OMV, Samsun 870 MW NG CCPP Construction Project, HSE management of entire
construction and commissioning phases on behalf of EPC Contractor, 2010-14 (Client: Power
Projects Ltd. a part of METKA Group)
OMV, Samsun 870 MW NG CCPP Project, HSE expertise service by providing A class H&S
expert, occupational doctor and other health personnel, since 2014 (Client: OMW Samsun
Elektrik Co.)
YENI ELEKTRIK (a UNIT and ANSALDO Venture) Dilovasi 850 MW NG CCPP Construction
Project, HSE expertise service during construction and commissioning phases, Kocaeli, 201214 (Client: EKON Endüstri İnşaat ve Ticaret Co.)
ICDAS Bekirli 600 MW Coal Fired Power Plant Construction Project, HSE expertise service
during construction phase, Biga, 2013-14 (Client: UET Uran Endüstri Tesisleri Co.)
EnerjiSA (Sabanci and EoN Venture), preparation of ‘Explosion Protection Document’ and
‘Process Safety Risk Assessment with HAZOP Method’ for the below mentioned facilities,
2013-14, (Client: EnerjiSA Enerji Üretim Co.)
o
Bandirma 937 MW NG CCPP
o
Kocaeli Kentsa 120 MW NG Cogeneration Plant
o
Adana 120 MW NG Cogeneration Plant
o
Mersin 65 MW NG Cogeneration Plant
o
Canakkale 65 MW NG Cogeneration Plant
EnerjiSA (Sabanci and EoN Venture), preparation of ‘HSE Risk Assessment’ for the below
mentioned facilities, 2013-14, (Client: EnerjiSA Enerji Üretim Co.)
o
Tufanbeyli 450 MW Coal Fired Power Plant Construction Project
o
Sucati 7 MW Hydro Power Plant
o
Kusakli 20 MW Hydro Power Plant
o
Kavsak Bendi 191 MW Hydro Power Plant
o
Yamanli 85 MW Hydro Power Plant
o
Balikesir 142,5 MW Wind Power Plant
o
Canakkale 29,9 MW Wind Power Plant
1
SAMGAZ, Samsun Natural Gas Distribution Facility, HSE expertise service, 2014, (Client:
SAMGAZ Doğalgaz Dağıtım Co.)
ANAR Eğitim ve Danışmanlık Hizmetleri Ltd.Şti.
Tekstilkent Koza Plaza A blok Kat:8 No:30 34235 Esenler/İSTANBUL
T:+90 212 438 46 32 F:+90 212 438 46 25
ETİ BAKIR, Blister Copper and Sulphuric Acid Production Facility, HSE expertise service,
Samsun, 2013-14 (Client: ETI BAKIR Co.)
CENGIZ Energy, HSE expertise service during operation of below mentioned plants, since 2012
(Client: CENGIZ Enerji Co.)
o
Samsun 243 MW NG CCPP
o
Samsun-II 137 MW NG CCPP
CENGIZ Energy, Samsun 610 MW NG CCPP Construction Project, HSE management of entire
construction and commissioning phases on behalf of the Client, 2013-14 (Client: CENGIZ
Enerji Co.)
CENGIZ Energy, Samsun 610 MW NG CCPP Construction Project, HSE expertise service, 201314 (Client: TEST Makina Co.)
CENGIZ Energy, Samsun 610 MW NG CCPP Construction Project, HSE expertise service, 201314 (Client: TEKNOKON Co.)
TANRIVERDI Group, SHERATON Samsun Hotel Construction Project, HSE expertise service,
2013-14 (Client: EGE YAPI Group)
BGM (a Garanti-Koza Venture), Q-HSE system, documentation and implementation solution
partnership, 2014 (Client: BGM Engineering Ltd.)
ATA Energy ( a MITSUBISHI HI ve Urundul Venture), Kirklareli 520 MW CCPP Construction
Project, HSE expertise service, 2014 (Client: SINERGY Construction Ltd.)
AESEntek (Koc Holding and AES Venture), preparation of ‘Explosion Protection Document’
and ‘Process Safety Risk Assessment with HAZOP Method’ for the below mentioned facilities,
2014, (Client: AES Entek Co.)
o
Kocaeli 160 MW NG Cogeneration Plant
o
Bursa 160 MW NG Cogeneration Plant
o
Koc University 2.6 MW NG Cogeneration Plant
TAN ENERGY, Aliaga 9,6 MW Wind Farm Construction Project, HSE expertise service, 2014
(Client: NORDEX Energy Co.)
2
Training courses delivered to the following companies;
o
TAI (Turkish Aerospace Industry) “Accident Investigation, Root Cause Analysis and
Reporting”, Ankara, 2013
o
EnerjiSA Tufanbeyli 450 MW Coal Fired Power Plant Construction Project (EnerjiSA,
SK Engineering, Mitek, OZG, Kalemci, Berksan) “Accident Investigation, Root Cause
Analysis and Reporting”, Adana, 2013
ANAR Eğitim ve Danışmanlık Hizmetleri Ltd.Şti.
Tekstilkent Koza Plaza A blok Kat:8 No:30 34235 Esenler/İSTANBUL
T:+90 212 438 46 32 F:+90 212 438 46 25
3
o
EnerjiSA Tufanbeyli 450 MW Coal Fired Power Plant Construction Project (EnerjiSA,
SK Engineering, Mitek, OZG, Kalemci, Berksan) “Health and Safety Requirements
According to the Turkish Legislation”, Adana, 2013
o
MMO (Chamber of Mechanical Engineers Turkey) “Risk Assessment (Legal Frame, 5
Steps and Methods)”, Ankara, 2013
o
ISTAS, ETI BAKIR 30.000 m3 Ammonia Storage Tank Erection Project,
“ScaffoldingSafety, Scaffolding Erection, Dismantling and Modification”, Samsun,
2013
o
ISTAS, ETI BAKIR Maintenance and repair project, “Scaffolding Safety, Scaffolding
Erection, Dismantling and Modification”, Samsun, 2014
o
YENI ELEKTRIK (a UNIT ve ANSALDO Venture), ESB International, Dilovasi 850 MW
CCPP O&M Phase, “Safe Entry and Work in Confined Spaces”, Kocaeli, 2014
o
EnerjiSA Tufanbeyli 450 MW Coal Fired Power Plant Construction Project (SK
Engineering), “ScaffoldingSafety, Scaffolding Erection, Dismantling and
Modification”, Adana, 2014