Mattole Road Bridge (No. 4C-55) Over Mattole River at Honeydew Bridge Type Selection Study Prepared for County of Humboldt Department of Public Works Prepared By MORRISON STRUCTURES, INC. 1890 Park Marina Dr., Ste 104 Redding, California 96001 January 2013 BRIDGE TYPE SELECTION STUDY SUMMARY Based on conditions at the bridge replacement site, analysis of viable bridge types, and our experience with similar projects, there are three viable alternative bridge types for the Mattole Road Bridge over the Mattole River at Honeydew. The three alternatives are: 1. Two-span steel Camelback through truss 2. Two-span composite welded steel girder 3. Two-span precast, prestressed concrete spliced girder Based on preliminary cost comparisons for these alternative bridge types, the Alternative 3, two-span precast, prestressed concrete spliced girder bridge is the most economical The estimated construction cost for this alternative is $4,499,000. The estimated construction cost for bridge type Alternatives 1, and 2 are $5,737,000, and $5,609,000 respectively. INTRODUCTION The purpose of this study was to determine the most suitable bridge type for crossing the Mattole River on Mattole Road at Honeydew in Humboldt County. The steps taken to achieve this goal were as follows: Determine the selection criteria based on conditions at the Mattole River site (geometric constraints, etc.). Select suitable bridge types through a fatal flaw analysis. Prepare preliminary cost estimates for selected bridge types for economic comparison. Prepare a report outlining the work and summarizing the findings. PROJECT DESCRIPTION The Mattole River Bridge (Honeydew Bridge No. 4C-55) on Mattole Road crosses the river at Honeydew north of the junction with Wilder Ridge Road. The bridge is posted for 15 miles-per-hour and a vertical clearance of 14 feet. Built in 1920, the existing bridge is a single-lane, two-span, 386-foot-long structure consisting of two 190-foot-long riveted steel Camelback truss spans. The existing deck, curbs, and rails are timber plank and the clear roadway width is less than 15 feet. As-built plans indicate both abutments and the pier are founded on spread footings. The structure is structurally deficient and functionally obsolete. The bridge is MORRISON STRUCTURES, INC. R136rep.001 1 January 2013 eligible for listing in the National Historic Register under Criterion C as an excellent example of its type, period, and method of construction as a rare and significant bridge type, the Camelback truss. Approach Roadways are two lane with minimum 2 foot gravel shoulders on each end of the existing bridge. Horizontal curved alignments at each end limit speeds to 25 miles per hour. Estimated average daily traffic on Mattole Road is 250 vehicles. The north approach is on a horizontal curve and fairly steep climbing grade leading away from the bridge. Burrell Road intersects Mattole Road from the west, only a few feet north of the existing bridge and a design exception for shortened length metal beam guardrail will be required. County right-of-way varies from 50 feet to 45 feet centered on the roadway. The south approach is on sharp curved horizontal alignment, bounded on each side by fairly level ground. Wilder Ridge Road intersects Mattole Road about 100 feet south of the bridge. A residence and driveway are located to the east of the roadway. A shortened metal beam guardrail will be necessary along the east edge of the roadway to avoid existing trees. The Honeydew Post Office and Store parking, and fuel facilities are located just west of the bridge. Shortened metal beam guardrail adjacent to the Store parking may be necessary and the roadway cannot be raised significantly without impacting the use and access to the property. Utility poles are located along the south edge of the roadway intersection, and likely will not be impacted by the project. County right-of-way narrows to 40 feet at the south span and approach of the bridge. County supplied mapping indicates the existing bridge deck is at about Elevation 347.0. The as-built plans indicate the superstructure depth is about 3 feet 9 inches from the top of the deck to the bottom of the steel truss chords, placing the soffit at about Elevation 343.25. Existing condition hydraulic analysis prepared by Pacific Hydrologic indicates that the water surface elevations for the design floods (50- and 100-year) are 332.0 and 333.0, respectively. For the purpose of this study we have assumed the minimum bridge soffit elevation will be 335.0 to provide 3 feet of freeboard above the 50-year flood water elevation at the crossing. Review of historical river bed elevations at the site indicate that the river bed has raised nearly 20 feet in the main channel since the existing bridge was constructed due to deposits of alluvium. It appears also that the recorded elevation of high water during the 1964 Flood for the bridge site now matches the current estimates of high water elevation for a 5-year flood. The proposed bridge will be a multi-span structure on existing alignment, supported on pier walls and cantilever abutments with an overall length of approximately 375 feet. The proposed vertical alignment is a declining grade with only a slight overall increase in profile grade elevation compared to existing in order to minimize impact to the south approach intersection at Honeydew. Clear roadway width on the bridge will be 26 feet (two 12-foot travel lanes with 2-foot shoulders) between Type 117 metal tube bridge railings. Construction funding is to be provided by Humboldt County and the Federal Highway Administration under the Highway Bridge Replacement and Rehabilitation (HBRR) program. MORRISON STRUCTURES, INC. R136rep.001 2 January 2013 Based on the preliminary findings of the geotechnical exploration at the bridge replacement site, a layer of fractured, weathered, decomposed rock was encountered at depth at anticipated pier and abutment locations. For the purpose of economic comparison, it was assumed that foundations would consist of driven piles at the north abutment and cast-in-drilled-hole piles at the south abutment and piers. Other aspects of the project will include a temporary detour crossing the Mattole River, removal of the existing bridge, construction of approximately 600 lineal feet of roadway approach, and installation of rock slope protection. Estimated construction costs for the detour, existing bridge removal, approach roadway alignments, guard railing, and rock slope protection were not included in the economic comparison. Due to the short time frame allowed for construction (June to October 15), work in the channel will likely be required to be conducted over two seasons. The first season phase of work would be to construct deep foundations and support walls required for new piers and south abutment. The second season phase of work would be to construct the detour, dismantle and remove the old bridge and construct new pier walls, abutments, superstructure, and approaches. BRIDGE TYPE SELECTION SELECTION CRITERIA The initial step in the bridge type selection process was to determine the criteria appropriate for the Mattole River Bridge site. The following criteria were used in the type selection process: Feasibility of falsework Environmental Issues Configuration (span lengths, number of substructure supports, and superstructure depth) Hydraulic efficiency and clearance over high flows Durability and Maintenance Most economical construction Falsework and Environmental Issues For the Mattole River Bridge site, falsework and temporary support bents are considered feasible for removal of the existing bridge and for construction of the new bridge superstructure. Falsework that is necessary in the water will likely be provided by driven piles that will be removed at completion of superstructure construction. For falsework on dry gravel bars and river bank, steel and timber trestles on timber crib footings can be utilized. Environmental constraints will limit the time period when piles can be installed and/or removed, but once piles are in place, work above the water is typically allowed by permit, provided the work does not involve additional channel disturbance. Similarly, time MORRISON STRUCTURES, INC. R136rep.001 3 January 2013 constraints may be placed on installing and removing cofferdams for foundation construction, but once the cofferdam is closed off from the live channel, work is typically allowed to proceed within the enclosure, provided dewatering operations deposit the water into a temporary sedimentation basin prior to discharge back into the stream. An area of the overbank should be designated for the anticipated sediment basin and the contractor’s staging area. If the cofferdam work and substructure can be completed during the low flow months, the sedimentation basin can typically be located in a nearby area of the dry gravel flood plain portion of stream channel. In addition to falsework, gravel pads pushed out from the stream bank and a temporary pile-supported work bridge is anticipated for driving falsework and temporary bent piles, constructing the falsework over the main (low flow) stream channel, removing the existing bridge, and constructing the new bridge. Access to the gravel pads and/or work bridge will be from the south stream bank and gravel bar floodway area. The work bridge will be supported by temporary driven piles and will be removed at completion of the superstructure. FATAL FLAW ANALYSIS The following alternative bridge types were considered as potential candidates for the Mattole River Bridge site: 1. 2. 3. 4. 5. 6. 7. Two-span steel Camelback through truss Two-span composite welded steel girder Two-span precast/prestressed concrete spliced girder Three-span composite welded steel girder Two-span steel tied arch Two-span prestressed, cast-in-place concrete box girder Two-span conventionally reinforced concrete box girder Based on a fatal flaw analysis, two of the above alternative bridge types were eliminated from further consideration. Given environmental constraints Alternatives 6 and 7 were eliminated due to the excessive time required to construct the bridge. Therefore, only alternatives 1 through 5 were selected for economic comparison. ECONOMIC COMPARISON OF ALTERNATIVE BRIDGE TYPES The economic comparison of the remaining alternative bridge types included determining the configuration and superstructure depth and hydraulic efficiency. The economic comparison addressed only the estimated cost of the superstructure and substructure. For bridge type alternatives 1, 2, 3, and 5, the bridge configuration considered in the economic comparison was a two-span configuration with equal span lengths, and an overall total bridge length of 375 feet. For bridge type alternative 4, the bridge configuration considered in the economic comparison was a three-span configuration with an overall total bridge length of 375 feet. The two-span configuration minimizes the number of obstructions in the channel, increasing passage of flood debris and hydraulic conveyance, while a three span configuration minimizes the superstructure depth. MORRISON STRUCTURES, INC. R136rep.001 4 January 2013 Additionally, each alternative selected for comparison can be constructed in the available length of construction season. Unit prices used in the economic comparison were estimated based on review of construction cost data in District 1 and throughout the State, and our experience with similar projects. Unit prices used for the different bridge types were consistent throughout the economic comparison. Presented below in Table 1 is a summary of preliminary cost comparisons for the bridge configurations considered. Table 1 Summary of Substructure and Superstructure Costs Bridge Type Configuration Superstructure Minimum Hydraulic Depth Clearance Alternative No. 1 10.96 feet at the south 43 inches Two-span, Steel Camelback abutment Through Truss Alternative No. 2 125 inches at Two-span, Composite 5.07 feet at the pier pier and varies Welded Steel Girder Alternative No. 3 Two-span, Precast- 118 inches and 5.66 feet at the pier Prestressed Concrete Spliced varies Girder Alternative No. 4 92 inches at pier Three-span, Composite 7.38 feet at Pier 3 and varies Welded Steel Girder Alternative No. 5 10.46 feet at the south Two-span, Steel Tied Arch 49 inches abutment Comparative Cost $5,737,000 $5,609,000 $4,499,000 $5,609,000 $7,024,000 As shown in Table 1, the estimated comparative cost for the steel tied arch alternative is significantly higher than that for the steel Camelback through truss, the plate girders, or the precast concrete girder. Therefore, no further consideration will be given to the steel tied arch alternative. The steel Camelback through truss has a thin structure depth that will provide at least 4 more feet of freeboard than any of the girder type alternatives, while maintaining a twospan configuration for hydraulic conveyance, and is therefore the most desirable alternative for the passage of flood debris. Also, the steel Camelback truss alternative is the same truss type and span configuration, and has similar overall length to the existing bridge, which will minimize the impact to aesthetic setting and historic character at the site. MORRISON STRUCTURES, INC. R136rep.001 5 January 2013 The precast-prestressed concrete spliced girder will provide the most economical option, but will also affect the aesthetic setting and historic character at the site. The 2-span steel girder option is less economical than the precast-prestressed concrete spliced girder but may be constructed in about 4 less weeks. The 3-span steel girder option is similar in cost but requires a support to be located in the main low flow channel and therefore will not be considered further. In summary, Alternatives 1 through 3 are each viable options for Mattole Road Bridge over the Mattole River at Honeydew.. Cost comparisons were prepared based on our experience and judgment and on current available data. Morrison Structures, Inc. has no control over future changes, competitive bidding procedures, market conditions, and other factors affecting cost. The final bridge configuration and actual construction cost may vary. MORRISON STRUCTURES, INC. R136rep.001 6 January 2013
© Copyright 2026 Paperzz