60% REVIEW CHECKLISTS

60% REVIEW CHECKLISTS










































Title Sheet
General Layout
Standard Plates
Earthwork Tabulation & Summary
Tabulations
Inplace Utility Tabulation
Inplace Utility Plans
Typical Sections
Standard Plan Sheets
Staging Plans
Alignment Plan
Alignment Tabulation
Topography Plans
Removal Plans
Construction Plans
Intersection Detail
Profiles
Concrete Paving Plan & Details
Bituminous Paving Plan & Details
Superelevation Plans
Retaining Wall Plans
Retaining Wall Profiles
Retaining Wall Tabulations
Noise Wall Profiles
Noise Wall Tabulations
Noise Wall Details
Drainage Plans
Drainage Profiles
Drainage Tabulations
Water Resources Notes
Erosion Control Plans
Attenuator Plan
Traffic Barrier Details
Traffic Control Plan
Striping Plans
Lighting Plans
Signing Plans
Traffic Management System Plans
Signal Plans
Contour Sheets
Matchline Layout
Cross Sections
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Title Sheet
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: General Layout
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Standard Plates
Page 1 of 1

Standard Plates listed in numerical order

Numbers, Letters and Descriptions of Standard Plates match the Standard Plates
Manual

Standard Plates applicable to other groups (Traffic, Signals, Lighting, etc.) are
included

Blank lines provided every 8-10 lines and between 1000 series

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

All text is legible and there is no text on top of text or lines going through text

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)_________________________________________________________
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
Page 1 of 2
60% Plan Review Checklist: Earthwork Tabulation & Summary

Earthwork quantities tabulated by alignment

Earthwork computed by stages, if applicable

Swell and shrinkage factors shown in the balance

Swell and shrinkage factors comply with the recommendations in the soils letter

Earthwork balance includes any excess material that is to be hauled away

Breakdown of granular materials included

Footnote in the common excavation column indicates how much topsoil
excavation, bituminous excavation (less than 6”), rubble, or other material is
included in the common excavation quantity. Or, these various items and
quantities are included in the earthwork balance.

Quantities are accurate from the tabulation to the summary and from the summary
to the balance

If the plan is a metric plan, the metric symbol is in the upper right corner or along
the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Earthwork Tabulation & Summary
Page 2 of 2

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Tabulations

If tabulations are included in the 60% plan submittal, see the 95% Checklist for
the tabulations checklist
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Inplace Utility Tabulation
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Inplace Utility Plans
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Typical Sections
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Standard Plan Sheets
Page 1 of 1

Standard Plans in numerical order

Standard Plans applicable to other groups (Traffic, Signals, Lighting, etc.) are
included

Current sheet only

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Staging Plans
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Alignment Plan
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Alignment Tabulation
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through
text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Topography Plans
Page 1 of 1

30% review comments that were sent to the consultant have been addressed in the
60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Removal items may be included on the Topography Plans
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Removal Plans

Page 1 of 2
The following items are shown and properly labeled:



All roadway alignments (including equations)
At least two stations for each alignment on each sheet
R/W and Easements

Beginning and End of Construction

Scale

North Arrow

Legend which clearly indicates removal items

Removal items included on the Removals tabulation

Coordinate grid ticks and labels (minimum of three per sheet)

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Removal Plans
Page 2 of 2

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Removal items may be included on the Topography Plans
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Construction Plans
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Intersection Details
Page 1 of 1

Use the 30% Plan Review Checklist if Intersection Details were not part of the
30% plan, but are included in the 60% plan

Check to see that the 30% review comments that were sent to the consultant have
been addressed in the 60% plan

Check items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Profiles
Page 1 of 1

30% review comments that were sent to the consultant have been addressed in the
60% plan

Other items that may have been changed or added since the 30% review

Vertical Control note (may or may not have been included in 30% plan)

Subgrade excavation depth and tapers (may or may not have been included in
30% plan)

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)_________________________________________________________
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
Page 1 of 2
60% Plan Review Checklist: Concrete Paving Plan and Details

The following items are shown and properly labeled:








Roadway alignments
(including equations)
______________________________
At least two stations for
each alignment on each sheet ______________________________
Curb and C&G
______________________________
Raised medians
______________________________
Joints
______________________________
Headers
______________________________
Bridges
______________________________
The following items are shown:




Construction notes
on first sheet
______________________________
Uniform panel lengths
______________________________
Pavement thickness
______________________________
Taper rates and pluses
______________________________
Taper rates should be shown as 1:x, not x:1.

Beginning and End of Construction

Roadway and shoulder dimensions

Pavement design complies with the Project Memo, soils letter, and the typical
sections

Panel dimensions

Reinforced panels over culverts (patterned)

Taper lengths computed correctly

Scale
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Concrete Paving Plan and Details
Page 2 of 2

North Arrow

Legend

Coordinate grid ticks and labels (minimum of three per sheet)

Plan Sheet Location box (on projects with complicated plan sheet layouts)

Note(s) referring to details

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.) _________________________________________________________
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
Page 1 of 2
60% Plan Review Checklist: Bituminous Paving Plan & Details

The following items are shown and properly labeled:





Roadway alignments
(including equations)
______________________________
At least two stations for
each alignment on each sheet ______________________________
Curb and C&G
______________________________
Raised medians
______________________________
Bridges
______________________________

Beginning and End of Construction

Roadway and shoulder dimensions

Pavement design complies with the Project Memo, soils letter, and the typical
sections

Taper rates and pluses shown. Taper rates should be shown as 1:x, not x:1.

Taper lengths computed correctly

Scale

North Arrow

Legend

Coordinate grid ticks and labels (minimum of three per sheet)

Plan Sheet Location box (on projects with complicated plan sheet layouts)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Bituminous Paving Plan & Details
Page 2 of 2

Note(s) referring to details

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Superelevation Plans
Page 1 of 1

30% review comments that were sent to the consultant have been addressed in the
60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Superelevation Plan may be included with the Drainage Plan
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Retaining Wall Plans

Page 1 of 1
The following items in the area of the retaining wall are shown and properly
labeled:




Roadways (including
centerline and stationing)
Walks
Paths
Other walls

Beginning and End of Construction

Scale

North Arrow
______________________________
______________________________
______________________________
______________________________
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Retaining Wall Profiles

The following items are shown and properly labeled:









Page 1 of 2
Top of railing (or Parapet)
Top of Retaining Wall
Finished Groundline at
front face
Inplace groundline
Top of footing
Bottom of footing
Any inplace utilities, sewer pipes
or culverts which are to remain
Any utilities, sewer pipes or
culverts that will be installed
________________________
________________________
________________________
________________________
________________________
________________________
________________________
________________________
If not shown in tabulation form, the elevations of the following items should be
shown at each wall joint:





Top of railing (or Parapet)
Top of Wall
Finished Groundline
at Front Face
Top of Footing
Bottom of Footing
________________________
________________________
________________________
________________________
________________________

If not shown in tabulation form, the station of the each joint is shown

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Sheet title at lower right

S.P. number with T.H. designation at lower right
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Retaining Wall Profiles
Page 2 of 2

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line
weight, text size, cells, etc
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Retaining Wall Tabs

Page 1 of 2
If not shown on the profile, the elevations of the following items should be shown
at each joint:





Top of Railing (or Parapet)
Top of Wall
Finished groundline at Front Face
Top of Footing
Bottom of Footing
________________________
________________________
________________________
________________________
________________________

Joint Station

Joint XY coordinates

Panel Height

Panel Length

Concrete quantity for each panel

Reinforcement quantity for each panel

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Retaining Wall Tabulations
Page 2 of 2

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Noise Wall Profiles

Page 1 of 2
The following items are shown and properly labeled:






Top and Bottom of
Noise Wall
Ground Elevation
at face of wall
Inplace Groundlines
Depth of Post Embedment
Any inplace utilities, sewer pipes
or culverts which are to remain
Any utilities, sewer pipes or
culverts that will be installed
________________________
________________________
________________________
________________________
________________________
________________________

Station of each post/joint

Elevations along the top of wall

Every 10th post numbered

Stationing along bottom of profile

Even increment elevations on both sides of sheet

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Noise Wall Profiles
Page 2 of 2

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Noise Wall Tabulations
Page 1 of 2

Post number and station

Ground Elevation

Slope

Top of Wall Elevation

Area

Post Length

Post Embedment

Bottom of Embedment

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Noise Wall Tabulations
Page 2 of 2

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Noise Wall Details
Page 1 of 2

Location of wall alignment in relation to the wall is indicated

Station range that detail applies to, if not the entire wall

Slopes

Width of slopes

Inplace groundline

Limits of excavation

Backfill material

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Noise Wall Details
Page 2 of 2

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Drainage Plans

Page 1 of 3
The following items are shown and properly labeled:









All roadway alignments
(including equations)
At least two stations for
each alignment on each sheet
Walls
Bridges
Paths/Walks
Lakes
Rivers
Environmentally sensitive areas
R/W and Easements
________________________
________________________
________________________
________________________
________________________
________________________
________________________
________________________
________________________

Beginning and End of Construction

Inplace drainage structures, with numbers, and pipes, labeled (only those that
won’t be removed)

Proposed drainage structures, with numbers, and pipes, labeled

Inplace culverts and aprons, numbered and labeled (only those that won’t
be removed)
____________________________________________________________

Proposed culverts and aprons, numbered and labeled

Ponds with Bottom, Normal Water Line and High Water Line data shown
____________________________________________________________

High and Low Point station and elevation shown
____________________________________________________________

Roadway and shoulder dimensions
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Drainage Plans
Page 2 of 3

Direction of surface flow arrows

Riprap locations

Proposed ditch blocks

Note(s) referring to drainage profiles, tabulations and details

Scale

North Arrow

Legend

Coordinate grid ticks and labels (minimum of three per sheet)

Plan Sheet Location box (on projects with complicated plan sheet layouts)

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Drainage Plan s
Page 3 of 3

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Superelevation and Erosion Control information may be shown on Drainage Plan sheets
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Drainage Profiles

The following items are shown and properly labeled:






Elbows
Bends
Reducers
Inplace and Proposed Groundlines
Utilities adjacent to
structures or pipes
________________________
________________________
________________________
________________________
________________________
Pipes are labeled with the following information:





Page 1 of 1
Type
Diameter
Length
Class (if other than class II)
________________________
________________________
________________________
________________________
The following items are accurate when spot-checked:




Structure station and offset
Elevation
Pipe lengths
Grades
________________________
________________________
________________________
________________________

Any inplace structures or pipes are shown dashed

Structure numbers

Pipe diameters, length and class are consistent between profiles and tabulation
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Drainage Tabulations
Page 1 of 2

All information spot-checked

All totals checked for accuracy

Pipe diameters, length and class are consistent between profiles and tabulation

Guide Posts are included at proper locations

Sheet totals and notes correctly transferred to any summary tabulations

Notes which indicate the location of station and offset for aprons, pipes and
structures

Note referring to casting assembly key and summary

At the lower right, list of points found on this sheet

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Drainage Tabulations
Page 2 of 2

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Water Resources Notes
Page 1 of 1

Information agrees with the information provided by the Water Resources section

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Erosion Control Plans

Page 1 of 3
The following items are shown and properly labeled:










All roadway alignments
(including equations)
At least two stations for
each alignment on each sheet
Paths/Walks
Walls
Bridges
Lakes
Rivers
Environmentally sensitive areas
Construction limits
R/W and Easements
________________________
________________________
________________________
________________________
________________________
________________________
________________________
________________________
________________________
________________________

Beginning and End of Construction

Inplace drainage structures, with numbers, and pipes, labeled (only those that
won’t be removed)

Proposed drainage structures, with numbers, and pipes, labeled

Inplace culverts and aprons, numbered and labeled (only those that won’t be
removed)

Proposed culverts and aprons, numbered and labeled

Ponds with Bottom, Normal Water Line and High Water Line data shown

High and Low Point station and elevation shown
____________________________________________________________

Roadway and shoulder dimensions
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Erosion Control Plans
Page 2 of 3

Direction of surface flow arrows

Land feature changes

Riprap locations

Bale checks

Silt fence

Silt fence note (see Sample Plan)

Proposed ditch blocks

Note(s) referring to drainage profiles, tabulations and details

Scale

North Arrow

Legend

Coordinate grid ticks and labels (minimum of three per sheet)

Plan Sheet Location box (on projects with complicated plan sheet layouts)

Note(s) referring to details
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Erosion Control Plans
Page 3 of 3

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Erosion Control information may be shown on Drainage Plan sheets
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Impact Attenuator Plan
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Traffic Barrier Details
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Traffic Control Plans
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Striping Plans
Page 1 of 2

Roadways labeled

Stationing shown

Bypass striping and staged construction striping shown if not included in the
Traffic Control Plan

Scale

North Arrow

Legend

Patterns in legend match the patterns in the plan
____________________________________________________________

If the plan is a metric plan, the metric symbol is in the upper right corner or along
the bottom of the sheet

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Striping Plans
Page 2 of 2

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Striping plans may not be included with the 60% plan
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Lighting Plans
Page 1 of 2

Roadways labeled

Stationing shown

Bypasses and staged construction shown and labeled, if applicable

Check for conflicts between light bases/wiring and drainage structures or utilities

Scale

North Arrow

Legend

Patterns in legend match the patterns in the plan
____________________________________________________________

If the plan is a metric plan, the metric symbol is in the upper right corner or along
the bottom of the sheet

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Lighting Plans
Page 2 of 2

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Lighting plans may not be included with the 60% plan
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Signing Plans
Page 1 of 2

Roadways labeled

Stationing shown

Bypasses and staged construction shown and labeled, if applicable

Scale

North Arrow

Legend

Patterns in legend match the patterns in the plan
____________________________________________________________

If the plan is a metric plan, the metric symbol is in the upper right corner or along
the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Signing Plans
Page 2 of 2

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Signing plans may not be included with the 60% plan
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
Page 1 of 2
60% Plan Review Checklist: Traffic Management System Plans

Roadways labeled

Stationing shown

Bypasses and staged construction shown and labeled, if applicable

Check for conflicts between TMS and drainage structures or utilities

Scale

North Arrow

Legend

Patterns in legend match the patterns in the plan
____________________________________________________________

If the plan is a metric plan, the metric symbol is in the upper right corner or along
the bottom of the sheet

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Traffic Mgmt. Sys. Plans
Page 2 of 2

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Traffic Management System plans may not be included with the 60% plan
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Signal Plans
Page 1 of 2

Roadways labeled

Stationing shown

Bypasses and staged construction shown and labeled, if applicable

Check for conflicts between signals/wiring and drainage structures or utilities

Scale

North Arrow

Legend

Patterns in legend match the patterns in the plan
____________________________________________________________

If the plan is a metric plan, the metric symbol is in the upper right corner or along
the bottom of the sheet

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
60% Plan Review Checklist: Signal Plans
Page 2 of 2

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
Note: Signal plans may not be included with the 60% plan
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Contour Sheets
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
Page 1 of 1
60% Plan Review Checklist: Cross Section Matchline Layout

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc
S.P. Number: ________________________________
Consultant Designer:______________________
Checked By:__________________________________
Date:________________________________________
Mn/DOT DESIGN
60% Plan Review Checklist: Cross Sections
Page 1 of 1

30% Review comments that were sent to the consultant have been addressed in
the 60% plan

Other items that may have been changed or added since the 30% review

Text reads from the right side of the sheet or from the bottom of the sheet

All text is legible and there is no text on top of text or lines going through text

Drawn by: and Checked by: Initials included

File name, plot name and date of plot at lower left

Sheet title at lower right

S.P. number with T.H. designation at lower right

Comparison with Sample Plan completed

Sample Plan Narrative and Checklist reviewed

Complies with CADD Data Standards (i.e. level, line style, line weight, text size,
cells, etc.)
File Path: Mwentwfd056 / mn / PRJ / SQUAD / Documents / PlanCheckList / 60%CheckList.doc