FACT SHEETS

Januar 2014
Center for Økonomi
Budget og Byggestyring
FACT SHEETS
FOR LARGE-SCALE HOSPITAL CONSTRUCTION
PROJEKTS IN THE CAPITAL REGION OF DENMARK
The following pages contain fact sheets about each of the large-scale
hospital construction projects in the Capital Region of Denmark. The
fact sheets provide an up-to-the-minute account of each building
project, but the dates specified are approximate and subject to
change.
Further details about the construction projects are available by
contacting Birgitte Leolnar, Head of Section , tel. +45 2917 6362, email [email protected].
FACT SHEET
THE NEW RIGSHOSPITAL
Geographic location
Blegdamsvej 9
DK-2100 Copenhagen Ø
Construction plots

North Wing on the corner of the cadastral plot
facing Blegdamsvej and Frederik V’s Vej.

Patients’ hotel and administration next to the
Rockefeller Complex facing Amorparken

Multi-storey car park on the corner of the
cadastral plot at Frederik V’s Vej and Edel
Sauntes Allé.
No. of square metres
North Wing: approx. 54,700 m²
Patients’ hotel and administration: approx. 8,000
m²
Total capacity, approx. 62,700 m²
Upcoming procedures
Prequalification for the North Wing will take place
from late January 2014.
Contents
The North Wing will contain beds, operating
theatres and auxiliary functions for the
Neuroscience Centre and the Centre of Head and
Orthopaedics, as well as outpatient functions for
the Centre of Head Orthopaedics.
The building at the Rockefeller Complex will
house a patients’ hotel with 75 beds, and
Righospitalet’s administration department.
The multi-storey car park will contain about 665
parking spaces and will be constructed to make it
2
possible to subsequently enlarge the facility to
house a total of 1,000 parking spaces.
Total financial framework
(2013 prices)
Consultants
DKK 1.975 billion (EUR 0.26 billion)
Client consultant: Niras A/S
Main consultant: aarhus arkitekterne A/S
Sub-consultants: 3XN, Nickl & Partner, Grontmij
and Arkitekt Kristine Jensens Tegnestue
General schedule
Construction start-up, North Wing: autumn of
2014
Commissioning, North Wing: mid-2018
3
FACT SHEET
STERILISATION UNIT
RIGSHOSPITALET
Geographic location
Blegdamsvej 9
DK-2100 Copenhagen Ø
Construction plots
Next to multi-storey car park on the corner of
Frederik V’s Vej and Edel Sauntes Allé.
No. of square metres
Approx. 12,000 m²
Upcoming procedures
Invitation to tender for construction works: April
2015
Invitation to tender for equipment and furnishings:
October 2014
Contents
The regional Sterilisation Unit will be established
with a complete goods terminal and will be
dimensioned with the capacity to meet roughly
half of the region’s needs.
Total financial framework
(2013 prices)
Consultants
DKK 503 million (EUR 67.43 million)
Main consultant: Alectia A/S
Sub-consultants: Arkitektfirmaet C.F. Møller and
the Danish Technological Institute
General schedule
Construction start-up: August 2015
Commissioning: January 2017
4
FACT SHEET
NEW HOSPITAL HERLEV
Geographic location
Herlev Ringvej 75
DK-2730 Herlev
Construction plots

New building south of the existing hospital
buildings.

New parking spaces in the southern part of the
hospital area.

Enlargement of the service building and
hospital chapel north-west of the existing
hospital buildings, upgrading of the central
technical and supply facility and purchasing of
medical technology, IT and inventory.
No. of square metres
New building: approx. 53,000 m²
Enlargement of service building and hospital
chapel: approx. 6,300 m²
Upcoming procedures
Invitation to tender for infrastructure works pushed
forward: January 2014
Invitation to tender for the construction of the new
building (accident & emergency department;
women, child and reproduction building; etc.)
October 2014
Contents
The new building will house the accident &
emergency department, a women, children and
reproduction building, cardiology, etc.
A total of 900 new parking spaces will be
established, 500 of which in a multi-storey car park
and 400 in an outdoor ground-level car park.
Total financial framework
(2013 prices)
DKK 2.402 billion (EUR 0.32 billion)
5
Consultants
New building (accident & emergency department,
etc.)
Client consultants: Niras A/S and aarhus
arkitekterne A/S
Main consultants: Henning Larsen Architects A/S,
Friis og Moltke A/S, Orbicon A/S, NNE Pharmaplan
A/S and Norconsult A/S
Sub-consultants: Bruunsgaard & Lauersen Aps and
SLA A/S
Service building, etc.
Client consultant: Niras A/S
Main consultant: Alectia A/S
Sub-consultant: C.F. Møller
General schedule
Works pushed forward (including the establishment
of a construction site and new entrance and exit
conditions: 2013–2014
Construction start-up: 2015
Commissioning: 2018
6
FACT SHEET
STERILISATION UNIT HERLEV
Geographic location
Herlev Ringvej 75
DK-2730 Herlev
Construction plots
North-west section of the cadastral plot, connected
to the service building
No. of square metres
Approx. 12,000 m²
Upcoming procedure
Invitation to tender and tendering procedure: June–
September 2015
Contents
The regional Sterilisation Unit will be established
with a complete goods terminal and will be
dimensioned with the capacity to meet roughly half
of the region’s needs.
Total financial framework
(2013 prices)
DKK 483 million (EUR 64.74 million)
Consultants
The invitation to tender for the construction contract
is in process.
General schedule
Construction start-up: September 2015
Commissioning: Early 2018
7
FACT SHEET
NEW HOSPITAL HVIDOVRE
Geographic location
Kettegård Allé 30
DK-2650 Hvidovre
Construction plots
Construction of new building west of the existing
hospital complex.
Rebuilding of the existing hospital.
No. of square metres
New construction: approx. 30,560 m²
Rebuilding: approx. 24,000 m²
Upcoming procedures
Invitation to tender for the construction contract,
rebuilding: continuous from late 2014 until mid2018.
Invitation to tender for the construction contract,
new construction: early to mid-2016.
Contents
The new construction project comprises the
establishment of a new accident and emergency
department, on-call GP, paediatric department
(bed ward and outpatient department), neonatal
department, cardiology department (bed ward and
outpatient department), obstetrics department,
new main entrance and other functions, including
offices and enlargement of existing underground
car park adding 325 parking spaces.
The rebuilding comprises the renovation and
enlargement of outpatient departments for all
major clinical specialities: gastrointestinal surgery
and medicine, orthopaedic surgery, gynaecology,
obstetrics and infectious diseases, establishment
of a new oncology outpatient department, and the
rebuilding of 320 four-bed rooms into single-bed
8
and two-bed rooms.
Total financial framework
(2013 prices)
Consultants
DKK 1.548 billion (EUR 0.21 billion)
Client consultant: Cowi A/S
Main consultants: aarhus arkitekterne and schmidt
hammer lassen architects
Sub-consultants: Royal Haskoning DHV, Krag &
Berglund Landskabsarkitektur & Urban Design as
well as Søren Jensen Rådgivende Ingeniører A/S.
General schedule
Construction start-up: 2016
Commissioning: 2019–2021
9
FACT SHEET
NEW MENTAL HEALTH CENTER SCT.
HANS
Geographic location
Boserupvej 2
DK-4000 Roskilde
Construction plots
The west section of Mental Health Centre Sct.
Hans East.
No. of square metres
25,000 m²
Upcoming procedure
Invitation to tender for the construction contract,
new construction: early to mid-2016.
Contents
This construction project comprises 126 forensic
psychiatric bed units with associated auxiliary
functions, technical facilities, staff facilities, offices,
arrival area, visiting facilities, as well as indoor and
outdoor activity areas.
Total financial framework
(2013 prices)
Consultants
DKK 587 million (EUR 78.68 million)
Client consultant: Niras A/S
Main consultant: KHR arkitekter A/S
Sub-consultants: Rubow Arkitekter A/S, Oluf
Jørgensen A/S Rådgivende Ingeniører,
Spangenberg & Madsen Rådgivende Ingeniører
A/S, WSP UK Ltd. and Opland Aps
Landskabsarkitekter
General schedule
Preparatory works: 2015
Construction start-up: mid-2016
Commissioning: early 2019
10
FACT SHEET
NEW HOSPITAL NORDSJÆLLAND
Geographic location
Overdrevsvejen
DK-3400 Hillerød
Construction plots
A brand-new hospital will be built in a new
greenfield urban-development area and will have
its own station in the future.
No. of square metres
124,000 m²
Upcoming procedures
The invitation to tender for the construction
contract is expected in 2016–2017.
Contents
The hospital is intended to house functions
currently found at the hospital grounds in Hillerød
and Frederikssund, including accident and
emergency department; the women-and-children
specialist medicine areas of obstetrics,
gynaecology and paediatric departments; surgery;
orthopaedic surgery; ear, nose and throat
department; ophthalmology department (outpost);
cardiology; nephrology; endocrinology; pulmonary
medicine; infectious diseases; neurology;
rheumatology; and oncology, as well as a unit for
dementia and palliative care. In addition, the
hospital is intended to house interdisciplinary
clinical departments, image diagnostics and
laboratories.
The hospital is expected to house a total of 24
medical specialities and around 660 beds.
Total financial framework
(2013 prices)
Consultants
DKK 4.057 billion (EUR 0.54 billion)
General schedule
Expected construction start-up: 2017
Client consultant: Cowi A/S
Commissioning: 2020
11
FACT SHEET
NEW HOSPITAL AND MENTAL HEALTH
BISPEBJERG
Geographic location
Bispebjerg Bakke 23
DK-2400 Copenhagen N.
Construction plots

North section of the cadastral plot (including the
Lersø Complex): new psychiatric building
project, as well as joint outpatient departments
for psychiatry and somatic medicine

North-west section of the cadastral plot: new
somatic medicine hospital, laboratory and
logistics buildings, as well as multi-storey car
park.
No. of square metres
Construction of new somatic medicine building
(88,000 m²) and rebuilding (64,000 m²). The
rebuilding comprises both listed pavilions and the
Lersø Complex.
Construction of new psychiatric building (27,000
m²) and rebuilding of the Lersø Complex (25,000
m²).
Upcoming procedures
Invitation to tender for construction contract,
laboratory and logistics building: Q3 2014.
Construction of new somatic medicine building
Invitation to tender for consultancy contract (project
competition), somatic medicine: prequalification will
begin in early 2014.
Invitation to tender for construction contract,
somatic medicine: mid-2017.
Construction of new psychiatric building
Invitation to tender for consultancy contract (project
competition), psychiatry: prequalification begins in
mid-2014.
12
Invitation to tender for construction contract,
psychiatry: Q3 2017.
Rebuilding of listed pavilions
Invitation to tender for main consultancy contract
concerning refurbishment of listed pavilions: mid2015.
Invitation to tender for construction contract, listed
pavilions: early 2017
Rebuilding of the Lersø Complex
Invitation to tender for consultancy contract
concerning the Lersø Complex: mid-2019.
Invitation to tender for construction contract, Lersø
Complex: late 2020.
Contents
The Copenhagen Psychiatry Centre will be
gathered in the northernmost section of the
cadastral plot. The buildings in this section of the
area also contain child-and-adolescent psychiatric
functions.
A number of outpatient departments across
psychiatry and somatic medicine will be gathered in
the Lersø Complex with a shared entrance and
foyer functions. The building will house the somatic
medicine departments in the areas of clinical
physiology and nuclear medicine, mammography,
pulmonary medicine and bronchoscopy and
neurology.
The somatic medicine building will house the new
accident and emergency department with
ambulance receiving area, surgery ward with
recovery, intensive care unit, emergency and
outpatient x-rays, as well as all the bed units for all
specialist medicines with the exception of palliative
care, venereology and dermatology.
The laboratory and logistics building is intended to
supply both the somatic medicine and psychiatry
departments. In addition a clinical biochemical
laboratory and shared research facilities will be
placed in the building.
Also, 1,100 parking spaces will be established at
the cadastral plot in a multi-storey car park, an
underground car park and on an outdoor groundlevel car park.
Total financial framework
(2013 prices)
DKK 4.249 billion (EUR 0.57 billion)
Consultants
Main client consultant: Emcon with KPMG
Client consultant, somatic medicine hospital: Drees
& Sommer Nordic with Sub-consultants
Munksgaard plus Andersen, EKJ Ingeniører and
13
Sweco Arkitekter.
Client consultant, psychiatry: Moe A/S, with Subconsultants Bruunsgaard Laursen Aps and Mtre
Aps
Client consultant, laboratory and logistics building:
Kuben Management, with Sub-consultants Balslev
and Arkitema
Client consultant, multi-storey car park: Bascon
Client consultant, shared construction site: Drees &
Sommer Nordic
Main consultant, laboratory and logistics building:
Mikkelsen Arkitekter A/S, WHR Architects Europe
and Ove Arup & Partners International Ltd.
General schedule
Construction start-up, multi-storey car park: late
2014
Construction start-up, somatic medicine building:
2nd half of 2017
Construction start-up, psychiatry: 2nd half of 2017
Construction start-up, laboratory and logistics
building: Q4 2014
Commissioning: occupation in stages, in the period
2015–2025.
14
FACT SHEET
NEW HOSPITAL GLOSTRUP
Geographic location
Nordre Ringvej 57
DK-2600 Glostrup
Construction plots

Neurorehabilitation building in the south-west
section of the cadastral plot

Multi-storey car park in the north-west corner of
the cadastral plot.
No. of square metres
Approx. 25,000 m² (neurorehabilitation building).
Upcoming procedure
An invitation to tender for the construction of the
neurorehabilitation building will be carried out in the
first half of 2016.
Contents
A new neurorehabilitation building will be
constructed to house the region’s
neurorehabilitation specialists. The building is
intended to include bed wards, outpatient
departments and rehabilitation facilities (both
outdoors and indoors).
In addition, a multi-storey car park, an emergency
power system and refrigeration centre will be built.
Total financial framework
(2013 prices)
DKK 820 million (EUR 109.93 million) (including
multi-storey car park)
Consultants
Client consultant: Rambøll A/S with Friis & Moltke
A/S, as well as Brunsgaard & Laursen
Main consultant for neurorehabilitation building:
AART Architects and Nordic – Office of
Architecture
Sub-consultants: Marianne Levinsen, landscaping;
Harde Larsen, Rådgivende Ingeniører (consulting
15
engineers); Buro Happold, Alectia and Hospitalitet.
Design-build contractor for multi-storey car park: 5E
Byg
Sub-consultants: Grontmij A/S and Christensen og
Co. Arkitekter A/S
General schedule
Neurorehabilitation building
Construction start-up: September 2016
Commissioning: April 2018
Multi-storey car park:
Commissioning: May 2015
16