New York City Transit Coney Island Rail Yard Boiler Plant

New York City Transit
Coney Island Rail Yard Boiler Plant Upgrade
Draft Public Participation Plan
Introduction
New York City Transit (NYCT), an agency of the Metropolitan Transportation Authority
(MTA), is proposing to replace three existing boilers located at the Coney Island Rail
Yard in Brooklyn, New York. The existing dual-fuel fired boilers (natural gas and #2 fuel
oil) are old and beyond repair. In fact, two of the three existing boilers have failed as they
are beyond their useful life, and are inoperable. As a result, the boiler plant is currently
being supplemented by a temporary portable boiler. NYCT would replace the existing
boilers with three new factory-built dual-fuel fired 24.5 million BTU/hour rated boilers (2
operating, 1 spare). The proposed new units have higher energy efficiency, lower
emissions and higher reliability.
The goals of the project are supportive of Mayor Michael Bloomberg’s goals for New
York City outlined in PlaNYC, and include:
x
Decreasing CO2, particulate, and greenhouse gas (GHG) emissions;
x
Improving local air quality; and
x
Achieving energy efficiencies and cost savings.
The project is currently in the process of finalizing the construction contract for the
installation of the new boilers. During the construction period, a 24.5 million BTU/hour
rated temporary boiler and a 32.7 million BTU/hour rated temporary portable boiler
would be used to provide the heat and steam needed at the yard. Once the permanent
boilers are installed and being operating, the temporary and portable boilers would be
shut down and removed from the site. Construction and equipment installation is slated to
begin in mid-2012 with the startup of the new replacement boilers targeted for the Fall of
2012. This Public Participation Plan (PPP) is part of NYCT’s permitting application to
the New York State Department of Environmental Conservation (NYSDEC) to modify
the existing Title V Facility Air Permit to include the operation of the three new
permanent boilers as well as the temporary and portable boilers to be used at the Coney
Island Rail Yard boiler plant during the construction and installation of the new
permanent boilers. In accordance with Commissioner Policy-29 Environmental Justice
and Permitting (CP-29), NYSDEC requires the permit applicant to develop and execute a
public participation plan targeting the local community, and conduct outreach as part of
the environmental permit review process.
In contrast to the existing boilers, which do not have an NOx permit cap, the potential
NOx emissions from the new replacement boilers would be capped to 24.5 tons/year. In
addition, the new boilers will be equipped with low- NOx burners and will comply with
all applicable air quality regulations and requirements. Total CO2 emissions from the new
boilers will be less than the 25,000 metric tons per year GHG reporting threshold, and
much less than the 100,000 tons per year Prevention of Signification Determination
(PSD)/Title V threshold.
Final Draft
~1~
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Public Participation Plan
The draft PPP for this permit application includes a number of activities and tasks that
will be undertaken to inform stakeholders about the proposed project and the Title V
Permit Modification being sought from NYSDEC. This will provide stakeholders access
to information about the project and permit and encourage dialogue.
Task # 1 -- Identify Affected Area
Because of the project’s location (in the existing Boiler House, off of Shell Road
within the larger NYCT Coney Island Rail Yard transit property in Brooklyn), a 1mile radius from the proposed boiler replacement site has been selected in
consultation with NYSDEC staff, to ensure that outreach to an appropriate area and
interested entities (stakeholders) is undertaken. This is shown in Figure 1, attached.
This area will serve as an initial component in identifying stakeholders. Particular
emphasis will be placed on identifying stakeholders representing the area’s minority
and low-income populations for outreach during the public participation process.
Within this 1-mile radius of the proposed project site lies the entire Coney Island Rail
Yard facility, an approximately 1-mile section of the Belt Parkway, and portions of
the following Brooklyn neighborhoods: Homecrest in the northeastern portion,
Gravesend in the northwestern portion, Brighton Beach in the southeastern portion,
and Coney Island in the southwestern portion. South of the Belt Parkway and west of
Ocean Parkway, the Coney Island portion of the study area is largely characterized by
auto-related and parking uses, and residential uses. The Luna Park Houses are in this
area, comprising a 5-building Mitchell-Lama residential cooperative complex of
almost 1,600 apartments, making it one of the largest Mitchell Lama developments in
the state. Additional large tracts of residential uses are located in the southwestern
portion of the study area, including housing operated by the New York City Housing
Authority (NYCHA). NYCT operates a subway along Stillwell Avenue. The
communities of Homecrest, Gravesend, and Brighton Beach are largely residential.
Task #2 -- Identify Stakeholders and Create an Outreach Contact List
Stakeholders who may be affected by the operation of the upgraded boiler plant at the
NYCT Coney Island Rail Yard will be identified. This will be done in coordination
with Community Board representatives and with input from NYCT. It is expected
that the stakeholders for this plan will include, but may not be limited to:
•
•
•
•
•
Final Draft
NYCT employees who work at or visit portions of the Coney Island Rail Yard
facility,
Residents/neighborhood groups who reside or are active in the vicinity of the
proposed project
Community boards, local community and civic organizations, environmental
and business groups, and any entities recommended by these groups
Neighborhood religious establishments
Elected officials
~2~
April 2012
KING S
H WY
21
AV
AV R
RD
E
AV R
W 3 ST
W N AV
HIGH LA
BA
Y
PK
W
Y
1.27.12
N
QU EN TI
AV S
23
AV
PKWY
OC EA N
24
86
BE
NS
ON
MC DONA
LD AV
AV
W 6 ST
AV T
ST
AV
AV U
AV V
25
AV
GR AVESEN
D NE CK RD
AV V
26
AV
AV V
AV
27
AV W
AV
AV X
28
AV
AV
T
4S
HA
RW
AY
E 13 ST
Y
SE
OP
CR
AV Y
AV
AV Z
R
SH O
WY
E PK
ST
BAY 54
GU ID ER
AV
WES T
AV
PED OV PS
W 15 ST
W 10 ST
SE A
B RE
EZ E
C
BE A
BR
IG
P KWY
N
HT O
BR IG
W BR IGHT
ON AV
D AV
MERMAI
V
FA
SU R
OC EA
N
W 12 ST
E AV
W5S
T
Y AV
NE PT UN
CONEY ISLAND AV
E
CR OP S
NE PTUNE AV
HT
ON
11
S
T
W
22
ST
EL L AV
P KWY
ST IL LW
AV Z
OC EA
N
Y4
BA
AV X
SH EL L RD
AV
W 8 ST
BA
TH
W 11 ST
Y
SE
OP
CR
AV
25
CONEY ISLAND AV
AV W
H AV
BOARDWALK E
AV
AL K W
BO AR DW
W 29 ST
Project Site
1-Mile Study Area
0
1,000
Feet
2,000
2000 Census Block Group Boundaries
NYCT BOILER REPLACEMENT TITLE V
Public Participation Plan Outreach Area
Figure 1
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
•
Other appropriate state and local government officials.
A preliminary outreach contact list of stakeholders is being assembled, including
names, addresses, telephone numbers and e-mail addresses (if available) of
individuals and organizations (as described above) with a possible interest in the
proposed project. This list will be updated regularly to include new stakeholders
identified as the public participation process continues. The preliminary outreach
contact list that has been developed to date for this plan is included in Attachment A.
Task #3 -- Prepare Written Information
Written information on the proposed action and the environmental permit review
process will be prepared for posting and distribution. The following written materials
will be prepared and made available to the public as part of this outreach effort:
•
•
•
•
•
•
Project Fact Sheet (An outline of the contents of the Fact Sheet has been
developed, and is included in the draft PPP as Attachment B.)
Information Availability Notices
Title V Permit Modification Application
Draft Title V Modification Permit
Environmental Justice Analysis
Draft Public Participation Plan
Prepared materials will be written in clear, concise language, avoiding legal or overly
technical terminology. Materials will be prepared in English; translation into Spanish
will be undertaken if necessary, to the extent possible and practical.
Task #4 -- Establish Document Repositories/Distribute Project Information
Easily accessible public Document Repositories will be established at locations close
to the proposed project and easily accessible to stakeholders. It is anticipated that
these will include local Libraries and Community Board offices in or near the
outreach area (defined above), as well as at the Coney Island Rail Yard facility office,
and postings on the MTA-NYCT website (http://www.mta.info/nyct). The proposed
locations of these repositories are shown in Attachment C. The availability of any
additional public Document Repositories, if they are established, will be noted on
NYCT website, when they become active.
The repositories will contain a copy of the written information prepared for the
proposed project’s PPP, (as outlined above in Task #3) as well as copies of the permit
applications, and draft permits, once they are available. The contents of the
repositories will be checked and updated regularly to ensure that no documents are
missing. A list of document contents will be prepared and updated, to help keep the
repositories organized.
The locations and web address of the physical and web-based Document Repositories
will be included in the Project Fact Sheet and in any project notices and/or flyers
distributed publicly.
Final Draft
~3~
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
It is envisioned that information will be distributed or made available to NYCT staff
by the following means: i) an official memorandum would be circulated at the Coney
Island Rail Yard facility containing a brief explanation of the project to provide
information to on-site staff; and ii) flyers could be posted in employee meeting and
notice areas. With the implementation of these measures, adequate notification would
be provided to NYCT Coney Island Rail Yard staff to learn about the proposed
project, and thus afford them the opportunity to provide comments.
Task #5 -- Conduct Public Information Meeting/Informational Briefings
One Public Information Meeting will be held at a publicly accessible location in the
outreach area to provide information about the proposed boiler replacement and
upgrade project, and the associated NYSDEC permitting process. In addition, project
information will be sent to elected officials and the Brooklyn Community Boards, to
provide information about the proposed Coney Island Rail Yard Boiler Plant Upgrade
project and the associated NYSDEC permitting process. Stakeholders will also be
invited to the Public Information Meeting and will be invited to provide comments on
project materials and the draft PPP, in writing to a specified NYCT representative.
NYCT and consultant team staff members will be available to receive and answer
questions about the project at the Public Information Meeting and/or at any project
briefings held.
The meeting (and any briefings requested) will be scheduled after consulting
Community Board calendars and with municipal and agency officials. This will help
to avoid conflicts with important meetings or events that are regularly held or already
scheduled within the community. The Public Information Meeting will be held after
the draft permit application has been submitted to NYSDEC for review.
Meeting logistics will be publicized approximately ten (10) days ahead of the meeting
date, in order to give stakeholders reasonable notification.
A general mailing will be prepared for the project for delivery to all interested parties
on the Contact List (see Attachment A). This mailing will include Project Notices
announcing the project’s Public Information Meeting, as well as a copy of the Project
Fact Sheet (written in English and Spanish), which will also be sent to the local
organizations and all other stakeholders identified on the Contact List for posting at
those locations. These Project Information Notices will include:
•
•
•
•
•
•
Final Draft
the name of the project sponsor;
the name and address of the proposed project;
a brief description about the project information available for review;
the description of why the project information is being sent;
the comment period being provided for submitting comments on the project,
and when the comment period will end;
contact information for any questions about the project information, or how
and where to provide comments (written or via website); and
~4~
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Where answers to any questions or comments submitted will be made available, and
approximately by when, after the comment period has concluded.
An agenda will be prepared and distributed when the Public Information Meeting is
held. Attendees will also be informed of where they can obtain answers to any
questions they may have after the meeting has concluded. Outreach documents
related to this boiler replacement and upgrade project will be available at the
following website:
http://www.mta.info/nyct
Task #6 - Prepare Participation Plan Outreach Summary/Certification Document
A written summary of the outreach conducted under the PPP will be prepared and
submitted to the NYSDEC. This report will serve as the participation plan’s
Certification Document, and will include:
•
•
•
•
•
•
•
A summary of PPP milestones, outlining plan implementation;
Methods used to engage the public and solicit outreach;
Time and date of the Public Information Meeting;
Time and date of project informational briefings undertaken (if any);
Any substantive concerns/issues raised during outreach activities or received
during the public comment period from stakeholders or the public at large:
Descriptions of how the issues raised were addressed; and
A description of any unresolved or outstanding issues.
The written Certification Document will confirm that the applicant has complied with
the PPP, and will include a summary detailing the activities that occurred pursuant to
the plan. The Certification Document will become part of the permit application and
will be made available to the public at the document repositories. The Certification
Document will also include several appendices as follows:
•
•
•
•
Final Draft
Copies of written information such as notices, flyers, and briefing invitations;
Copies of meeting agendas
Meeting summary of the Public Information Meetings; and
Names of attendees at the Public Information Meeting and at any other project
informational briefings, if any are held (copies of sign-in sheets).
Ï
~5~
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment A – Preliminary Contact List
COMMUNITY BOARD OFFICES
Brooklyn Community Board #11
2214 Bath Avenue
Brooklyn, NY 11214
Phone: 718-266-8800
Fax: 718-266-8821
Email: [email protected]
Chair: William Guarinello
District Manager: Marnee Elias-Pavia
Brooklyn Community Board #13
1201 Surf Avenue, 3rd Floor
Brooklyn, NY 11224
Phone: 718-266-3001
Fax: 718-266-3920
Email: [email protected]
Chair: Eddie Mark
District Manager: Chuck Reichenthal
Brooklyn Community Board #15
Kingsboro Community College
2001 Oriental Boulevard, C Cluster
Room C124
Brooklyn, NY 11235
Phone: 718-332-3008
Fax: 718-648-7232
Email: [email protected]
Chair: Theresa Scavo
District Manager: Pearl Burg
NEW YORK STATE ELECTED OFFICIALS
Sixth Congressional District, New York
Congressman Gregory Meeks
St. Albans District Office
153-01 Jamaica Avenue, 2nd floor
Jamaica, New York 11432
Tel 718-725-6000 | Fax 718-725-9868
Final Draft
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment A – Preliminary Contact List
Ninth Congressional District, New York
Congressman Robert Turner
Queens Office
82-20A Eliot Avenue
Middle Village, NY 11379
Tel: (718) 426-5000
New York State Assembly District 32
Assemblywoman Vivian E. Cook
Jamaica District Office
142-15 Rockaway Blvd.
Jamaica, NY 11436
718-322-3975
New York State 10th Senate District
State Senator Shirley L. Huntley
District Office
161-10 Jamaica Avenue
Suite 504
Jamaica, New York 11432
Tel (718) 523-3069 | Fax (718) 523-3670
Rosedale-Laurelton Satellite Office
133-24 233rd Street
Rosedale, New York 11422
Tel (718) 949-1601 | Fax (718) 949-1619
New York State Assembly District 29
Assemblyman William Scarborough
Jamaica District Office
129-32 Merrick Blvd.
Jamaica, NY 11434
718-723-5412
New York State 15th Senate District
State Senator Joseph P. Addabbo Jr.
District Office
159-53 102nd Street
Howard Beach, NY 11414
Tel 718-738-1111 | Fax 718-322-5760
New York State 14th Senate District
State Senator Malcolm A. Smith
District Office
205-19 Linden Boulevard
St. Albans, NY 11412
Tel (718) 528-4290 | Fax (718) 528-4898
New York State Assembly District 31
Assemblywoman Michele R. Titus
South Ozone Park District Office
131-17 Rockaway Boulevard
South Ozone Park, NY 11420
718-322-4958
New York State Assembly District 23
Assemblyman Phillip Goldfeder
Ozone Park District Office
108-14 Crossbay Blvd.
Ozone Park, NY 11417
718-641-8755
Final Draft
8th Congressional District of New York
Congressman Jerrold Nadler
Brooklyn Office
445 Neptune Avenue
Brooklyn, NY 11224
718-373-3198
13th Congressional District of New York
Congressman Michael Grimm
Brooklyn Office
7308 13th Avenue
Brooklyn, NY 11228
Tel 718-630-5277 | Fax 718-630-5388
New York State 23rd Senate District
State Senator Diane J. Savino
District Office 2
2872 West 15th Street
Brooklyn, NY 11224-2602
Phone: 718-333-0311
Fax: 347-492-3263
New York State Assembly District 47
Assemblymember William Colton
District Office
155 Kings Highway
Brooklyn, NY 11223
718-236-1598
New York State 27th Senate District
Seat is Currently Vacant
Carl Kruger – resigned
Seat currently empty
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment A – Preliminary Contact List
New York State Assembly District 46
Assemblymember Alec Brook-Krasny
District Office
2823 West 12th Street, Suite 1F
Brooklyn, NY 11224
718-266-0267
District Office
8703 3rd Avenue
Brooklyn, NY 11209
718-680-2845
NEW YORK CITY OFFICIALS & COUNCIL REPRESENTATIVES
Brooklyn Borough President
Honorable Marty Markowitz
209 Joralemon Street
Brooklyn, NY 11201
718-802-3700
New York City Council, District 31
Council Member James Sanders, Jr.
District Office
234-26 A Merrick Blvd.
Laurelton, New York 11422
Tel 718-527-4356 | Fax 718-527-4402
Legislative Office
250 Broadway, Suite 1820
New York, NY 10007
Tel 212-788-7216 | Fax 212-227-1210
Legislative Office
250 Broadway, Room 1816
New York, NY 10007
Tel 212-788-6850 | Fax 212-442-2729
New York City Council, District 32
Council Member Eric Ulrich)
District Office
93-06 101st Avenue
Ozone Park 11416
Tel 718-738-1083 | Fax 718738-1918
Legislative Office
250 Broadway
Suite 1555
New York, NY 10007
Tel 212-788-7069
New York City Council, District 28
Council Member Thomas White, Jr.
District Office
145-40 Rockaway Blvd.
South Ozone Park, New York 11436
Tel 718-843-2735 | Fax 718-845-0817
RELIGIOUS & COMMUNITY ORGANIZATIONS
St Paul's Evangelical Lutheran
2801 West 8th Street
Brooklyn, NY 11224-3603
(718) 266-1831
Contact: Harvey W. von Harten, Pastor
Congregation Meor Hachaim-L
2880 W 12th Street, #8
Brooklyn, NY 11224-2901
(718) 449-1208
Final Draft
Coney Island Congregation
2829 West 16th Street
Brooklyn, NY 11224-2605
(718) 449-4912
Salt & Sea Mission
1530 Mermaid Avenue
Brooklyn, NY 11224-2618
(718) 372-3576
Contact: Debbe Santiago, Pastor
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment A – Preliminary Contact List
Sisters of St Joseph
1840 West 6th Street
Brooklyn, NY 11223-2646
(718) 627-5456
Beach Haven Jewish Center
723 Ave Z
Brooklyn, NY 11223
(718) 375-5200
Horizon Christian Fellowship
2585 West 13th Street
Brooklyn, NY 11223
(718) 714-5433
Contact: John Connors, Pastor
Avenue Z Jewish Center
875 Avenue Z
Brooklyn, NY 11235
(718) 646-9874
Jehovah's Witnesses
2160 West 11th Street
Brooklyn, NY 11223-3529
(718) 372-6526
House of Prayer
170 Avenue T
Brooklyn, NY 11223-3725
(718) 333-2233
Contact: Gannady P. Zavaliy, Pastor
First Korean Church
14 Gravesend Neck Road
Brooklyn, NY 11223-3827
(718) 265-2584
Marlboro Jewish Center
2324 West 13th Street
Brooklyn, NY 11223
Our Lady of Grace Church
430 Avenue W
Brooklyn, NY 11223-5499
(718) 627-2020
Contact: Rev. Thomas F. Leach, Pastor
Congregation Shaare Zion
2022 Ocean Parkway
Brooklyn, NY 11223-4045
(718) 375-3834
Final Draft
Young Israel of Sheepshead Bay
2546 East 7th Street
Brooklyn, NY 11235-6207
(718) 891-6767
Congregation Beth El-Flatbush
2181 East 3rd Street
Brooklyn, NY 11223
(718) 336-1926
Trinity Tabernacle-Gravesend
121 Gravesend Neck Road
Brooklyn, New York
(718) 998-7827
Contact: Rev. Dr. Lucian Gandolfo, Pastor
Congregation Beth Yosef
2108 Ocean Parkway
Brooklyn, NY 11223-4829
(718) 645-0448
Jewish Community Council
2298 West 8th Street
Brooklyn, NY 11223-4555
(718) 373-6161
Al Mustafa Islamic Center
3126 Coney Island Avenue
Brooklyn, NY 11235-6449
(718) 743-6666
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment A – Preliminary Contact List
Universal Foundation Ltd.
2727 Coney Island Avenue
Brooklyn, NY 11235-5004
(718) 332-5775
60th Precinct Community Council
2951 West 8th Street
Brooklyn, NY 11224
(718) 946-3328
Contact: Judd Fischler
Astella Development Corporation
1618 Mermaid Avenue
Brooklyn, NY 11224
(718) 266-4653
Contact: Judi Orlando
Bensonhurst West End Community Council
521 West Avenue
Brooklyn, NY 11224
(718) 946-0234
Contact: Carmine Santamaria
Comprehensive Care Management (CCM)
1519 Mermaid Avenue
Brooklyn, NY 11224
(718) 688-0200
Contact: Inna Goldshmidt
Coney Island Board of Trade
1618 Mermaid Avenue
Brooklyn, NY 11224
tel: (718) 266-4653
tel: (917) 710-1004
Contact: Edwin Cosme, President
Coney Island Community Emergency Response
Team (CERT)
1201 Surf Avenue
Brooklyn, NY 11224
(718) 266-3001
Contact: Charles Reichenthal
Final Draft
Coney Island Chamber of Commerce
1000 Surf Avenue
Brooklyn, NY 11224
(718) 265-2100
Contact: Carol Albert
Friends of the Boardwalk
199 27th Avenue, 1st Floor
Brooklyn, NY 11214
email: [email protected]
Contact: Todd Dobrin, President
Grace Gravesend Athletic Association
430 Avenue W
Brooklyn, NY 11223
(718) 336-7148
Contact: Lou Cornacchia
Jewish Association for Services for the Aged
(JASA) Luna Park Senior Center
2880 West 12th Street
Brooklyn, NY 11224
(718) 996-6666
Contact: Adrienne Sloman
P.R.I.D.E.
PO Box #240-453
Brooklyn, NY 11224
(718) 373-7633
Contact: Georganna Deas, President
Police Service Area #1
Police Residents Council
2860 West 23rd Street
Brooklyn, NY 11224
(718) 265-7313
Contact: Emily Sterling
Youth D.A.R.E.S
2857 West 8th Street
Brooklyn, NY 11224
(718) 996-5551
Contact: John Pasagiannis
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment A – Preliminary Contact List
Urban Neighborhood Services, Inc.
1718 Mermaid Avenue
Brooklyn, NY 11224
(347) 374-2455
-or-
PO Box #423
Brooklyn, NY 11224
(718) 801-1054
Contact: Mathylde Frontus, Executive Director
CIVIC ORGANIZATIONS
Amalgamated Warbasse Houses Inc.
2800 West 5th Street
Brooklyn, NY 11224
718-266-9000
Contact: Thomas Auletti, Acting Property
Manager
Brighton Towers Corporation
50 Brighton 1st Road
Brooklyn, NY 11235
(718) 266-3301
Brightwater Towers
601A Surf Avenue
Brooklyn, NY 11224
(718) 996-1300
Contello Towers 2
2740 Cropsey Avenue
Brooklyn, NY 11214
(718) 265-8625
Harway Terrace
2475 West 16th Street
Brooklyn, NY 11214
(718) 332-0777
Luna Park Housing
2879 West 12th Street
Brooklyn, NY 11224
(718) 266-5400
Contacts: Keith R. Murphy, Board President,
Fikret Deljanin, General Manager
NYCHA – Marlboro Houses
2740 86th Street
Brooklyn, NY 11224
(718) 373-9513
Contact: Victoria Stancil
Trump Village Co-Op Office
2915 West 5th Street, Suite #1
Brooklyn, NY 11224
(718) 946-1860
GOVERNMENT AGENCY
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION (NYSDEC)
Region 2 – Division of Environmental Permits
Contact: Michelle Moore, Environmental Analyst 3
1 Hunters Point Plaza
47-40 21st Street
Long Island City, NY 11101-5407
(718) 482-4900
Final Draft
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment B – Fact Sheet Outline
The following is an outline of the proposed contents of the Fact Sheet to be distributed
for the boiler plant’s Title V facility permit modification, as part of the outreach materials
for the project.
Title of Fact Sheet
We proposed to use:
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Project Fact Sheet
The NYCT Coney Island Rail Yard
A brief description of the rail yard and boiler plant’s purpose will be provided under this
heading.
Issues/Project Goals
This section would provide a brief outline of the issues with the existing boilers, the
project’s overall goals, and how they relate to and support the city-wide PlaNYC goals.
The Solution/Project Benefits
This section will include a brief description of the proposed replacement boilers and any
other related improvements, their proposed locations, and the benefits of operating
them. There will be a graphic showing the proposed site plan.
Public Outreach
This section mentions that this is part of the permit review process, refers to the Public
Participation Plan, indicates where project information is available.
Document Repositories
There will be a special “Information Box” on the Fact Sheet that shows the addresses
and locations of the document repositories for the project. There will also be a line
indicating a NYCT contact and web address for more information.
Final Draft
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment C – Proposed Document Repositories
LIBRARIES
Brooklyn Public Library–Gravesend Branch
303 Avenue X
Brooklyn, NY 11223-5933
718-382-5792
Brooklyn Public Library–Ulmer Park Branch
2602 Bath Avenue
Brooklyn, NY 11214-5502
718-265-3443
Brooklyn Public Library–Coney Island Branch Library
1901 Mermaid Avenue
Brooklyn, NY 11224-2507
718-265-3220
Brooklyn Public Library– Brighton Beach Branch
16 Brighton 1st Road
Brooklyn, NY 11235
718- 946-2917
COMMUNITY BOARD OFFICES
Brooklyn Community Board #11
2214 Bath Avenue,
Brooklyn, NY 11214
Phone: 718-266-8800
Fax: 718-266-8821
Email: [email protected]
Chair: William Guarinello
District Manager: Marnee Elias-Pavia
Brooklyn Community Board #13
1201 Surf Avenue, 3rd Floor
Brooklyn, NY 11224
Phone: 718-266-3001
Fax: 718-266-3920
Email: [email protected]
Chair: Eddie Mark
District Manager: Chuck Reichenthal
Final Draft
April 2012
New York City Transit
Coney Island Yard Boiler Plant Upgrade
Draft Public Participation Plan
Attachment C – Proposed Document Repositories
Brooklyn Community Board #15
Kingsboro Community College
2001 Oriental Boulevard, C Cluster
Room C124
Brooklyn, NY 11235
Phone: 718-332-3008
Fax: 718-648-7232
Email: [email protected]
Chair: Theresa Scavo
District Manager: Pearl Burg
ON-LINE WEBSITE
Outreach documents related to this boiler upgrade and replacement project will be available at
the MTA NYC Transit website:
http://www.mta.info/nyct
Final Draft
April, 2012