The Risk Driver Approach to Project Schedule Risk Analysis A Webinar presented by David T. Hulett, Ph.D. Hulett & Associates, LLC To the College of Performance Management April 18, 2013 © 2013 Hulett & Associates, LLC 1 Risk Drivers Method Agenda Limitations of traditional 3-point estimating Explain “Risk Drivers” approach, start with the risks themselves – One Driver per activity – Multiple Risk Drivers per Activity Correlation is modeled in the Monte Carlos simulation Assess the schedule against CPM scheduling best practice Simple space vehicle development schedule as an example Prioritize risks to schedule Mitigation of high-priority risks © 2013 Hulett & Associates, LLC 2 Limitations with the Traditional 3-point Estimate of Activity Duration Typical schedule risk analysis starts with the activity that is impacted by risks, not the risks themselves – Estimates the 3-point estimate for optimistic, most likely and pessimistic duration – Creates a probability distribution for activity duration – Performs Monte Carlo simulation Which risks cause the most overall schedule risk? These questions are typically answered by: – Sensitivity to activity durations – Criticality of activity durations © 2013 Hulett & Associates, LLC 3 Some Problems with Traditional Approach Can tell which activities are crucial, but not directly which risks are driving Makes poor use of the Risk Register that is usually available Cannot decompose the overall schedule risk into its components BY RISK – Ability to assign the risk to its specific risk drivers helps with communication of risk causes and risk mitigation © 2013 Hulett & Associates, LLC 4 We Propose a Different Approach: Start with the Risks Themselves Drive the schedule risk by the risks already analyzed in the Risk Register For each risk, specify: Starting with the risks themselves gives us benefits – Probability it will occur – Impact on time if it does – Activities it will affect – Links qualitative analysis to the quantitative analysis – Estimates the impact of specific risks for prioritized mitigation purposes – Correlations between activities happen automatically – never have to guess at these coefficients again, never get impossible matrices © 2013 Hulett & Associates, LLC 5 Simple Example of Risk Register Risks Use the Risk Drivers feature in Pertmaster 8 Collect probability and impact data on risks Load the risks Assign risks to schedule activities © 2013 Hulett & Associates, LLC 6 Risk Drivers Mechanics (1) The risk Driver is assigned to one or several activities, affecting their durations by a multiplicative Driver – E.g., the Driver may be .90 for optimistic, 1.0 for most likely and – 1.25 for pessimistic These Drivers multiply the schedule durations of the activities to which they are assigned Risks can be assigned to one or more activities Activity durations can be influenced by one or more risks © 2013 Hulett & Associates, LLC 7 Risk Drivers Mechanics (2) Risk Drivers are assigned a probability of occurring on any iteration. – When the risk occurs, the Driver used is chosen at random from – the 3-point estimate and operates on all activities to which it is assigned When not occurring on an iteration the risk Driver takes the value 1.0, a neutral value When an activity is influenced by more than one risk, their Drivers are multiplied together, if they happen on an iteration © 2013 Hulett & Associates, LLC 8 Risk Driver Probability is 100%, Driver can be + or Entire Plan : Duration 100% 115 90% 109 85% 108 350 80% 106 75% 105 70% 104 300 60% 103 250 55% 102 50% 101 200 45% 101 40% 100 Cumulative Frequency 65% 104 Hits Here the Ranges are based on deviations + and – from the Plan. Probability is 100% 95% 111 400 For the examples we use an activity with 100 days in the schedule 35% 99 150 30% 99 25% 98 100 20% 97 15% 96 50 10% 95 5% 94 0 0% 90 90 95 100 105 110 115 Distribution (start of interval) © 2013 Hulett & Associates, LLC 9 Risk Driver Prob. = 100%, Driver is all Overrun Entire Plan : Duration 100% 130 350 95% 125 90% 122 80% 119 75% 118 70% 117 250 60% 115 200 55% 114 50% 113 45% 112 150 40% 111 Cumulative Frequency 65% 116 Hits Here the Plan is the Optimistic Value. Probability is 100% 85% 121 300 35% 110 30% 109 100 25% 109 20% 108 15% 107 50 10% 105 5% 104 0 100 0% 100 105 110 115 120 , Distribution (start of interval) 125 130 10 Assigning a Probability Less than 100% The essence of a “risk” is its uncertainty in two dimensions: – Uncertainty of its occurrence, specified by a probability – Uncertainty of its impact, specified by a range of durations If the risk may or may not occur, we specify the probability that it will occur – The risk occurs and affects the activities it is assigned to on X% of – the iterations, chosen at random, the multiplicative Driver used is chosen at random from the range of data input by the user On (1 – X)% of the iterations, Driver takes 1.0 value © 2013 Hulett & Associates, LLC 11 Assigning a Probability Less than 100% Entire Plan : Duration Spike contains 40% of the probability Entire Plan : Duration 2000 100% 130 100% 114 95% 123 95% 107 90% 120 90% 104 3500 85% 118 85% 101 80% 116 1600 80% 100 3000 75% 114 75% 100 70% 113 1400 70% 100 1200 Hits 55% 109 50% 107 1000 45% 106 40% 103 800 65% 100 2500 60% 100 55% 100 Hits 60% 110 Cumulative Frequency 65% 111 2000 50% 100 45% 100 40% 100 1500 35% 100 Cumulative Frequency 1800 Spike contains 70% of the probability 35% 100 30% 100 30% 100 600 25% 100 1000 25% 100 20% 100 400 20% 100 15% 100 15% 100 500 10% 100 200 10% 99 5% 100 0 100 0% 100 105 110 115 120 Distribution (start of interval) 125 130 5% 97 0 0% 90 90 95 100 105 110 115 Distribution (start of interval) © 2013 Hulett & Associates, LLC 12 Assigning More than One Risk to an Activity If more than one risk is acting on an activity, the resulting ranges are the multiplication of the percentages This is reality – an activity is often affected by multiple risks Two cases are shown next: – When both risks are 100% likely to occur – When both risks are < 100% likely to occur In each case, the computer simulation creates the uncertainty range on an activity’s duration – it is not estimated © 2013 Hulett & Associates, LLC 13 Parallel and Series Risks – Multiplicative – Used with Risk Drivers (RiskDrivers) Risk 1 1.2 Driver Risk 2 1.05 Driver Use 1.2 Driver, the largest Driver only If these two risks are parallel, they can be recovered simultaneously Risk 1 1.2 Driver Risk 2 1.05 Driver Use (1.2 x 1.05 = 1.26) Driver, multiply the two If these two risks are series, they can not be recovered simultaneously © 2013 Hulett & Associates, LLC 14 Two Risks affect One Activity using Drivers that Occur 100% - placed in Series Entire Plan : Duration 100% 146 260 95% 131 90% 127 240 85% 124 220 80% 123 75% 121 200 70% 119 180 60% 117 160 55% 116 140 50% 115 45% 114 120 40% 112 100 Cumulative Frequency 65% 118 Hits Risks in series, P80 is 123 days 35% 111 30% 110 80 25% 109 60 20% 108 40 15% 106 10% 104 20 5% 102 0 0% 92 100 110 120 , Distribution (start of interval) 130 140 15 Two Risks affect One Activity using Drivers that Occur 100% - in Parallel Entire Plan : Duration 100% 130 95% 125 350 90% 122 85% 121 80% 119 300 75% 118 70% 117 60% 115 Risks in parallel, P80 is 119 days Hits 55% 114 200 50% 113 45% 112 40% 111 150 Cumulative Frequency 65% 116 250 35% 111 30% 110 100 25% 109 20% 108 15% 107 50 10% 106 5% 105 0 100 0% 100 105 110 115 120 125 130 Distribution (start of interval) © 2013 Hulett & Associates, LLC 16 Two Risks with Less than 100% Probability Affecting one Activity – Risks in Series Entire Plan : Duration 100% 144 1800 90% 119 1600 85% 116 80% 114 1400 75% 112 70% 110 1200 60% 107 1000 55% 105 50% 103 45% 101 800 40% 100 Cumulative Frequency 65% 108 Hits The spike at 100 days represents (1) the likelihood that neither risk occurs [60% x 50% = 30%] and (2) the chance that 100 days is picked when one or both occur. 95% 123 35% 100 600 30% 100 25% 100 400 20% 100 15% 100 200 10% 99 5% 96 0 0% 90 90 100 110 120 130 140 Distribution (start of interval) © 2013 Hulett & Associates, LLC 17 Two Risks with Less than 100% Probability Affecting one Activity – Risks in Parallel Entire Plan : Duration 100% 130 95% 122 2200 90% 118 85% 115 2000 80% 113 1800 75% 111 70% 110 1600 60% 107 1400 55% 105 1200 50% 103 45% 101 1000 40% 100 Cumulative Frequency 65% 109 Hits With one parallel risk’s having a minimum range of 100%, it cannot be less than 100 days 35% 100 800 30% 100 600 25% 100 20% 100 400 15% 100 10% 100 200 5% 100 0 100 0% 100 105 110 115 120 125 130 Distribution (start of interval) © 2013 Hulett & Associates, LLC 18 Risk Drivers Model How Correlation Occurs Coefficients are Calculated (1) Risk Probability = .5, Range .95, 1.05, 1.15 Activity 1 Activity 2 Correlation = 100% © 2013 Hulett & Associates, LLC 19 Scatter showing 100% Correlation © 2013 Hulett & Associates, LLC 20 Risk Drivers Model How Correlation Occurs Coefficients are Calculated (2) Risk Probability = .25, Range .8, .95, 1.05 Risk Probability = .5, Range .95, 1.05, 1.15 Activity 1 Risk Probability = .45, Range 1.0, 1.10, 1.20 Activity 2 Correlation = 37% Correlation is modeled as it is caused in the project Correlation coefficients are generated, not guessed © 2013 Hulett & Associates, LLC 21 Scatter showing 37% Correlation © 2013 Hulett & Associates, LLC 22 Sensitivity to the Risk Drivers Risk 1 is more important since it affects both Activity A and Activity B © 2013 Hulett & Associates, LLC 23 http://www.gao.gov/products/GAO-12-120G © 2013 Hulett & Associates, LLC 24 Schedule Check Report in Pertmaster ©(C) 2013 Hulett &Hulett Associates, LLC 2010-2013 & 25 25 Using Acumen FUSE for Best Practices ©(C) 2013 Hulett &Hulett Associates, LLC 2010-2013 & 26 26 Simple 2-Stage Space Vehicle Schedule Software used: Pertmaster v. 8.7 © 2013 Hulett & Associates, LLC 27 Two Types of Risk Inherent variability including duration estimating error – uncertainty – Probability = 100% – Used Quick Risk of -5% and +10%, could be reference ranges for – different types of activities Could use reference ranges that would differ by type of activity Discrete risks derived from Risk Register – Probability < 100% – Summarized from detailed Risk Register – These have a probability of occurring and an impact on specific – activities if they do Parallel to their Risk Register information © 2013 Hulett & Associates, LLC 28 Standard 3-point Range Representing Inherent Variability and Duration Estimating Error Inherent variability and estimating error: Optimistic 5% Pessimistic +10% © 2013 Hulett & Associates, LLC 29 Results with Inherent Variability and Duration Estimating Error Only Spacecraft for PMChallenge 2009 Entire Plan : Finish Date 100% 30 Oct 20 95% 27 Aug 20 400 90% 14 Aug 20 85% 06 Aug 20 350 Deterministic: 13 APR 2020 is 1% 80% 30 Jul 20 75% 24 Jul 20 300 70% 20 Jul 20 60% 10 Jul 20 250 Hits 55% 06 Jul 20 50% 01 Jul 20 200 45% 26 Jun 20 40% 22 Jun 20 150 Cumulative Frequency 65% 15 Jul 20 35% 17 Jun 20 30% 11 Jun 20 25% 08 Jun 20 100 20% 01 Jun 20 P-80 is 30 JUL 20, about 3.5 months later than planned Spread from P-5 to P-95 is 5 MAY 20 to 27 AUG 20 for 3.7 months 15% 25 May 20 50 10% 15 May 20 5% 05 May 20 0 0% 11 Mar 20 15 Mar 20 04 May 20 23 Jun 20 12 Aug 20 01 Oct 20 Distribution (start of interval) © 2013 Hulett & Associates, LLC 30 Risk Analysis on Space Vehicle Project Risk Drivers are from Risk Register Risk Requirements have not been decided Several alternative designs considered New designs not yet proven Fabrication requires new materials Lost know-how since last full spacecraft Funding from Congress is problematic Schedule for testing is aggressive Min Most Likely 95% 105% 95% 100% 90% 103% 95% 105% 100% 100% 90% 105% 100% 120% Max Likelihood 120% 70% 115% 60% 112% 40% 115% 50% 105% 30% 115% 70% 130% 100% Seven risk Drivers have been identified and quantified. Each Risk has probability assigned Five have optimistic ranges possible, two are pure threats © 2013 Hulett & Associates, LLC 31 Risks Assigned to Activities (1) Risk Requirements Not Complete Alternative Designs Possible Requirements Definition FS Preliminary Design FS Final Design FS Fabrication X X Designs Not Proven X New Materials in Fabrication X Lost Know-How X Funding Problematic Test FS Engine X X X Testing Schedule Aggressive X X © 2013 Hulett & Associates, LLC 32 32 Risks Assigned to Activities (2) Risk US Preliminary Design US Final Design US Fabrication US Test Integration Integration Testing Requirements Not Complete Alternative Designs Possible X Designs Not Proven X New Materials in Fabrication X Lost Know-How X Funding Problematic X X X Testing Schedule Aggressive X X X X © 2013 Hulett & Associates, LLC X X 33 33 Results Adding Risk Drivers to the Background Risk Spacecraft for PMChallenge 2009 Entire Plan : Finish Date 100% 08 Mar 22 95% 06 Aug 21 550 90% 16 Jun 21 Baseline 13 APR 20 is only 3% likely 85% 10 May 21 500 80% 07 Apr 21 450 75% 03 Mar 21 70% 05 Feb 21 80th percentile is 7 APR 21, 11.8 months later 60% 22 Dec 20 350 55% 03 Dec 20 300 50% 16 Nov 20 45% 29 Oct 20 250 40% 13 Oct 20 35% 28 Sep 20 200 30% 11 Sep 20 150 25% 31 Aug 20 20% 14 Aug 20 100 15% 28 Jul 20 10% 30 Jun 20 50 5% 13 May 20 0 0% 12 Nov 19 25 Jan 20 12 Aug 20 28 Feb 21 16 Sep 21 Distribution (start of interval) © 2013 Hulett & Associates, LLC 34 Cumulative Frequency 65% 13 Jan 21 Hits Spread P-5 to P-95 is 13May20 to 6 Aug 21, for ~ 15 months 400 Activity Tornado Chart from All-In Simulation Spacecraft for PMChallenge 2009 Duration Sensitivity: Entire Plan - All tasks 00025 - US Fabrication 81% 00011 - FS Fabrication 81% 00028 - Integration 79% 00023 - US Final Design 76% 00009 - FS Final Design 75% 00021 - US Preliminary Design 70% 00007 - FS Preliminary Design 70% 00029 - Integration Testing Risky Activities: Fabrication, Integration, Final Design, Preliminary Design, Testing All are correlated with the finish date > 60% These are activities / paths, NOT RISKS 63% 00026 - US Test 61% 00012 - Test FS Engine 61% © 2013 Hulett & Associates, LLC 35 Risk Driver Tornado from All-In Simulation Risk Factors Driving Project Schedule 6 - Funding from Congress is problematic 4 - Fabricaton requires new materials 3 - New designs not yet proven The main RISK, however, is funding from Congress, which affected all activities in this model. 7 - Schedule for testing is aggressive 2 - Several alternative designs considered 5 - Lost know-how since last full spacecraft This is the main risk to mitigate, if possible 1 - Requirements have not been decided 8 - Cost Risk is based on immature data 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 Correlation © 2013 Hulett & Associates, LLC 36 Contribution of Each Risk to the Contingency (1) Explain the Contingency to the P-80 P-80 Date All Risks In Take Risks Out: 7-Apr-21 Days Saved % of Contingency Specific Risks Taken Out in Order 23-Nov-20 135 Testing Schedule 5-Oct-20 49 New Materials 3-Sep-20 32 Alternative Design 21-Aug-20 13 Requirements 14-Aug-20 7 New Design 6-Aug-20 8 Lost Know How 31-Jul-20 6 38% 14% 9% 4% 2% 2% 2% Uncertainty Natural Variation & Estimating Error Total Contingency 13-Apr-20 109 30% 359 100% Funding © 2013 Hulett & Associates, LLC 37 Contribution of Each Risk to the Contingency (2) 100% 90% Variation:108 Variation:6 :8n:7 n:13 ation:32 Variation:49 Variation:134 80% 60% 50% 40% 30% Variation:50 ariation:3 4 5 3 :11 ariation:45 ia ion:1 20% 10% 0% 19 20 Jan 20 10 Mar 20 29 Apr 20 18 Jun 20 07 Aug 20 26 Sep 20 15 Nov 20 04 Jan 21 23 Feb 21 14 Apr 21 03 Jun 21 © 2013 Hulett & Associates, LLC 23 Jul 21 11 Sep 21 31 Oct 21 20 Dec 21 08 Feb 22 38 Cumulative Probability Graphic of the effect of taking the risks out in order of priority at the P-80 70% Mitigating the Most Important Risk Effect of Partially Mitigating the Risk with the Highest Priority Min Funding from Congress is problematic 90% Most Likely 105% Max 115% Likelihood P-80 Date 70% 7-Apr-21 Mitigation: Situate your suppliers strategically by Congressional District of the members of the Committee. Make the “jobs” case for continuous funding. Impact on the parameters 90% 105% 115% 30% 5-Jan-21 Mitigating the risk is estimated to reduce the probability from 70% to 30% but, if the risk happens, the impact range remains the same. This saves 92 calendar days at the P-80 target level of confidence © 2013 Hulett & Associates, LLC 39 Summary (1) The focus is on the risks, not their impact Risks “explain” the need for a contingency Management appreciates this focus on risks Risk interviews are conducted at 5,000 foot level, where people typically think of risk Interviews go faster, stick to the substance © 2013 Hulett & Associates, LLC 40 Summary (2) Use Risk Register for quantitative analysis Specific risks can be quantified and assigned to schedule activities – Quantification is probability and impact – A risk can affect several activities – An activity can be affected by several risks Risk Drivers can be combined with other more traditional approaches such as 3-point estimates for inherent variability risk, estimating error or for probabilistic branching © 2013 Hulett & Associates, LLC 41 The Risk Driver Approach to Project Schedule Risk Analysis A Webinar presented by David T. Hulett, Ph.D. Hulett & Associates, LLC To the College of Performance Management April 18, 2013 © 2013 Hulett & Associates, LLC 42
© Copyright 2025 Paperzz