Switchboard
230V LV Switchboard
Small Power DB
DET NORSKE VERITAS AS
Recommended Practice DNV-RP-A204, September 2011
APPENDIX A Categorization of Systems for Testing and Commissioning – Page 26
Table A-5
No.
19
20
21
22
23
24
25
26
27
28
29
30
31
Category III Systems for Commissioning (as independent system) (Continued)
Name of the System
Lighting And Small Power
Shore Connection Box
Column And Pontoon Machinery Rooms Ventilation Systems
Electrical And Auxiliary Machinery Rooms Ventilation Systems
Engine Rooms Ventilation Systems
Port/Stbd/Aft Machinery Rooms Ventilation Systems
HVAC Duck Air Leak Test Procedure for Hull & Topside
ICCP
Pneumatically Operated Door
Provision Cold Store & Freezer System
Noise Level Measurement
Vibration Level Measurement
Helideck Drains
Table A-6 Category I Systems for Commissioning (CRANE)
No.
Name of the System
1
Deck Crane
Note:
1) New Technology and Applications including Changes to Approved Design: Applications of new technology and
non-traditional applications of existing technology shall be approved by DNV. Any changes to design that is
already approved by DNV shall be submitted to DNV for re-approval e.g., scaling up equipment/design, etc. In
most cases, such changes will be treated as Survey Category 1 for follow up during construction, mechanical
completion, testing and commissioning.
2) Additional systems based on the choice of additional class notations should be added in addition to the above.
---e-n-d---of---N-o-t-e---
DET NORSKE VERITAS AS